Reschedule of delivery times in delivery processing

Hello!
In the delivery we want the possibility to reschedule the delivery times  when pushing the scheduling button in the header processing tab. At the same time we do not want the delivery to be rescheduled if we change one time (for example the loading time and then save the document. What I can find out is that either the system reschedules at both save and reschedule button by setting Rescheduling field to A or Y in the delivery type or not at all by leaving the Rescheduling field in the delivery type blank..
Is there a way to get both functionalities.
Best regards
/Björn

It landed at East Midlands Airport this morning at 5.38, maybe yours is in the same consignment. Hopefully it will be here today or tomorrow - not sure how quick the turn over is from airport to van and zooming up the motorway to me. Hope they dont take the scenic routes!

Similar Messages

  • How planned delivery time effects delivery creation?

    Dear All,
    Some time before, while placing order thro' CRM, we came across a typical error (hard error).
    "date (11/12/2011) lies afterthe end of validity calendar". 
    we could not place order in CRM but in SAP we could create save the order despite of same error but soft. However system didn't allow to create delivery for same order & same error message populated"
    Later it was found that it is because for material  " Planned Deliv. Time  maintained for say "X "days in material master MRP2 view" & was corrected.
    How planned delivery time effects delivery creation?
    For material even though planned delivery time was maintained as say for 500 days, sales order requested delivery date & delivery date in order schedule line got determined as order date (Considering avaliability of funds & material).
    i.e order date/req. delivery date/delivery date in schedule line are same as date on which order is placed.
    Regards
    Suhas W

    Hi,
    Extended your factory calender in SCA3.
    Regards,

  • Regarding planned delivery time for Subcontracting process

    1.Factory calender is maintained  and assigned to the plant,SUNDAY is
    not working day for Client,so the system is not planning any internal
    activities for SUNDAY,up to here it is fine.
    2.One semi finished material is produced by vendor.i.e.Sub contracting
    process, it takes 2 days to complete.For vendor SUNDAY is not a
    working day.
    3.Planned delivery time is maintained as 2 days ,so that if PO is
    release on MONDAY ,the delivery date on WEDNESDAY.
    4.If  requirement is on MONDAY ,In MRP Run System is generating the
    release date on SATURDAY and delivery date on MONDAY,here system is
    taking the calender days not the factory calender days,Client is
    asking for correct delivery date.
    5.Is there any way to tell the system that SUNDAY is not working day
    for vendor,so that system will generate the release date on FRIDAY
    and delivery date on MONDAY.
    Please give your valuable inputs.

    Hi
    the following link might help you in setting the planned delivery time in your defined calendar, rather than the general calendar days.
    SAP ERP Manufacturing - Production Planning (SAP PP)

  • Creation of SNP PDS using planned delivery time

    Dear Experts,
    How do i control creation of PDS because of operaion generated from planned delivery time,although planed delivery ime is zero.
    the scenario is as follows:
    Material :XXXXX
    Planned Delivery time
    Procurement Type:E
    Plant:XXXX
    in transaction /sapapo/curto_simu: there are two PDS displayed with PDS usage as PDS for Supply Network Planning(SNP)
    the first one is because of operation generated fromm planned delivery time,output qty is the same a s that maintained as base qty in BOM and mode is blank,activity field is even blank.
    the other PDS is created because of the valid production version in R/3.
    Thanks in advance
    Amrish

    Hi Dutta,
    Thanx for a quick revert.
    Yes we are using reciepe and we have a valid PDS being generated because of Production Version.
    The problem lies with the creation of other PDS from planned delivery time whereinplanned delivery time is zero.I want a resolution so as the system doesnot create thses PDS which are invalid in nature.
    These invalid PDS are hamperring result out of SNp optimizer for the reason these are considered in the input log of optimizer.
    Regards,
    Amrish

  • Overruling of planned delivery time in inforecord

    Dear Experts,
    for certain materials we have defined planned delivery Times within the respective material info records.
    This is working as expected.
    However, in certain cases the real delivery time for a material could differ from the one stored in the inforecord (be shorter).
    Is it possible, that the end-user can overrule this planned delivery time during the PO creation, or do we have
    to maintain the info-record for this (keeping in mind, that only as an exception the delivery time should be overruled).
    Thanks for your Support on this and best regards.
    Jan

    Of-course they can change the planned delivery time at the time of PO creation.
    System will fetch the default planned delivery time and delivery date as per defined material master.
    But when you change the planned delivery time (in delivery tab), then system will calculate the delivery date automatically.
    If this will happen very exceptional, then no need to maintain in info record or material master. Just change the planned delivery time at the time PO creation, system will change the delivery date accordingly automatically.

