Required Month end process in MTS

Dear All,
Plz. explain me the details for Month end process in Make to Stock (Repititive Manufacturing)
OH Calculation
WIP Calculation
Variance Calculation
Settlement what is entries system will pass and how the system is picking the G/L account or Cost centers
and i have few more doubts life what is the use of
What is PCC
What is Production Version
What is Mixed price costing
What is Preliminary costing
What is Failure Cost how to post and how to analize.
Plz. dont send me any links i already go through it.
Regards
Radha
Edited by: Radha Yandrapu on Sep 15, 2010 10:28 AM
Edited by: Radha Yandrapu on Sep 16, 2010 3:27 AM
Plz. dont send me any links i already go through it.
Moderator: Apparently, not enough, if you are asking about basic concepts

Hi,
Month end process for MTS using Product cost collectors:
In repetitive manufacturing we do the perios end closing for the material.(Product cost collector created for a material). all the costs are collected on the PCC instead of the individual production order.Pls follow the following month end process in rep manufacturing for individual processing.
Overhead calculation- Co42
WIP Calculation- KKAS
Variance Calc-KKS6
Settlement- KK87
The system will pick the GLs for wip and variance settlement based on the assignment we maintain in customising for Line IDs, Assignment and Update in the period end closing activities in SPRO.
PCC- it is a Product cost collector created using a production version, BOM, Routing for the material.
Production version- it is created using either Bom and routing or Plant material combination.
Mixed costing- it is a cost estimate created for a material using various procurement alternatives(based on equivalance nos).
Preliminary costing- it denotes the planned values for a cost object created like production order or product cost collector based on the quantity structure in PP module.
Hope this helps you.
Regards,
Vishnu.
VST IT Projects.

Similar Messages

  • WM-Implem -Physical inventory and Month end process- Need configuration

    Hi
        Iam doing WM implementation,  i need to know what are the configuration required for Physical inventory and
        Month end process .
        kindly suggest me
        With  Regards
        dinesh
    Edited by: code acess on Dec 7, 2011 7:55 AM
    Moderator message:
    Locked. Reason: basic question
    Please search before posting question.
    Edited by: Csaba Szommer on Dec 7, 2011 8:27 AM

    Hi
    There is no standard settings for your requirement. With a help of abaper you need to define an enhancement.
    Regards
    Antony

  • Month end processes

    hello ,
        can somebody kindly lists some generic  month end processed for fi and co , we are not using ex.rates now.
    thnaks very much.

    Hello,
    1. Recurring Documents.
    a) Create Recurring documents
    b) Create Batch Input for Posting Recurring Documents
    c) Run the Batch Input Session
    2. Posting Accruals or Provisions entries at month end
    3. Managing the GR/IR Account-Run the GR/Ir Automatic Clearing
    4. Foreign Currency Open Item Revaluation-Revalue Open Items in AR.AP
    5. Maintain Exchange Rates
    6. Run Balance Sheets –Run Financial Statement Version
    7. Reclassify Payables and Receivables if necessary
    8. Run the Depreciation Calculation
    9. Fiscal Year Change of Asset Accounting if it is year end
    10. Run the Bank Reconciliation
    11. Open Next Accounting Period
    Check out the following link
    http://www.sap-img.com/financial/check-list-for-fi-year-end-closing.htm
    Assign points if useful
    regards
    Genie

  • MM Month end Process

    Hi,
    Could anyone please explain briefly about the MM Month end Process.
    Very Urgent!!!!!!!!11
    Reg,
    Ashok

    Hi
    In order to complete month end process we need to close MM  period
    following are some trnx which we use for month end closing process
    MMRV:You can see which period is open in MMRV and sed to open back period posting for one period.example, if ur period open 12th(december), You can posting in 11th (November) by allowaing back posting.
    MMPV : is used to closed Old period which in turn open new period ( i.e If u close dec period it will open Jan period as current period and Dec will become Previous period)
    All above are related to MM module
    In similar way FI peoples also close or open new periods
    also read following for more info
    http://help.sap.com/saphelp_nw04/helpdata/en/50/dc9e10122211d3a54fdfb7b31fd578/frameset.htm
    Vishal...

  • Daily doing month end process

    Hi
    Is that ok to do the month end process ( WIP calcualation / Variance calculation and settlement )  settlement daily. ( Is there any impact to FI )
    Pls help

    Hi,
    Yes. You can do daily settlement on today's posting date for the Production orders which are technically complete or fully delivered for each day. This will not have any impact on Finance. There shall be no extra entries and no data inconsistencies, etc as you fear.
    Trust this helps much!
    Cheers!

  • Forex Month End Process, Need Steps

    Gurus,
    Need steps for FOREX valuation on month end.
    Kindly, please.
    Thanks.

