Hi,
Even no pegged requirement exist for the Material, System generated requirements for components in MRP run and displays in components Requirement list MD04 - "<b>Material /NProc</b> " in MRP element data column .
I am unable to delete the requirements of dependent requirements of components material.
I will appreciate if any one can guide me to solve this.
RK
Message was edited by: RK Talabathula
Message was edited by: RK Talabathula

hi
Delete the main material if you dont require.
Otherwise you hav to write a ABAP code to trace out the dependent requirements in the related table and delete them all
assign points if useful
regards
Ganesh

Similar Messages

  • Stock Requirement List - MD04 - adding columns in this list

    Dear All,
    I am working on the Stock Requirement list ( transactioncode MD04) and the customer wants to add columns with the fields STPO-DATUV ,date of change of a drawing, and the drawing number with revision level STPO-YY_DZEINR.
    There is a badi MD_ADD_COL_EZPS which provides in adding columns, but according the structures MDPSX , MDEZX and MDSUX there are no fields in thoser structures, which directly match with the required fields; somebody has a clue to help me out and get it working.
    For instance: Vendor- and Customer data  can be added by using the pushbuttons and those fields are available from above mentioned structures.
    Thanks in advance and kindest regards,
    Rene.

    Hi Utpal Mishra
    You guessed correctly. I missed to inform our Strategy. We are using Strategy group  11  Make-to-stock prod./gross reqmts plnning.
    User is not able to do PGI or create delivery. He says I have enough stock in MMBE but why system is not allowing.
    Here there are some pending document like -
    1. Pending sales order
    2. Pending deliveries (picking not done)
    2. Delivery created & Picking Done but PGI not done. These things will have a commitment against the stock. But we are interested in getting these document numbers, so that we can take come action against them.
    MD04 simply shows the mrp element as order / delivery but the document number is not available. How to find these documents.
    Please help. Is there any table or a standard transaction ??
    Thanks

  • Table for Stock Requirement List related information

    Dear Sir,
    We have make-to-order scenario , on receiving the Order from Customer  we first create a Sale-Order for the Ordered Item . Subsequently in MD04 , we find a requirement getting reflected  for the Customer Order .
    For example say the Sale-Order number is S-101 and the Line Item is 10 for the FERT material say FERT-101 having the Order quantity as 1 number .  In MD04 , we find a requirement getting reflected with the following information :
    MRP Element  --> CustOrd
    MRP element data --> S-101 / 00010 / 0001
    Recd/Reqd Qty  -->  1-
    Available Qty  --> 1-
    We need to write a Z program for getting the list of  the requirements against the Customer Order (as shown in MD04) .
    Kindly guide us as which Tables we need to refer for getting the above information pl .
    We assure to award full points for the suggested solution .
    Rgds
    B Mittal

    Hi,
    Pls use below function module, same as you will get Stock Requirement List related information
    MD_STOCK_REQUIREMENTS_LIST_API
    For test, goto SE37 and test it
    Regards,
    Sankaran

  • Stock Requirements List

    Friends,
    When we are using the t-code MD04 to generate the stock requirements list for a material, it is throwing an error "Please maintain version in table T009". Table T009 is the table for fiscal year variants. There are no versions to be maintained there. Also, the fiscal year variant that is assigned to our company code is maintained there. Further, the stock requirement list is being generated for other materials (even those marked for deletion).
    Please advise on how to solve this issue.
    Thanks & Regards,
    Sameer S. Gupte
    Cell: +91 9323274801
    Office: +91 66452730

    Friends,
    The problem was with the material master wherein a different fiscal year variant was maintained in the MRP view (different from the one attached to the company code). Changing the material master has solved this problem.
    Thanks & Regards,
    Sameer S. Gupte
    Cell: +91 9323274801

  • Stock/requirement list at a particular date

    MD04 gives current stock/requirement list and MD05 gives planning result of last MRP run.
    Hoe to see stock/requirement of a particular date

    Dear Harshad,
    As explained there is no standard report to meet this requirement,but stock on a posting date is possible through MB5B.
    If my understanding is correct then this stock/requirements list is a dynamic one(even on a particular date) this list gets updated
    for each fixed/planned- receipts/issues.So on the same day there may be number of updated list.So there cant be only one
    stock/requirements list on a given particular date.
    Correct me if I'm wrong.
    Regards
    Mangalraj.S

  • Sales Order in the Requirements List

    Hello everyone,
    I have a problem with the sales orders which do not appear in TX-MD04 (Requirements List) once they have been partially delivered. In other words, the sales order appear in TX-MD04 before posting the goods issue, but it doesn´t even if it is only partially delivered. The outstanding quantity of the order to be delivered should still appear.
    I would really appreciate any help relating this issue on how to manage it in the customizing.
    Thank you very much to you all in advance.
    Víctor

    Please check in VOV7 for your item category what is maintained for the field "Completion Rule".  It should have been B
    thanks
    G. Lakshmipathi

  • "SubReq" is still available in the stock/requirements list.

