Requirement Class 101 and 105

Hi,
In std system settings for requirements class 101 & 105 are kept same. Similarly for the requirement class 103, 106, 107 the settings are kept same (requirements class for planned independent requirement)
Can anybody suggest the reason behind that. Is there any specific reason for creating multiple requirement class for same settings?
regards,
Mohit

Dear Lauliu,
Requirement class 101 - is linked with planning strategy 40 and requirement class 105 is linked with planning strategy 70.
With planning strategy 40 it's a pure make to stock scenario where based on PIR's(planned independent requirements) the system
creates planned orders for the finished products and these can be processed from production perspective without recieveing
any sales order.
With planning strategy 70 it's a planning strategy for planning the components designed for planning the procurement (production
or purchasing) of components by planning the components themselves. This is particularly useful in the following cases:
There is a variety of finished products (possibly with an irregular demand pattern where planning is not possible).
The finished products are consumption-based.
The overall purpose of planning at component level is to procure components to stock (without sales orders) in order to react to
customer demand as quickly as possible.
check and revert back with your queries.
Regards
Mangalraj.S

Similar Messages

  • Help required: class assignment and values for functional location

    Hi All,
    My requirement is to get classification data for a functional location as in IL03.
    Can any one let me know where in the standard program are they getting the assigned classes
    and class values. So that I can use the same logic.
    Thanks.

    FM BAPI_OBJCL_GETDETAIL
    OBJECTKEY                       ?0100000000000011643
    OBJECTTABLE                     IFLOT              
    CLASSNUM                        ZPMI_BLDG          
    CLASSTYPE                       003                
    KEYDATE                         29.07.2009         
    UNVALUATED_CHARS                                   
    LANGUAGE                        EN                 
    Cheers!

  • Mvt type 103 and 105

    Dear all,
    I am doing GRN through 103 mvt type of 100 Qty. But at the time of 105 Mvt type qty found 90 that means 10 Qty still pending in block stock. How to process with 10 Qty in block stock which is due to vendor mistake. Please suggest exact procedure and accounting effect on the same.
    Regards
    Atul

    While posting the document against the movement type 103, no FI documents get generated becasue there is no valuation for the materials at the blocked storage Location. The FI document is generated with the movement type 101 and 105.
    In this case, you can cancel the material document number created by the movement type 103 by 104. Then again you will have to do the GRN in 103. The quantities in the material document number created by 103 movement type can't be modified.
    Secondly, if you have the final GRN against the 103 document, then you will have to return the stock by movement type 122.
    Still any queries, revert back.

  • Required to get class Charateristics and values for an functional location

    Hi ,
       As per the requirement ,i have to read the class characteristics and the corresponding values for an function location.I have functional location number ,and the various class names associated with fn.location. Any pointers would be helpful
    Regards
    Arun T

    FM BAPI_OBJCL_GETDETAIL
    OBJECTKEY                       ?0100000000000011643
    OBJECTTABLE                     IFLOT              
    CLASSNUM                        ZPMI_BLDG          
    CLASSTYPE                       003                
    KEYDATE                         29.07.2009         
    UNVALUATED_CHARS                                   
    LANGUAGE                        EN                 
    Cheers!

  • Help required: Classes and class values for Func Loc

    Dear All,
    I have a requirement to get the classes and values associated with a functional location.
    Any idea how to get this data, as in IL03.
    Thanks,
    nsp.

    Hello nsp,
    You can try to check out the Function module ALM_ME_TOB_CLASSES to see how they fetched class, characteristics and their values.
    You can keep a break-point in this module and run MAM30_031_GETDETAIL and check how we can pass the appropriate values.
    However, above FMs are available from PI 2004.1 SP 14 of release 4.6c, 4.7 and 5.0.
    If you are in ERP 6.0, the FM's are available.
    Hope this helps
    Best Regards,
    Subhakanth

  • Requirement class- consumtion indicator and requirement reduction indicator

    hi
    in DEMAND MANAGEMENT WE CAN SET REQUIREMENT CLASS
    can any one elobrate whats the difference between the consumption indicator and requirement reduction indicator.
    in help i dint get any explanation regarding the indicators which we need to se at requirement class
    in siemens material i got the diff on between but i couldnt understood
    can any experts elobrate the issue.
    the explantion is like that
    consmtion is not the only integartion between actual sales requirements and PIR. reduction of the PIR will also takes place asa result of the sales requirement.
    Reduction is the process of actual reducing the value of PIR and its stored in the system. where as  during  consumtion the actual value stored was not changed, only the quantity passed to planning was lowerd.
    can any body elobrate the above statement
    regards
    sasikanth

    HI
    Consumption indicator
    The PIR are consumed with respectve to sales order
    requirement reduction indicator
    make-to-stock production is reduced by customer requirements which are planned as sale from stock
    -ashok