    Hi
    T-code  FAGL_FC_VAL
    BR Tarik
    read the SAP help:
    Foreign Currency Valuation Locate the document in its SAP Library structure
    Use
    To create your financial statements, you have to perform a foreign currency valuation. This valuation covers the following accounts and items:
    Foreign currency balance sheet accounts, that is, the G/L accounts that you run in foreign currency.
    The balances of the G/L accounts that are not managed on an open item basis are valuated in foreign currency.
    ●     Open items that were posted in foreign currency.
    Open items that are open on the key date are valuated in foreign currency.
    You have the following options for the foreign currency valuation:
    ●     You can perform the valuation in local currency, (company code currency), or a parallel currency (for example, group currency).
    You can also use different valuation methods (for example, lowest value principle).
    If you translate additional currencies from the local currency, foreign currency valuation automatically performs a currency translation according to FASB 52 (US GAAP).
    Caution
    You can only perform a valuation run once for each valuation area for a specific key date.
    Prerequisites
    You have made the following settings in Customizing:
    ●     You have defined exchange rates.
    For more information, see Exchange Rates.
    You have made the settings in Customizing for new General Ledger Accounting under Financial Accounting (New) ® General Ledger Accounting (New) ® Periodic Processing ® Valuate.
    ●     Define Valuation Methods
    You have defined a valuation method here.
    ●     Define Valuation Areas
    Here, you have defined a valuation area and assigned a valuation method to it.
    ●     Assign Valuation Areas and Accounting Principles
    If you are using parallel ledgers, you have assigned to the valuation area an accounting principle that is also assigned to a ledger group.
    The exchange rate differences from the parallel valuation are posted in this valuation area. If you perform a parallel valuation with a different valuation method to the first valuation, you do not have to reverse the postings from the first valuation. This information is then available for subsequent closing operations, for example, Transferring and Sorting Receivables and Payables
    ●     Foreign Currency Valuation ® Prepare Automatic Postings for Foreign Currency Valuation.
    Here, you have defined the expense and revenue accounts for exchange rate differences from valuations. For payables and receivables accounts you must also define the financial statements adjustment accounts.
    Features
    The program Foreign Currency Valuation (New) comprises the following functions:
    Valuation of foreign currency balance sheet accounts
    Valuation of open items in foreign currencies
    ●     Saving the exchange rate differences determined from the valuation per document
    ●     Posting account assignments in valuation documents:
    If you use document splitting, the valuation documents are posted with the account assignments that you have defined as document splitting characteristics in Customizing.
    ○     For balance valuation, you can define additional account assignment characteristics. These characteristics are always updated (even if you do not use document splitting). You define the additional account assignment characteristics in Customizing for foreign currency valuation under Define Additional Account Assignments for Balance Valuation. For more information, see the documentation on this IMG activity.
    ●     Performing the adjustment postings required
    Note
    The following topics describe how to perform foreign currency valuation using the reports, and how to post valuation differences. You can also make this posting manually. From the SAP Easy Access screen, choose Accounting ® Financial Accounting ® General Ledger ® Document Entry ® Valuate Foreign Currency.
    Activities
    To perform a foreign currency valuation, from the SAP Easy Access screen, choose Accounting ® Financial Accounting ® General Ledger/Accounts Receivable/Accounts Payable ® Periodic Processing ® Closing ® Valuate ® Foreign Currency Valuation (New).

  • Settlement of the month end process order KKS1 & C088

    Hello all ,
    we are trying to settle the variance & upadte WIP for the month end but facing some  problems.
    When try to Run KKS1 getting the errors for some ordera as
    Only remaining var. in version 0 - no target costs for 000001003928.
    Should we just ignore these errors & proceed with the settlement which is using Txn CO88.
    Also if I run the CO88,I  hope it just updates the WIP account so whether there is any high risk of running this transaction.
    Any documentaion on CO88 will be helpful  & also if you can explain what is reasons for  the errors on KKS1 then it will be quite helpful .
    Thanks,
    AG

    Hello All ,
    One more question . I have done the variance calculation for my process order via KKS2 but when I run CO88 it does not settle this order . Not sure what is the criteria for order not considered for the settlement.
    Order already has the delivered & Techoed status.
    Thanks,
    AG

  • New GL ...month end processes.....

