Rescheduling horizon impact on net requirement calculation

Dear MRP experts ,
What is the impact of Recrudescing horizon on net requirement calculation .
Regards
Sasikanth

Dear Sashikant,
The rescheduling check is used to change the dates of already existing firmed receipts not planned on the same day as the requirement to suit the requirement date.
If you look at MD04, the rescheduling date is based on the Stocks Requirement date. 
In the net requirements calculation, the system checks whether warehouse stock or firmed receipts are available to cover requirements. If a material shortage exists, the system usually creates a new procurement proposal.
Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
hope it helps. please revert back.
Regards,
Alok Tiwari

Similar Messages

  • MRP Net Requirements Calculation

    Hi Guys:
    I defined a Planning Horizon of 40 days, for Example if  today is the start date Since Planning horizon is 40 days (01/30/2012).
    Vendor Lead time = 2months
    Purchase order to vendor with Delivery Date (12/20/2011)  : 5000 Pc
    Purchase order to vendor with Delivery date ( 03/04/2012): 6000Pc
    Onhand Inventory = Zero
    So i have Sales order for 10000 with Delivery Date ( 12/28/12) with in the Planning horizon.So when I run MRP using MD02 ,
    Does the system consider Purchase orders with delivery dates  that are outside planning horizon into the net requirements calculation?
    thanks for the help.
    Kodali

    dear friend,
    as far as i know the available stock is calculated as follows:
    plant stock
    safety stock
    +
    receipts (pur.orders, prod. ordersfirmed proc. proposals)
    requirements quantity (say, PIRs, mat. reservations,...)
    =
    available stock
    shortage occurs if available stock is negative, that is, the requirement quantities are greater than expected receipts and stock quantity.
    so, system specifies the date of the issue (for example, customer requirement, planned independent requirement, reservation, forecast requirement) as the requirements date.
    regards,

  • Net requirement calculation in MRP

    Hi Gurus,
    Is there any way we can exclude Created Purchase order ( Not yet released ) in MRP run for the Net req calcualtion . ( pl suggest other than exit )
    Regards,
    Prasanna

    Hi prasana
    Net requirement calculation in MPR will include firmed receipts. ( P.O.). You can only block what are all given in plant parameter.
    We can exclude in Availability Check, in scope of Availability check setting.
    Regards
    J. Saravan

  • Net requirement calculation for Sales Order

    Dear Experts,
    I have configured a strategy comprising both( KE,040) and (LSF and 100), say the strategy is Z0.But the system is not doing net requirement calculation for the dependent requirement(always proposing Pr Req though there is stock).Checking group and checking rule, I have created like the standard PP order.Will anybody Pl. guide me regarding this?
    Regards
    Reshmi

    Hi,
    1. The MRP group or the strategy group in the MRP view of the material master record determines what requirements type is used.
    If you have not specified this information, the requirements type will be selected through the item category of the sales order item and the MRP type in the MRP view of the material master record.
    If you have maintained both an MRP group and a strategy group, the system uses the strategy group (precedence to strategy group).
    You can enter the strategy group directly in the MRP view. If you have specified a strategy group, you do not need to enter an MRP group.
    The configured Strategy group need to be copied from a standard Strategy and even if you group many Strategies(Max 7) you ned to check the req Type assigned to it .
    2. The item category is derived from the item category group in the Sales view of the material master record and from the order type of the sales document. Together with the MRP type in the MRP view of the material master record, the item category determines what requirements type is selected. The MRP group in the material master record is irrelevant here.
    The advantage of this method is that the selection of the requirements type depends on the business process (such as quotation, sales order, or repair).
    All the above Points need to checked in your case
    Pavan

  • Net requirement calculation

    Dear Gurus
    In Net requirements calculation, Safety Stock, Recipts (Purchase Orders, Production Orders, Firmed Procurement Proposals), Requirement qty(Pir, Customer requirements, Material reservations) are considerd
    In My Situvation, I want to exclude considering Safety stock while doing net requirements calculation
    Kindly tell me the setting i have to do
    regards
    palaniappan

    Dear Planiappan,
      In IMG Production + Material Requirements Planning + Planning + MRP Calculation + Stocks + Define Safety Stock Availability maintain 100% in AvSafetySt field. So in planning your 100 % safety stock will be considered.
    Regards
    Sunil Kumar