  • Availability check box at schedule line level and requirement class level

    Hi All
    What is the significance of availability check field at schedule line level and requirement type level.
    If I remove the check box at schedule line level, then there won't be any availability check carried out in the sales order, even though in requirement class it is checked. Is it for doing availability once the requirement is passed to MRP...
    In make to stock scenario, no availability check is active at schedule line level.
    scenario 1. stock is 0 in plant, when i place an order for 10 quantity, does system give any confirmed quantity on so and so date...or the confirmed quantity will be zero or as there is no availability check carried out, it confirms 10 quantity on customer requested delivery date and the time of creation of delivery, it gives an error message stating zero quantity is available. which one is correct in all the above.
    In make to order scenario, no availability check is active at schedule line level.
    order was created for 10 qty, as there is no availability check active, does the system give some date based on the lead times maintained in the material master or not?
    Regards
    Sree

    Hi sreekar
    The significance of availability check at schedule line level  is to determine weather availability check and TOR should be carried out for sales orders  or not. 
    If you remove check box at schedule line level , availability check and TOR wont be  carried out at sales order level.
    Coming to the scenario you said , make to stock , i think the availability check you are using is 01 make it 02. which is planned requirements. and stratergy group as 10. in MRP3 view in MMR. .
    as the availability check u have put 01 & stratergy group as 10 availability check doesnt carry
    coming to the scenario 2  , if the stock is 0 in plant and if you create a sales order, then the confirmed quantity should be 0 and that particular order will go to backorder processing.
    sometimes it  confirms the ordered quantity as the  confirmed qunatity, and it gives a confiremed delivery date on which the stock is confirmed , but that date is a tentative date.
    all these unconfirmed orders will go to backorders. once the qunatity is confirmed automatically , delivery date also will be done
    Coming to scenario 3 , when you create MTO order there will be availability check checked at the schedule line level. can you tell wat is the schedule line you are getting is it CP or ND?
    for schedule lines , ND - no availability check will be there , PD - availability check will be there
    Note: plz check 1st the availability check you have entered in MMR , if it  is 01 make it as 02. and then run these cycles.
    Reward points if useful and if Any queries let me know
    Regards
    Srinath
    Edited by: sri nath on Mar 21, 2008 7:53 PM

  • Requirment class in ECC and APO

    Hello,
    I need to know how requirment class in ECC is t/f to APO.
    For instance if we create a new requirment class ZE. Do we need to create similar ZE check mode in APO.
    Or
    the requirment class will be CIF'd. If yes how. requiremnt class becmes check mode in APO.
    regards
    Pamela

    Hello Brahmankar
    But there are many ways a requirement class gets determined in SD module in ECC. One is the way you have told in T code OPPS.
    but sometimes the requirment class is determined based on  requirment type . requirment type is based on  item category + MRP type .  ( req type=item cat + MRP type ) and then  requirment type is assigned to requirment class. This is how  requirement class gets determined in sales order in ECC.
    So  what if requirment type and requirment class is not in material master and is determined thrugh item cat + MRP type ?
    regards
    Pamela

  • Processing class 59 for /101 and /110 wagetypes

    Hello Gurus,
    Can anyone give some explanation about wagetypes /101 and /110  Processingclass 59 setup. Can these be left to sap standard?. How does these impact Garnishments calculation ? Appreciate your help.

    If this is for US Payroll, PCR UGGR is used to calculate the gross amount for garnishments.
    Regards,
    Howard

  • GR with Excise Capuring and Posting ( Movements 103 and 105 )

    Hi
    We have the requirement like .
    1. we have the Business requirement like GR 103 and 105 movements types .
    our requirement: while doing GR with Movement type 103 will capture the Excise . While releasing Blocked stock to unrestricted will post the excise . please advise me how to configure .
    thanks
    @sakhi

    Hi Sakhi,
    When you post 103 the system takes it as GR blocked stock,not a valuated stock in plant.
    But you can capture excise invoice at the time of 105 --i.e Release blocked stock and Post the same in J1IEX  transaction.
    With Regards,
    Vijaykumar Panchagattimath

  • MIGO with respect to 103 and 105 movement

    Hi,
    Is it possible to have same migo no. in 103 and 105 movement type migo. If yes, what are the spro setting requried.
    Ishu

    dear,
    it is not possible to have two movement types having the same GR no
    again when it comes to 103 and 105 movement
    what is logic for that
    do u accept that 105 u can do only after 103 ?
    what it means ?
    u have to do 103 first then 105
    if u want to do 103 and 105 at a time then what r doing  u are just doing 101 because end result is same.
    clear
    regards,
    snb

  • Abap report103 movement type is done and 105 is NOT done.

