Requirements date for VSF "backdating" itself in two months
Please help me understand this peculiar system behavior.
MD04 routinely displays the plant/materialu2019s planned independent requirement as a u201CVSFu201D having a requirements date of the first work-day of the period. What I cannot explain is why the October 2012 VSF has a requirements date of September 21, 2012. Why would the date not be October 1, 2012? The factory calendar assigned to the plant has October 1, 2012 as a work-day.
Same situation for December 2012. The VSF for December has a requirements date of November 21, 2012.
For the rest of 2012, and for the first three months of 2013, the VSF elements are dated on the first work-day of the month. What would cause the requirements to fall a week and a half early for October and December 2012?
I should add that this peculiarity is not limited to one material. It happens over many materials and across all plants. The common thread among the materials is that we plan them into info structure S608 and then disaggregate among the active warehouses / shipping points.
By the way, I am not very fluent in MRP, so please do not assume that I have ruled out something obvious.
Regards,
zKen
Well, we figured it out. The problem was the fiscal year variant.
A few years ago, we were a nine-to-five, Monday-thru Friday kind of company. As such, the accounting periods were carefully managed so that a period never ended over a weekend or on a holiday. Nowadays, we are a 24-7 operation, and accounting periods correspond to calendar months.
But when we changed over the fiscal year variant, it was only set up thru 2011. 2012 still had the old period strategy.
On the MRP3 tab of the material master record, material/plants are assigned the period indicator u201CPu201D, Period according to fiscal year variant. We forecast by periods in S608.
MRP was just doing its thing and determining requirements according to our accounting periods and setting the requirements date accordingly.
Solution: correct the fiscal year variant out for a few more years. Transport, reload the forecast data, transfer to demand management, and run MRP.
All is well in the stock/requirements list.
Similar Messages
-
Requirements date for VSF -- why not on first of month?
Please help me understand this peculiar system behavior.
MD04 routinely displays the plant/materialu2019s planned independent requirement as a u201CVSFu201D having a requirements date of the first work-day of the period.
What I cannot explain is why the October 2012 VSF has a requirements date of September 21, 2012. Why would the date not be October 1, 2012? The factory calendar assigned to the plant has October 1, 2012 as a work-day.
Same situation for December 2012. The VSF for December has a requirements date of November 21, 2012.
For the rest of 2012, and for the first three months of 2013, the VSF elements are dated on the first work-day of the month. What would cause the requirements to fall a week and a half early for October and December 2012?
By the way, I am not very fluent in MRP, so please do not assume that I have ruled out something obvious.
Regards,
zKenWell, we figured it out. The problem was the fiscal year variant.
A few years ago, we were a nine-to-five, Monday-thru Friday kind of company. As such, the accounting periods were carefully managed so that a period never ended over a weekend or on a holiday. Nowadays, we are a 24-7 operation, and accounting periods correspond to calendar months.
But when we changed over the fiscal year variant, it was only set up thru 2011. 2012 still had the old period strategy.
On the MRP3 tab of the material master record, material/plants are assigned the period indicator u201CPu201D, Period according to fiscal year variant. We forecast by periods in S608.
MRP was just doing its thing and determining requirements according to our accounting periods and setting the requirements date accordingly.
Solution: correct the fiscal year variant out for a few more years. Transport, reload the forecast data, transfer to demand management, and run MRP.
All is well in the stock/requirements list.
Edited by: zKen on Nov 22, 2011 3:27 PM -
How to get the date for the first monday of each month
Dear Members,
How to get the date for the first monday of each month.
I have written the following code
SELECT decode (to_char(trunc(sysdate+30 ,'MM'),'DAY'),'MONDAY ',trunc(sysdate+30 ,'MM'),NEXT_DAY(trunc(sysdate+30 ,'MM'), 'MON')) FROM DUAL
But it look bith complex.
Abhishek
Edited by: 9999999 on Mar 8, 2013 4:30 AMUse IW format - it will make solution NLS independent. And all you need is truncate 7<sup>th</sup> day of each month using IW:
select sysdate current_date,
trunc(trunc(sysdate,'mm') + 6,'iw') first_monday_the_month
from dual
CURRENT_D FIRST_MON
08-MAR-13 04-MAR-13
SQL> Below is list of first monday of the month for this year:
with t as(
select add_months(date '2013-1-1',level-1) dt
from dual
connect by level <= 12
select dt first_of_the_month,
trunc(dt + 6,'iw') first_monday_the_month
from t
FIRST_OF_ FIRST_MON
01-JAN-13 07-JAN-13
01-FEB-13 04-FEB-13
01-MAR-13 04-MAR-13
01-APR-13 01-APR-13
01-MAY-13 06-MAY-13
01-JUN-13 03-JUN-13
01-JUL-13 01-JUL-13
01-AUG-13 05-AUG-13
01-SEP-13 02-SEP-13
01-OCT-13 07-OCT-13
01-NOV-13 04-NOV-13
FIRST_OF_ FIRST_MON
01-DEC-13 02-DEC-13
12 rows selected.