    If I make the PCA as balancing segment, will the month end open item revaluation will be posted by PCA also?
    Will the BCF will be executed by PCA also?
    If One company code is mapped to one PCA (which is balancing segemnt), what the month end posting willnot be done by PCA?
    Any inputs is appreciated.

    hi maddi,
    Pls check inthe Tcode F.97 for all GL accounts
                                     F.98 for the Vendors
                                     F.99 for the Customer
    enter the Tcode and drill down each and every line item u can find it and it is very usefulll ...
    Hope this helps u and assign the points if helpfull
    Ranjit

  • Automate month-end process using BDC OB52

    Hello All,
    Did anyone work for FI period open/Close automation? OB52 is used for opening and closing of FI posting periods. Did anyone write a BDC for transaction OB52.
    Thanks in advance
    Pavan

    No, but it seems fairly straightforward. Could you be more specific about what you're looking for?
    Rob

  • How I can auto approve pending workflow process, once month end proces

    I have created workflow process for timesheet approval.
    I want to auto approve all pending timesheet (i.e (default notification timeout is 7 days) notification send to approver, but still not approved) in Oracle workflow Process, when Month end process started
    Month end process will initiate a flag in pending timesheet header table with process started

    I am not sure if I understand your requirements completely.
    1) If your requirement is that all the pending timsheets have to be approved by month-end (not really when month-end process starts) then set the Timeout of the notification to Absolute Time of end of that month... so that by the end of the month the background engine will pick it up.
    You may design the approval notification within a Sub-process with RESULT attribute of Approve / Reject. Design a Timeout transition for the Notification Activity within the sub-process that will go to an END activity that has Approve result. Thus once the notification times out, the sub-process will complete with result APPROVED.
    2) One other way is to respond to OPEN notifications using APIs.
    WF_NOTIFICATION.SetAttrText(nid, 'RESPOND', 'APPROVED');
    WF_NOTIFICATION.Respond(nid);
    You should have queried up all OPEN notifications for Timesheet approval and do this in a loop... which could be time-consuming sometimes.
    Thanks

  • Reverse Revaluation Process after month end

    Hi All,
    I want to ask is it a common practice to reverse the revaluation postings done by FAGL_FC_VAL after the month end process?  If so, that means the revaluation process is just giving us a better estimate of the outstanding AR and AP amount in the balance sheet to make it more accurate.  Is this correct?
    Thanks.

    Hi,
    Foreign Currency Valuation is needed for all open items (G/L, A/R and A/P) as per different Accounting Standards so that Balance Sheet of the entity displays correct Profit or Loss for the period.
    However since the items are still open its advisable to reverse the valuation on the 1st day of the next period. That's why in FAGL_FC_VAL, system would posts to Unrealized Exch Gain /Loss Account.
    There is an exception though to the Account with balance in Foreign Currency like Main Bank Account. In this case the difference in Foreign Currency needs to be posted to Exch Gain / Loss Realized Account.
    Once the item gets cleared automatically system posts to Exch Gain / Loss Realized Account.
    Regards,
    Sanjay

  • Regarding Month End reports

    Hello SAP Experts
    I got a requests from SAP user that
    for SAP report (T-Code for report) List of GR IR Balances to be part of the month end processing. Can this report be automatically scheduled as part of month end.

    Hi ,
    Please use see below reprot
    MB5S - Display List of GR/IR Balances
    EWM6 - Reconcile GR/IR Clearing Account
    S_P6B_12000135 - List of GR/IR Balances
    Amd MR 11  to clear any dis cripancey in GR and Clearning is F.13
    Many Thanks

  • Month End Procedure

    Please explain settings for the Month End Procedure
    What are the precautions need to be taken