    HI,
    Requirement need materials for which 103 movement type is done and 105 is NOT done.
    Scenario: - Material comes in company means we do movement 103 for that. after that we do movt. type 105 for that material. I want those material document list that had 103 but not 105.
    Means material has enters in company but movt. type 105 not done.
    Please advice am abap fresher
    Regards..
    R.Sudhakar

    Is possible Query in sap to get this only 105 not release report ?
    ANS:
    Quary table MSEG,
    Check the table content with BWART = 105
    Get the EBELN Nos.
    Pass the EBELN into EKKO Table, Get the value of Field FRGKE.
    if FRGKE <> 'G'.
    ie. Document not yet released.

  • How do I connect to an SMTP server that requires a username and password?

    Hi,
    I am currently working on a project for university which requires me to send and receive email. I was until this week able to send mail no problem, but now the SMTP server has been upgraded so that each time a mail is sent it requires the username and password.
    Ideally the connection should be made using TLS/SSL, and not use the Authenticator method. I want to pass the username and password directly if possible.
    I've been trying to use the following but have been getting handshake, and other exceptions:
    SMTPSSLTransport smtpSSLtransport = new SMTPSSLTransport(session,
                        new URLName("smtp", smtpHost, port, null-File,
                        "USERNAME", "PASSWORD"));
            smtpSSLtransport.setStartTLS(true);
            smtpSSLtransport.connect(new Socket(smtpHost, port));
            smtpSSLtransport.sendMessage(smtpMessage,                                                     message.getAllRecipients());
            smtpSSLtransport.close();Can anyone correct this piece of code for me or point me in the right direction of what classes and methods I should be using?
    Many thanks in advance,
    Gordon

    I always wonder what misleads people to do things this way.
    Was there some example you saw that suggested that instantiating
    an SMTPSSLTransport was the correct approach? I hope not.
    See the smtpsend.java demo program for how to use SMTP
    authentication. If you need to use SSL, see the SSLNOTES.txt
    file for hints on using the "smtps" protocol. smtpsend.java also
    illustrates use of SSL, but you'll need to fix a bug in it to use the
    correct property names ("mail.smtps.auth", etc.).

  • Purpose of Requirement Class

    What is the purpose of requirement class?

    The requirements class contains all control features for planning such as relevance for
    planning, requirements planning strategy and requirements consumption strategy. In
    addition, it is specified at a global level whether an availability check is to take place for
    the material in the sales and distribution documents on the basis of the ATP quantity
    (ATP = available to promise) and whether requirements are to be passed on. A finer
    degree of control can be obtained for sales documents using the schedule line category.
    Replenishment lead time is only included in the check performed on the basis of the
    ATP quantity.
    Also please check this link: http://wiki.sdn.sap.com/wiki/pages/viewpage.action?pageId=29323
    Regards
    Sai

  • Requirement class MRP control ?

    Hi Gurus,
    i have created a material with strategy 40. first i created sales orders without changing any option in Requirement class. then i run MRP. planned orders are created for sales order.
    after that i changed the requirement class as No MRP and creatred new sales orders when i run MRP The sales orders which i created after changing the Requirement class is getting added to the planned order.
    as the second sales orders should not consider in MRP Why they are gettind added to the planned order.is there any other control that controls the sales order MRP consideration.
    Thanks&Regards,
    Venkat.

    Hi Venkat
    Check the requirement type on the sales order and make sure that your requirement type assigned to the requirement class was selected.
    Also take a look on point 5 of the following document:
    http://scn.sap.com/docs/DOC-50641
    BR
    Caetano

Maybe you are looking for

  • S.M.A.R.T fail on brand new hard drive

    I recently had complete hard drive failure on my iMac and got it replaced this week. Everything is now running perfectly but just now I was checking the system profile and noticed the drive is reporting s.m.a.r.t failure. I checked in Disk Utility an

  • Previews in 3.3

    So what exactly is the change in 3.3 concerning RAW images, previews and the imbedded JPG? In pre 3.3 version you had the option to use the imbedded JPG preview during import while Aperture created its preview to speed things up: So what's different

  • Problem with hyperlink when JEditorPane in JDialog

    This following code works great: import javax.swing.*; import java.awt.event.ActionEvent; * Created by IntelliJ IDEA. * User: ilie * Date: Mar 31, 2005 * Time: 1:21:28 PM * To change this template use File | Settings | File Templates. public class Te

  • Redemtion code not working - what do I do?

    I have bought and downloaded Photoshop elements 13 and now have an activation cod- wich I figure is also my redemtion code? But it is not working and I therefore can not get my serial number - does anyone know how to resolve this?

  • Bank Account tab is disables in supplier site form

    Hi All, we have oracle apps 11i (11.5.10.2). In Supplier Master form, BANK ACCOUNTS tab is disabled at site level right now in AP. How can I enable it ? regards sanjay