SQL> SY. -
Requirement date for 3 level Component in BOM
Iam having Multilevel Sales order bom
Header material requirement date and receipt date given by system is 23.04.2009
first level assembly requirement date and receipt date given by system is is 07.04.2009
second level assembly is phantom
Third level componant requirement date is 31.03.2009 and receipt date given by system is 19 June 2009 .
Gr proceesing time of 2 days is maintained and no planned delivery time is maintained.
Why Third level componant receipt date given by system is 19 June 2009 ?
Edited by: mayuresh bhurke on Jan 19, 2009 6:31 PMMayuresh,
It seems the 3rd level component has a long planned delivery time in material master. Hence the system has pushed the receipt date forward to 19 June 2009 from 31.03.2009. Please check material master time for the 3rd level component.
Hope this helps.
Thanks,
Ram -
Hi Everyone,
We we create PIR in MD61 by weeks, say plan qty 25 in W38, 2008, the system will automatically assign the requirement date as 2008-09-15 (Monday) in MD04.
Is it possible to change the date to the last day of the week 38... in this case, 2008-09-21..?
Thanks,
BinHi,
It is not possible to set the date to the last day of the week as the requirement date.
If you want every Saturday to be your requirement day, create planning calender with the week starting day as Saturday and assign it in your material master and check up whether it suits with your requirement.
-Thaila Shree -
IPad did not require password for in app purchase after two days
I just made an in-app purchase on my iPad and was not prompted to enter my account password. I checked my settings and it was set to require a password after 15 minutes. The last time I entered my password to make a (free) purchase was two days ago! I've now disabled in app purchases as a precaution.
Is this a bug in iOS 8? It asked for a password every 15 minutes in iOS 7.Even after disabling in app purchases (General > Restrictions) and setting the password requirement to 'immediately', I tried another in app purchase (for a smaller amount) and again it went straight through without asking for a password.
-
Required path for opened pdf document if two Acrobat.exe are associated with it.
Hi,
We are getting two Acrobat.exe in taskmanager for single opened document and we are intercepting windows API. how can we get the opened document's absolute path? or is there any API provided by Adobe to get the absolute path of opened document ?
Thanks
-Dharmendra SinghHi Dharmendra,
For getting the absolute path of opened document, please refer to :
http://forums.adobe.com/message/1162040
Thanks,
Shweta -
Will accepting "extra data for the same price" offer remove "monthly discount" offer?
Yesterday I received an offer saying that I could change my plan and go from the MORE Everything 4GB to 6GB without any cost or contract extension. This seems like a good deal, who doesn't want more data without paying for it? My concern is that the recent monthly discounts Verizon added in December 2014 ($10 for basic phone line and $15 for a smartphone line) will be removed from my plan.
While extra data would be nice, I do not want to essentially pay $25 a month for 2GB bump. Can I keep the monthly discounts totaling $25 and still take advantage of the 4GB to 6GB bump? Have my cake and eat it too?I suggest you be very careful of what Verizon describes on the phone, it may be worth a trip to the store and get everything in writing. In my case the More Everything description given to me was vastly different from what I got.
-
Why am I being billed for a subscription that ended two months ago?
And how may I speak to a LIVE PERSON to resolve this issue?
You may not.
There is no telephone support for itunes.
Live people answer the inquiries via e-mail and express lane. Just because they are not on the telephone does not make them any less "live".
http://www.apple.com/support/contact/ -
Requirement Date of PR for Service Activity
Hello All,
Can any one tell me how to enter the requirement date for service activity?
Scenario is that I don't have budget in current fiscal year, hence; cannot book my commitment. So, I want to book a commitment in future (for next fiscal year). How can I enter requirement date for service purchase requisition?
Thanks in advance.
Warm RegardsThanks for you quick response.
In this case I have to create multiple service activities. Is it possible that I can split service items from one service activity into muliple fiscal years.
For Example: There are three service items in activity XYZ, I require two items in current fiscal year and one item in the next. Please advise...
Regards -
Finish date for Activity to be determined from PO Deleivery date
Hello Friends,
I have the following scenario:
For non stock items, I am generating material requirement in network with item category. Based on my project requirement, I am putting requirement date for the material on "General Data" tab of component overview. However, while releasing PO, delivery date for this material will be based on date agreed by vendor.
I need my material requirement date on "General Data" tab of component overview in network activity to be overwritten by date mentioned in PO.
Similarly in case of stackable item, my activity requirement date need to be overwritten by date purposed in MRP run.
Can anybody help me ?
Thanks and best regards
BharatHello Virencra,
Can you help me by providing steps involved.
thanks and best regards
Bharar -
Component requirement date in subcontracting PO
Hello All,
I have subcontracting PR having delivery date as 26.11.2010 and release date as 17.10.2010 and planned delivery time as 40 days. I change the PR release date to 10.10.2010 and it shows the requirement date for the components as same as 10.10.2010 which is my requirement. But when I convert PR to PO it is showing the component requirement date as 19.09.2010 and release and delivery date same as in PR.