    Hi,
    Month end processes to be followed:
    Month-End Closing: Checklist
    Assets
    Fixed Assets
    -     Execute the depreciation run and update the batch input session (SAP FI-AA)
    Current Assets
    Inventories
    -     GR/IR clearing account u2013 clarify any differences and correct them if necessary (SAP LO-MM)
    -     Clear the GR/IR clearing account (SAP FI)
    Prerequisite: Accounts have already been maintained by MM
    -     Period closing program (SAP LO-MM)
    -     Settle the work in process (SAP FI-CO)
    -     Post the reconciliation ledger (SAP FI-CO)
    Receivables and Other Asset Items
    -     Check whether all the billing documents have been posted (SAP LO-SD)
    -     Valuate the foreign currency for the open items (SAP FI), see also Payables
    -     Valuate the foreign currency for the balances (SAP FI + SAP FI-TR)
    Accruals and Deferrals
    -     Post accruals/deferrals (SAP FI-TR + SAP FI)
    Liabilities and Owneru2019s Equity
    Accruals
    Payables
    -     Payroll accounting (SAP HR)
    -     Valuate the foreign currency for the open items (SAP FI), see also Receivables
    -     Valuate the foreign currency for the balances (SAP FI + SAP FI-TR)
    Accruals and Deferrals
    -     Post accruals/deferrals (SAP FI)
    Miscellaneous:
    Additional Tasks (SAP FI)
    -     Post accruals/deferrals (SAP FI)
          Check whether the accrual/deferral documents have to be reversed
    -     Carry out recurring entries and update the batch input session (SAP FI)
    -     Reconcile cost of sales accounting/period accounting/profit center ledger (SAP FI/SAP FI-CO)
    -     Close the posting period (SAP FI)
    -     Run the reconciliation program (SAPF190)
    This program checks the documents and transaction figures in the R/3 System. You can only execute this run if you do not intend to carry out any postings for the period, otherwise reconciliation differences will occur. You can schedule the job to run in the background.
    Printing Reports and Notifications:
    -     Balance sheets and P&L statements
    -     Advance return for tax on sales and purchases
    -     INTRASTAT declarations (SAP LO-MM)
    -     Account balances (SAP FI)
    -     Journals (SAP FI)
    Internal Closing (SAP FI-CO)
    Internal order and project-related tasks:
    -     Transfer postings, surcharges, project interest calculation, settlement
    Product and production-related tasks:
    -     Release a standard cost estimate, perform inventory costing, transfer postings, surcharges
    Variance calculation, results analysis, and settlement
    Cost center-related tasks:
    -     Transfer posting, distribution, assessment, activity allocation, transfer key figures, cost center variance, price calculation
    Results-related tasks
    -     Evaluate actual postings, transfer external data, distribution, assessment, transfer balance sheet items to PCA
    Hope this helps
    regards,
    radhika

  • Sales doc items with the status CLSD ARE being selected for month-end

    We are working to improve month-end processing time for Sales Orders  We use SAPKKA12 to set CLSD status on line items
    SAP Help states: be sure that the status CLSD (closed) is set for all sales document items that you do not want to include in the period-end closing process. The sales document items with the status CLSD are then not selected for processing in the period-end closing process. Use report program SAPKKA12 to set the status.
    This use to work (in 4.0). I have been on other projects and just brought back to this after several years (now in 5.0).  Testing today shows that orders with CLSD status are being selected for month-end process.
    Any ideas why this is so?  System is selceting over 300,000 orders when well over half of them are set to CLSD.  I do get a message that the order is not relevant to processing, but selecting the order and logging the message take time. and the logs are VERY long.
    thanks

    Does any one else have this issue  that Sales documents with status CLSD are selected by RA (KKAK)?
    In just one of our jobs, i get this Basic List
    Perform actual results analysis      31273      
    Not relevant                                                 103894
    Error                                                        2306      
    Objects Selected                                    137,473
    75% of the orders are CLSD.  and the system is still counting them. (we do not out put information messages)
    I do understand that the orders are not analyzed,  but all documentaion states that CLSD status is not selected, and in our 5.0 system, they are selected.  In our 4.0 system, they were not selected.
    Does this truely work for anyone in a 5.0 system?
    Thanks
    Althea

  • ICR Process 003 Month-End Cut-off

    We have implemented ICR process 003 in the 5.0 system.  It seems that "posting period" relates to the period that the document was posted in ICR not necessarily to the customer account.  How can we get a good month-end cut-off when new documents are posted all the time.  For instance, when we run FBICS3, FBICA3, and FBICR3 after the new period begins, it will pull in documents created in the new period and all still open before in previous periods.

    Hello Staci,
    The period and year you enter on the selection screen is combined with the fiscal year variant maintained in your process customizing to derive a key date for open item selection. The open items are then selected in the sender system and stored in the year and period specified on the selection screen in the ICR database. This is also explained in the first message that is displayed in the log of data selection.
    Best regards,
    Ralph

Maybe you are looking for

  • Error while deleting loc - Object variable or With block variable not set

    I could not delete some of the existing locations in the HyperionFDM and it results in the error Object variable or With block variable not set. I verified that the Server has the apps and subfolder which is needed for this application \\servername\d

  • Why can't i drag footage onto the timeline?

    Why can't i drag footage onto the timeline? the timeline does not appear active.... Plz help

  • Filtering multi source data in a Dashboard

    Hello, I want to create a dashboard with multi source data (Tables / XML files) Filtering data from one source it's easy, but what I want is to use the same criteria to filter the rest Each (Table / XML file) Will stored in a separate Excel Tab Examp

  • Adobe Illustrator keep crashing after opening

    my Orginal , Uptodate Adobe Illustrtor keep closing after opening it, I cant open anything and do anything I just download the trial and WAS about to buy the product ,,, my pc: Win8.1 8GB ram 2GB GPU 100+ free HDD Space

  • Cube off and on button

    As soon as my Cube shuts off, it starts again immediately. It is very hard to turn on and it is only by playing with the power button that I can get it to turn on every now and then.