    Hi SAP guru's,
             In the subcontracting scenario for our client, the required quantity of child component will be provided to the subcontracting vendor.
    For one particular purchase order,
    Subcontracting PO for parent material "A" - qty 4284
    Child component "B" - qty 24,996 provided to the vendor
    "SubReq" is still available in the stock/requirements list of child component referring to the closed purchase order (delivery and invoice posting completed for full quantity, no open item quantity).
           What could be the reason for this issue and what is the best solution.
    Thanks in advance for your valuable reply.
    Reddy.

    Hi Csaba,
    Thanks for your immediate response to my query.SubReq should not appear in MD04 w/o existing requirement (e.g. PO) as a standard but it is observed for this PO.
    The  OSS note "115899- Correction report for subcotractor requirements" is not giving the direct solution, but the content in this note may be useful to analyse and resolve the issue which we are trying.
    Thanks & Regards,
    Reddy GY.

  • Printing the Collective Stock/Requirements List

    Hey All,
    I'm trying to print out the collective stock/requirements list via the menu path "System -> List -> Save -> Local File" but it is shaded out and i cannot do this, just like SD variants are needed to be maintained in own data for the report VA05 so that layouts can be saved, do we also need some such varient maintained in own data to access this option ?
    Best Regards.

    Dear Danish,
    After executing the Stock/Requirements List in MD04,in the top menu List -
    > variable print --->From
    here you can download into a spread sheet or as a local file or as a word processing.
    Or else you can print from here.
    Now come back with your further queries.
    Dear Vivek, MDLD is to print out the MRP list (which is a static one and stock/requirements list is a
    dynamic one).
    Regards
    Mangalraj.S

  • Different Exception messages in MRP list & Stock Requirement List

    Hello Experts,
    When I run MRP and then look at the stock Requirement List & MRP list for the same material, I see different exception messages in these list.
    I noticed that any of the exception messages in Exception group "7 - Exception during rescheduling" (ie, 10-reschedule in; 15-Reschedule Out; 20-cancel process; 30-plan process according to schedule) is not appearing in the stock requirement list even though they appear in the MRP list.
    Does any configuration affect what message group can appear in Stock Requirement List & MRP list?
    Please advice.
    Regards
    Tom

    Hi Tom,
    For exception message - 62, just do the below checks -
    Some of the reasons as to why you may find this exception message is because the backward scheduling can drive the start date in the past so far that:
    - there is no valid BOM as of that date
    - one or more of the work centers are not valid on that date
    - there is no valid factory calendar on that date
    Check the scheduling formulas in your work centers that are set up, and/or to specify for the material master a fixed lot or a max lot size so that planned orders result with realistic lot sizes.
    Also you can set up MRP to only run on basic dates for your overall run, and to follow up with an MRP run which generates capacity planning only within the planning horizon, such as NETPL.  You would need to configure the planning horizon so that it specifies a time frame over which capacity planning is to be done.
    Also check the note : 88505 - Planned order upload generates exception message 62
    In short, do a thorough check of the parameters maintained to ensure there is no inconsistency in the master data.
    Check & revert.
    Regards,
    Vivek

  • I am unable to upgrade to Mavericks even though I seem to have all the requirements listed by Apple.

    When offered the free upgrade in App Store, I am unable to upgrade to Mavericks even though I seem to have all the requirements listed by Apple.
    Model: MacBookPro 2,2, Processor: Intel Core 2 Duo, Speed: 2,33 GHz, Processors: 1, Cores: 2, L2 Cache: 4 MB, Memory: 4GB
    Bus Speed: 667MHz, Boot Rom Version: MBP22 00A5.B07, SMC Version: 1.12f5.

    10.7.5 is the max for your model. Your mac is one model too old to run anything higher.