How system is showing requirement date in PO as 19.09.2010? Is some one has any idea?
Mayur PhalakHi,
Can you upload screenshots of what you see in ME53N & ME23N with details as seen in component list & the dates to picasaweb or some portal?
Regards,
Vivek -
Component requirement date in subcontracting case
Hello All,
I have subcontracting PR having delivery date as 26.11.2010 and release date as 17.10.2010 and planned delivery time as 40 days. I change the PR release date to 10.10.2010 and it shows the requirement date for the components as same as 10.10.2010 which is my requirement. But when I convert PR to PO it is showing the component requirement date as 19.09.2010 and release and delivery date same as in PR. I want system should not change the component requirement date.
How system is showing requirement date in PO as 19.09.2010? Is some one has any idea?
Mayur PhalakHi Mayur
The requirement date for component in subcontract is Delivery date of the item minus planned delivery time -This is what SAP library says. But in your case I see a huge difference. Is your PR manually created or MRP generated?
Have you maintained info record? Is planned delivery time is copied from info record? You can see planned delivery time in PO delivery tab. (find out which value has been copied).
As per SAP standard when you press enter button in PO requirement date is redetermined based on planned delivery time in the PO delivery tab. So try giving Planned delivery time in PR or info record to adjust requirement date
Write to me if you are not clear.
Regards
Antony -
hi all,
i'm new to SAP and would like some intrepretation of MD04's requirement date for MRP element PrdOrd. How is this requirement date derive from (formula)? Basic finish date didn't help either. I needed this data to be downloaded into spreadsheet and appreciate if someone can let me know what tcode to use...
thanks!Hi,
MD04 shows the stock/requirement situation (current status), because this is a
dynamic screen.
Reg. prod dates,
for Eg. if we create a finished product (Fert) from a raw material (Roh).
Suppose we give the requirement date as 10/06/07.
The foll. are the diff methods of scheduling.
1. Backward scheduling : System schedules backward from 10/06.
2.Forward scheduling: System schedules forward.
3.Current date: System takes today's date as a prod start date & schedules.
,when you run MRP for 100 nos of Fert.
a planned order is created & a pur req is created for Roh.
For Fert prodn, we have given the machine time in the routings. Assume that it take 16 hours to produce 100 pcs. (8hr/day working).
In back ward scheduling, system will schedule such that the fert prodn should start 2 days ahead of 10/06 & hence schedules the prod start as 08/06.
If the PR/PO processing ,ie delv time is one day, then PR will schedules on 07/06.
This PR is converted in PO.(hence you know the del time here.This is the result of backward scheduling.
If you use current date scheduling.
Suppose today's date is 05/06, system will schedule PR for today & Pl.order on 06/06 & after 2 days prodn will be completed.
Hope this helps.
Pl. Reward if useful.
Regards,
Senthilkumar SD -
Req date for an activity based on planned delivery time of component
Hi Experts
I wish to create activities for purchase and install an equipment.
The procurement activity is assigned with the component.
the planned delivery time is specifed (ex: 100 days)
Based on this value, can i get calculated the requirement date for the activity (Ex: today+100days) in stead of manual specification of date for the corresponding activity?
warm regards
ramSivaHi Ahmed
Thanks for your response. This seems to be good feature.
However, i could not get the date corrected for my activity after applying this function.
I have created an activity with normal duration 1day. For the same activity, i have assigned a compnent which has 100days planned del time.
Then i have used 'Transfer Del time --> duration'. But no change.
Could you suggest me right approach?
warm regards
ramSiva
Maybe you are looking for
-
How do i connect to a wifi network after my time capsule has completed its auto setup.
Let me start by saying I contract overseas currently in Afghanistan. Ok so I have over 10 networks in my area and can not connect to a router with ethernet cable. When it does the auto setup it finds the network sometimes but doesn't stay up long eno
-
Hello. I am having a weird problem when trying to test a movie or publish preview -> flash on mac with Leopard os. The result is a blank movie with the usuall "movie not loaded" if u right click on it and the output returns the "Error opening URL 'th
-
Why does email appear in the draft folder after email is sent
could someone tell me why emails I am sending appear in the draft folder even after the email has been sent and is in the sent folder?
-
OBIEE 11g - Insufficient Privileges. "Access Home Page"
Hi All, We just upgraded 11.1.1.6.0 to 11.1.1.6.5 and also did trhe Active Directory setup. we are getting below error when we login. Please help us to resolve this. Error in login page: Insufficient Privileges. "Access Home Page" Error Details Error
-
Hi Expert, I am using below code for disabling user for from access through Management Studio:- SET ANSI_NULLS ON GO SET QUOTED_IDENTIFIER ON GO CREATE TRIGGER [blocker] ON ALL SERVER FOR LOGON AS BEGIN if app_name() = 'Microsoft SQL Server Manageme