  • Planned delivery time & GR Processing time

    Hi all,
      I would require a clarification on this one,
    Scenario - After an MRP run, the Purchase Requisitions for materials are generated & the order release date is being calculated by subtracting only the planned delivery time from the requirement date. But to the best of my knowledge
    "Purchase Order release date = Requirement date - (Planned delivery date + GR Processing time)"
    Solution required - Is my understanding correct & if so, where should i make the changes to include the GR processing time for the computation of order release date. Is there any other field which i need to add to my PO release date computation. An early response in this regard would be highly appreciated.
    Regards,
    Vivek

    Hi,
    The order release date simply takes the requirement date and subtracts the planned delivery period (as you have indicated).
    But this has ALREADY taken the GRP time into account and so you don't nedd to (and shouldn't) add it in again.
    For example,
    Material A has a Planned delivery period of 10 days and a GRP time of 3 Days. The date that the production order is to be started is 30 July.
    The MRP run sees the requirement date as 30 July but it also sees the 3 days GRP and so it asks for the item to be delivered 3 days prior to this date (27th July).
    The planned delivery period is 10 days and so the PO will need to be created by the 17th July. 
    So the dates are correct and do not need any further changes.
    If you were to take the GRP time off again this would be wrong.
    Steve B

  • GR Processing Time and Delivery Time not coming in CS11 Output screen

    Hi,
    I am executing a BOM explosion report using CS11.
    In the CS11 report output I added columns for GR Time and Delivery Time using change layout option.
    After changing layout when I see the details in columns of GR Time and Delivery Time all the values are ZERO '0' for all the components in BOM.
    I checked the material master for component items and find that in MRP view values are maintained in GR Time and Planned Delivery Time field which are also seen in MARC table.
    I do not know from where CS11 is fetching the values for display of GR Time and Del. Time.
    How can we populate the values in CS11 report out put for GR Time and Delivery Time? Am I missing some master data maintenance apart from Material Master?
    Regards...

    Hi Prasobh,
    I looked at the note 101262 and it seems that it is suggesting us to create a new Z report by copying existing report and then modify the WRITE Bloack in new report to display GR Time and Del. Time.
    Is my understanding correct? If yes can you share with me the steps in some more details then mentioned in note 101262 that I need to follow for addressing this requirement.
    If no can you suggest any solution that you know by which it is possible to include GR Time and Del. Time in CS11 output without Z development.
    Regards,

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

  • Planned Delivery Time of Schedule Line

    Dear Gurus,
    I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
    I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    With Regards.

    I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
    Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

  • Plannned Delivery time not considered while calculating delivery date

    Hi PP Gurus,
    We have a situation is that after MRP run system is not taking into account planned delivery time while calculating delivery dates in schedule lines
    It is taking into account GR processing time.We have GR processing time of 3 days.requirment date is 13.10.2011 & delivery date created by the system is 10.10.2011.
    We have maintained correct master data i.e.Materail Master , Info record & Scheduling agreement.
    Please advice why it is happening & what is the significance of planned delivery time in externaly procured materail with scheduling agrement schedule lines?
    Thanks & Regards,
    Sandesh

    Hi Sandesh,
    Is this happening for particular materials or for all materials
    Couple of checks -
    1) Check with material master changes, might be after MRP run PDT is updated in material master etc ..
    2) Check in OPPQ, for option external procurement , whether scheduling info records/agree is marked or not
    Best Regards
    K.Madhu Kumar