  • Excluding Stock From Net Requirement Calculation in PPDS

    Dear All,
    We can exclude stock on hand from Net Reuirement Calculation in ECC MRP by selecting Strategy 11 ( Gross requirement Plannung). Is there any Functionality like this in APO PPDS or SNP to exclude the Stock.
    Regards
    Sunil Kumar

    Hi,
              Its possible in SNP, try modifying stock on hand macro in planning book and overwrite initial column value to zero. hope this helps.
    Regds,
    Prasad

  • MRP Net Requirements calculation in External procurement Vs STO

    Hi gurus,
    Lets say I have a FG 1234 which has raw component 9999.
    Case1:
    Setting for 9999 is externally procured.
    I have a stock of 50 pc for 9999.
    I got order for 60 pc for FG 1234.
    so system will only create purchase reks for 10 pc of 9999 as it already sees 50 pc in stock.
    Case 2:
    Setting for 9999 is externally procured but from one of our own plant (Using SPK 40)
    I have a stock of 50 pc for 9999.
    I got order for 60 pc for FG 1234.
    will system create STR for 10 pc of 9999 as it already sees 50 pc in stock? or will it create STR for 60 pc without checking stock in the ordering plant?

    >
    dorian661 wrote:
    SPK 70 will not create an STR. Stock of 9999 will be checked in supplying plant. In case there is a shortage, a procurement proposal will be created against the dependent requirement here. Stock is not checked in ordering plant. You will notice that dependent requirements for 9999 will be seen in the supplying plant.
    Dorian,
    Thanks for the reply. so are you saying that in SPK70
    In ordering plant - MRP will not look at the stock situation for that material
    In supplying plant - system will check stock requirement and create dependent requirement for the shortage amount
    and in spk70 case, against what element is the delivery done to the ordering plant? in spk40 delivery is done against STO.
    Thx

  • Net requirement calculation considering stock ( Strategy 52 )

    Hi All,
    we are using the planning strategy 52 for process industry and according to the standard functionality the stock of finished product will NOT be considered when MRP run and consumption.
    For various reason like customer return we might have the stock of FG. when forecast is finalized and PIR is build in demand management MRP will generate the planned order (type VP) based on the consumption logic. but if stock exist system will not consider it and continue to generate the dependent requirements for the raw material. this is really not acceptable by my client. we want the MRP run considering the stock of FG whensystem generates planned order for PIR.
    Is there any other way to fix this issue?
    we try to use user exit and set consumption indicator 4 for requirement type of VSE.but we failed. the answer is PIR ONLY consumes the requirement elements. Stock somehow a receipt element.
    any pointer is highly appreciateed.
    Reagrds,
    Mao Ye
    Edited by: Mao Ye on Apr 7, 2008 5:38 PM
    Edited by: Mao Ye on Apr 7, 2008 5:41 PM
    Edited by: Mao Ye on Apr 7, 2008 5:43 PM

    Dear,
    Stg 52, will create planned order equivant to the PIR created. and when sales order is created, the planned order is created.
    Hence the wayout is use stg 40. this will suit your requirement, create PIR and run MRP. Planned order is created.
    Do not convert the planned order to production order and give this autjorization to one who can take decision in shopfloor and coordinate.
    You can also use stg 74 ...just see the help link
    http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm

  • MRP-Rescheduling Horizon

    Hi Experts,
    Could u please, explain what is Rescheduling horizon (OMDQ)?
    In OMDQ , if I change planning horizon to 999 days from 100 days.What will be the effects of it?
    Thanks in advance
    Regards,
    jay

    Dear,
    The rescheduling horizon is the period in which the SAP System checks whether the existing dates still suit the requirements situation for receipt elements that can no longer be automatically changed in the planning run. If the dates of a particular element are no longer suitable, the following exception messages are created depending on the requirements situation.
    Rescheduling check is to change the dates of already existing firmed receipts which were not planned on the same day as the requirements day to suit the requirement.
    For this we need to define a rescheduling horizon.
    Rescheduling horizon defines the period for bringing the receipts that should be taken into account for rescheduling.
    For further info: Please visit: http://help.sap.com/saphelp_40b/helpdata/pt/b4/7055967935d1118b3f0060b03ca329/content.htm
    For second question, if you change it to 100 days,
    If you put 100 days, for net requirement calculation, system will consider the firmed planned orders & receipts within 100 days.
    If one firmed planned order is in 4 months before ie 120 days before, system will not consider for net req calculation.
    Say demand is 100 on 23.09.08
    Resheduling Horizon 100 days
    Firmed planned order in 23.04.08
    When MRP run system create planned order for 100 qty.
    If rescheduling horizon 999 days, system will not create planned order & system propose reschedule the firm planned order to 23.09.08
    Regards,
    Syed Hussain.