  • Stock requirements list issue

    Hi all,
    Pl go through the following issue:
    There is a material B. It is a component of Material A in BOM.  This material A is to be supplied by a vendor by subcontracting.
    There is a subcontracting requiment for some 70,000 pieces for this material B for the past one month .But there is no pegged requirement corresponding to this requirement . So , this stray requirement , which is available in stock requirements list of Material B  is to be eliminated.
    Can you pl suggest some solution?
    Those who can give a probable solution shall be awarded points immediately.
    Edited by: venkateswara rao on Aug 21, 2008 7:52 AM
    Edited by: venkateswara rao on Aug 21, 2008 7:53 AM

    I have gone through the OSS notes and understood that it is a programme error . Hence the inconsistency.

  • Stock requirements list for special stock E

    Hello Experts,
    Is it possible to view sales order stock along with the sales order and the linked PO in Stock requirements list? If so, would it need configuration changes?
    Any input would be rewarded with points.
    Thanks,
    Raj

    Raj,
    Of course.  That is the standard display in MD04 for Make To Order (special stock E).  You can't make it display any other way.
    Regards,
    DB49

  • Require list of all events for Windows Server 2008 Active Directory

    Hi all,
    I require list of all events for Windows Server 2008 Active Directory. Event Log name for Active Directory log is "Directory Service".
    Regards,
    SR

    Hi,
    Thanks for your posting.
    Do you mean you want to list all Active Directory logs into one file named “Directory Services”?
    If that, it’s hard to achieve. There are kinds of Active Directory logs stored in different locations and they have different file formats. It’s hard
    to collect them into one file.
    Active directory records events in the directory services log in Event Viewer. By default, Active Directory records only critical error events. To instruct Active
    Directory to record other events in the directory services log, we need to modify registry.
    For more information please refer to following MS articles:
    Active Directory Diagnostic Logging
    http://technet.microsoft.com/en-us/library/cc961809.aspx
    How to configure Active Directory diagnostic event log
    http://support.microsoft.com/kb/314980
    Lawrence
    TechNet Community Support

  • Question about consignment pick-up and stock requirement list

    Hello,
    why consignment pick-up order is not taking into account as a supply in the stock requirement list?
    Thank you,
    Gunadi

    hi
    if you check the the item category KAN for consign pick up at VOV7, you can find out it is a return from the consignment process.
    so when the materials are coming in to ur plant, it is not a supply. it is your own material coming back to your stock.
    once you do the sales order and PGR( post goods receipt) you can see in MMBE your stock level increases.
    hope it is uuseful to u.
    suresh

  • Could not able to see Subcontracting PO in ME2O requirement list.

    Dear Experts,
    I have a subcontracting PO with Account assiged to the Project. I know as we can not use the 541 O Movement type to provide the components to the to the Sub contracting vendor when the PO is account assined to the Project. But my requirement is only to see My subcontracting PO (Account assigned to Project) in ME2O requirement list. Based on the requirement list I will transfer my stock to vendor sloc with 311q Movt type.
    I have created the PO but could not able to see in ME2O, is anything I have missed to maintain in config or in some othe rplace.
    Regards,
    Cherry K

    Hi Cherryk,
    In case of subcontracting PO with account assignment for Project, components are directly withdrawn from the project stock at the time of the goods receipt. But if you want to withdraw the components from the stock of material provided to vendor then you can set the collective requirement field in Material Master MRP4 view as Collective requirements only (2), then you can use ME2O.
    The collective requirement field has to be set for the components to be provided.
    Regards
    Chandra Shekhar
    Edited by: Chandra Shekhar Singh on Jun 2, 2011 10:05 PM

  • I can't see planned order in Long Term Planning Stock/requirements list.

    Hi
    I am trying to use Long Term Planning in SAP.
    I created scenario dates from 01.03.2011 to 03.09.2011. Between those dates i entered planned independent requirements as 300.
    When i went to Long Term Planning Stock/requirements list, i can see all planned independent requirements but i run Multilevel single-item planning and then when i went to  Long Term Planning Stock/requirements list again, i couldnt see planned order for planned independent requirements.
    So what is the problem? Can anyone help me please?
    Thank you.

    HI
    check the planning scenario in MS31 and the PIR assignment in MS31 also check the plant assignement.
    Check In MD61 you have enter PIRs in simulation version and the same version is to assigned in planning scenario
    Also check T code OPU5 for LTP setting for planned orders
    Regards
    Anupam Sharma
    Edited by: anupam sharma on Sep 3, 2010 2:33 PM