  • PO Delivery time

    Hi gurus,
    Something really strange is going on, when I create manually a PO system should calculate the delivery time based on GR time + planned delivery time + values at vendor level or purchasing organization. I have neither of this values but the vendor delivery time so I want that system adds to todays date this number of days and take it as the planned delivery time, the problem is that system behavies really strange, here is an example of how is populating the dates:
    Planned delivery time 5 days working days in calendar is only from monday to friday, lets say I put the order on March 10 which is thursday I spect delivery date on thursday 17 but system is saying Tuesday 15
    I changed the pln del time to several values to see if there is any patron and I noticed that if I put 2 days system gives monday 14 (cos sat and sun) but if I put 3 day, it also say monday 14th, and if I put 4 days it also gives me monday 14, only when I go for 5 days then system says tuesday 15th, and this is valid with all the numbers I put as delivery time, looks like system is trying to match the last digit of my planned delivery time with the last digits of the day like 14 with the 24th
    I know this sounds silly but it's what I am facing, any ideas or does someone have seen something like this before.?
    I have checked and this happens for all my materials
    PO Created at 10th march
    Pl Del TimDays - PO Del Date
    1- 11th
    2- 14th
    3- 14th
    4- 14th
    5- 15th
    6- 16th
    7- 17th
    8- 18th
    9- 21st
    10- 21st
    11- 21st
    Thanks and regards

    Saturday and sunday are holiday for you, but not for the transporter.
    if goods have been despatched on   friday, they will move on sat and sun as well and reach on time i.e after 5 days.  i.e. 15th.
    the basic concept being that goods(transporter)  will travel/move  on your holidays as well.
    FYI
    Delivery date calculation takes into consideration :
    1) Purchasing processing time in the Plant parameters in the customization and is calculated based on the Factory calendar days.
    2) Planned delivery time maintained in material master  and is calculated based on Normal calendar days
    3)GR Processing time Maintained in Material master record, calculated based on Factory calender.

  • PO delivery time going wrong very strange

    Hi gurus,
    Something really strange is going on, when I create manually a PO system should calculate the delivery time based on GR time + planned delivery time + values at vendor level or purchasing organization. I have neither of this values but the vendor delivery time so I want that system adds to todays date this number of days and take it as the planned delivery time, the problem is that system behavies really strange, here is an example of how is populating the dates:
    Planned delivery time 5 days working days in calendar is only from monday to friday, lets say I put the order on March 10 which is thursday I spect delivery date on thursday 17 but system is saying Tuesday 15
    I changed the pln del time to several values to see if there is any patron  and I noticed that if I put 2 days system gives monday 14 (cos sat and sun) but if I put 3 day, it also say monday 14th, and if I put 4 days it also gives me monday 14, only when I go for 5 days then system says tuesday 15th, and this is valid with all the numbers I put as delivery time, looks like system is trying to match the last digit of my planned delivery time with the last digits of the day like 14 with the 24th
    I know this sounds silly but it's what I am facing, any ideas or does someone have seen something like this before.?
    I have checked and this happens for all my materials
    PO Created at 10th march     
    Pl Del TimDays -     PO Del Date
    1-     11th
    2-     14th
    3-     14th
    4-     14th
    5-     15th
    6-     16th
    7-     17th
    8-     18th
    9-     21st
    10-     21st
    11-     21st
    Thanks and regards
    Edited by: Julio on Mar 11, 2011 7:19 AM

    Saturday and sunday are holiday for you, but not for the transporter.
    if goods have been despatched on   friday, they will move on sat and sun as well and reach on time i.e after 5 days.  i.e. 15th.
    the basic concept being that goods(transporter)  will travel/move  on your holidays as well.
    FYI
    Delivery date calculation takes into consideration :
    1) Purchasing processing time in the Plant parameters in the customization and is calculated based on the Factory calendar days.
    2) Planned delivery time maintained in material master  and is calculated based on Normal calendar days
    3)GR Processing time Maintained in Material master record, calculated based on Factory calender.

  • Revenue recognition at the time of Delivery - COPA

    Dear Gurus,
    Our sales cycles are bit different than the standard sales process.
    In one of the sales cycle the business does the Billing first and delivery later and the revenue recognition should happen at the time of delivery not billing.
    How do I achieve the same in COPA data flow and is this a reason why I should activate account based copa?
    Regards
    Roy
    Edited by: roy001 on Mar 27, 2011 8:03 PM

    Hi
    Thank you for you comments.
    Our business scenario is car sale- The car dealer looks into portal(called dealer portal) and checks the availability of a car.
    Once the dealer makes the car selection, he then places an purchase order to the car manufacturer.
    Based on the order the car manufacturer asks for the full payment from the dealer. After receiving payments, the car manufacturer delivers the car.
    Therefore the invoice is raised before delivery.
    The problem that we have in the above scenario is the COPA value flow. How do I flow the values into copa?
    Any input?
    Many thanks.
    Regards
    Roy

Maybe you are looking for