  • Exclude Stock Transfer from MRP Net Requirements

    Hi,
    Is it possible to exclude the Stock Transfer Orders from the Net Requirements generated by MRP? I want to base the requirements only from historical consumption. In my Stock/requirements list (MD04) for example, the Requisition generated by MRP increases in quantity since there are open Stock Transfers which are to be served by that plant to other plants.
    Regards,
    Lee

    Nazrin,
    Availability check configuration (OVZ9) has no impact on MRP.  MRP relies on its internal rules when it is performing its net requirements calculation.  You have very little control over which elements are included/excluded.
    You can exclude selected storage locations from MRP planning.  Stock and reservations against these storage locations will therefore also be excluded. 
    You can exclude a material from planning, change the material master MRP type to ND.
    Your best bet, though, would be to set your PM planning process up such that these materials never create the reservation in the first place.
    Regards,
    DB49

  • Best Method to calculate Net requirement

    Hi Expers,
    can you suggest the best methods to calculate net requirement for FMCG products in APO Production and distribution planning.
    Best Regards,
    Anandharaj

    Hi Anandharaj,
    There are multiple threads, SAP Notes and documentation in the web about this.
    Please read this note that explains everything about Net Requirements:
    448960
    - Net requirements calculation (documentation)
    You can also check this article:
    Net Requirements Versus Pegging in SAP ERP and SAP APO - SAP Planning
    Hope this helps.
    Kind Regards,
    Mariano

  • Pricing - Requirment / calculation type / base value

    Dear Friends,
    Thnaks for the support and guidance provided by you for my previous posts
    In Pricing Procedure we give Requirment, Calculation type and Alternative formula for condition base value, I would like to know where do we exctly define all this?
    Or are they standard? If standards where we can see how they works?
    Regards
    Vishal

    Hi,
    go through the below Examples for better understanding ..
    Example: 1
    Condition Type: PR00
    Requirement 2 Item with Pricing
    Purpose:
    This is an example of a pricing requirement.  This requirement is met if the document item category is relevant for pricing and no previous condition in the pricing procedure has set the condition exclusion flag. This requirement can be assigned to condition types in the pricing procedure to avoid unnecessary accesses to the database when an item is not relevant for pricing or a condition exclusion indicator has been set.
    Example: 2
    Condition Type:  Net value
    Calculation Type: 2 Net value
    Purpose:
    This is an example of a condition value formula.  This type of formula can be used to influence the value shown for the condition in pricing.  A condition value formula is assigned to a condition type or value line in the pricing procedure.
    Formula '2' sets the value equal to net value that has been calculated so far for the item in the pricing procedure.  It contains the amount excluding taxes.
    Example: 3
    Condition Type: R100
        Alt.Condition Base Value: 28 (100% Discount)
    Purpose:
    This is an example of a condition base value formula.  A condition base value formula can be used to influence the basis the system uses when computing a pricing value.  A condition base formula is assigned to a condition type in the pricing procedure.
    Formula '28' sets the rate of the condition to a 100% discount.  This formula was delivered with condition type R100 to support free goods functionality.
    Reward if it is useful,
    Chandramohan

  • Rescheduling Horizon

    Hi,
    Can u explain me the use of *rescheduling horizon*?
    How it will affect while planning?
    More over i have another doubt like wen i created a sales order on 10th as the delivery date of this month and a PIR on 13th of this month.My statergy is 40 and my inhouse pdn is 1 day.When i run MRP, can u plz tell me the dates wen the planned order will b created?
    Moreover if i want the the date of start date considering the inhouse pdn in  the planned order itself,where shld i do the setting?
    Regards,
    Prasanth

    Hi,
    The rescheduling horizon, defines the period for bringing forward the receipts, and the receipt elements, which should be taken into account in rescheduling, are included in these.
    In your example, you will get an exception message (depending on the tolerance values you have defined)to postpone the process , since the Sale Order is before the requirement.
    pls refer the foll links
    http://help.sap.com/saphelp_470/helpdata/en/f4/7d2c9744af11d182b40000e829fbfe/content.htm
    Rescheduling Horizon
    Re: Hi.Query on rescheduling proposal

  • Rescheduling horizon at 999

    Hello, we set our rescheduling horizon at 999 days for the correct MRP group in configuration, however when we run MD04, the date of 12/24/2018 did not reschedule. It should have pulled it in. We put the date of 12/24/2018 as a test to see if it would pull it in to within the 999 days, but it did not. What else could be causing the problem?  Everything in the material master looks fine.
    Thank you.

    Hi,
    What do you mean by "it should have pulled it in"? Are you expecting the PO lying outside the 999 day horizon to be brought inside it by MRP?
    Marianne Zoricak wrote:
    Hello, we set our rescheduling horizon at 999 days for the correct MRP group in configuration, however when we run MD04, the date of 12/24/2018 did not reschedule. It should have pulled it in. We put the date of 12/24/2018 as a test to see if it would pull it in to within the 999 days, but it did not.
    If yes, then that's not the intended functionality. The functionality is intended to check if any firmed proposals that exist in future can cover new requirements by rescheduling the proposal. If true, the system will propose rescheduling. The original proposal should however be within the rescheduling horizon.
    In your case, the PO could very well be outside the 999 horizon as pointed by Caetano. Besides, you have a situation of surplus. Both your customer orders are already covered by the stock and planned order and MRP has proposed cancelling your PO.

  • Infinite Rescheduling Horizon

    Currently, the maximum rescheduling horizon is 999 days.  Our customer queues up sales orders out in 2025 until they have been approved.  When the order receives design approval from the customer, it is moved into the current period.  Most of the materials are not custom and purchase orders and production orders for long lead items are created while the sales order sits in 2025.  When the sales order is moved into 2007, new planned orders are created and the original purchase orders and production orders receive a cancellation message because they are outside the horizon. 
    Is there any way to increase the rescheduling horizon to stop the duplication of orders?  Thank you in advance.

    Hello Eric,
    There is no option to increase the rescheduling horozon in customizing. Maximun will be 999 days only.
    Why dont you limit the planning of the sales orders which are falling in 2025. You can limit this if you run the MRP with NETPL prpcessing key and defined some planning horizon (period) in customizing..for example 100 days...that means the sales orders whcih comes under these 100 working days from the day of the MRP are only relevent for the MRP and planned orders will be created for these sales orders only..for the rest of the orders there will be no planned orders.
    There is no logic to have the planned orders for the requirements of the yesr 2025.
    By doing this you can avoid cancellation messages and you can work with rescheduling horizon.
    I still need the correct inputs from your side.
    regards
    TAJUDDIN

Maybe you are looking for

  • TDS Challan error - while creating payment document

    Hi, I was trying to create With holding tax Challan through J1INCHLN. Following error occurred after simulating payment document - "Withholding tax lines are being cleared along with other line items" Please help in above matter. Thanks Deepak

  • Different columns having different condition in BI Answers

    i want to have an report as like in the format : Name of the sectors      In local currency          In foreign currency           "<= 12 months" ">12 months" "<= 12 months" ">12 months"      0-250,000 >250,000 150,000- 350,000 >350,000 Public Sector

  • Created 'unread' mails in 'Sent' box

    If I reply to a message, there are no problems. However, when I create a new message and send it, it shows up in my 'Sent' box as unread, i.e. the little blue dot appears next to the message in the 'Sent' box. This is a new problem since I upgraded t

  • DB configuration details

    Based on the below thread I am working on a JDBC Scenario. /people/bhavesh.kantilal/blog/2006/07/03/jdbc-receiver-adapter--synchronous-select-150-step-by-step The database I am using is a freeware. Now what are all the configuration details needed to

  • How to transfer adobe photoshop to new iMac

    I have Adobe Master Collection CS6 and have just bought the latest iMac (27), I have migrated everything from old iMac (24) onto new iMac. Problem is I can't Deactivate the program on the old iMac, I have opened up Photoshop, gone to the "Help" butto