Reservation of Stock during MD50 run

Dear Sir,
We have a make-to-order scenario . We run MRP using MD50 , and MRP is run against a Sale-Order & it's Line Item .
Our problem is that during MRP run , System is not reserving the Stock Items available under the un-restricted own's stock .  Normaly such items are Inventory type Items and all such items are not procured  against a Sale-Order , rather these are procured as own's stock material .
Pl guide us , as how can we get such material reserved automatically during the MRP run .  We do not want the manual transfer of Stock from own's stock to Sale-Order stock .
We look-forward for the kind help please .
Regards
B Mittal

Dear Mr KrishnamruthyDSS
Thanks for reply .
As suggested by you , we changed the indicator value 2 . But now I face following problem . say if for the Material X the Stock qty is 10 numbers and as per the BOM of the Sale-Order Item the required quantity for Material X is 15 numbers , then it should reserve available 10 numbers and for balance 5 numbers a Planned Order must have been generated .
But in this case no Planned Order is getting generated and in MD04 against the Material X it disply an Exception "Coverage not provided in Master Plan" .
In the MD04 , the information displayed for Material X is as below :
Date -
MRP Element -
MRP Element Data -
Rec./Reqd Qty -
  Available Qty
20.06.2008 -- Stock -
  10
24.06.2008 -- DepReq -
1300-100  .................... 15-  ........................ 5-
Request you to Kindly guide us , as why the planned order is not getting generated for balance qunatity and the reason for the exception .
Regards
B Mittal

Similar Messages

  • Want to Exclude Stocks during Optimizer Run

    Hi ,
    Is it possible to exclude stocks during optimizer run which are available in the plants and sales Branches?
    Ajay

    Hi,
    In SNP, all the receipts and requirements are calculated based on the category group maintained with the Key figure.
    Please check what is the Category group maintained for the Receipt key figure. If you remove the stock category from that category group, I think the optimizer will exclude the stocks.
    Regards,
    Manimaran M.

  • To consider subcontract stock during mrp run

    Dear all,
    while mrp run it is not considering subcontractor stock .Is there any setting in spro so that it will consider subcontractor stock into consideration.
    with regards
    cp vijaya kumar

    Dear,
    Special stocks are not considered for MRP run. Subcontracting stock is a special stock(O), hence is not considered for MRP.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Consideration of stock of discontinued FG or trading material during MRP Run

    There is an functionality of follow up material for component. I would like to know if there is any similar option available for finished goods or trading materials.
    I am doing procurement planning for externally procured Trading materials. Now my previous material A is being replaced by material B. Therefore all the planned independent requirement is available in system only for B. But still there is some stock available for material A. How can it be considered during MRP run for material B.
    Example,
    Material A:
    On Hand Stock = 100
    Planned Independent Req. = 0
    Material B:
    On Hand Stock = 300
    Planned Independent Req. = 1000
    In this case if we run MRP for material B, how we ask system to plan Purchase Requisitions for 600 instead of 700 for material B, considering stock of material A.

    Hello
    Please refer to the following SAP note:
    43636 - Discontinued parts
    This note provides a detailed explanation of the system standard design of the usage of discontinued parts with material requiremenst planning and the most common questions about this issue.
    The following information is provided on this note regarding the PIRs:
    2. Planned independent requirements and forecast requirements are not redirected.
                  Explanation: Planned independent requirements after the effective-out date are not redirected but are provided with an exception message in the MRP list stating that they cannot be included in the availability check. Planned independent requirements and forecast requirements are therefore displayed in the MRP list and in the stock/requirements list. However, they do not influence planning
    BR
    Caetano

  • Alternative items during MRP run

    Hi,
       I have seen discussion on alternative items in BOM. Thanks for all for sharing your knowledge. I knew alternative items will be choosen while creating / release of production order (material availability check)
    Requirement:
          For material A, I am using component B as priority 1 and component C as priority 2.
    During MRP run, system needs to CHECK component B first. If stock is not available for component B then system need to consider component C automatically. It should not create any planned order for component B.
    Is it possible, system will check automatically alternate items during MRP run? if so kindly let me know the logic.
    If not, is there is any user exit. Customer is asking this facility. Its his basic requirement.
    Kindly give your suggestions....
    Regards / US

    Hi.
    I might have typed it wrong, I think the right one is called DIMP.
    As far as I know you don't have to purchase it. In the past those extensions were known as Industry Solutions, in this case Automotive and A&D.
    Before you go to this complexity for interchangeable materials functionality in MRP, I recommend that you have a design review with your customer, to strengthen the point that if two materials are the same for all usage purposes, but only differ, let's say, in the source (different manufacturer). for that in SAP we would define ONLY ONE material number, with additional manufacturer part number info, and in some cases with a classified batch.
    Regards,
    Mario

  • Storage location consideration during MRP Run

    Hi All,
    Within a company code, i am having 2 plants namely PS12 & PS13. In plant PS12, i am  three storage locations namely 1201, 1202,1203. Similarly in plant PS13, i am having stores 1301,1302,1303.
    During MRP run, i do not want to consider the stock in all the storage locations of PS12. The storage location 1203 to be exclued during MRP run. How to set this?
    Your input will be appreciated very much,
    Thanks
    Kumar

    Hi Kumar,
    Goto SPRO>Production>Planning>Define Storage Location MRP per plant, add the storage location to be ignored during MRP and select indicator '1' against it. Thereafter, all the materials created with this storage location will be defaulted with value '1' in the field 'SLoc MRP indicator'. However this can be modified later if required.
    For existing materials, select indicator '1' in the field 'SLoc MRP indicator' avaialble in MRP view under the column 'Storage location MRP'. Go for a mass update for a huge list of materials.
    Check this and revert for any clarifications.
    Regards,
    Murali

  • Intercompant STO working during MRP run.

    Dear Experts,
    How intercompany stock transfer works during MRP run?
    I mean if one company is purchaser and other is vendor and purchaser company's planned delivery time is 10 days and replenishment time in other company is 3 day then will system consider these two times in creating purchase requisition in first plant ( in MD04)?
    Regards
    Deepak Sharma
    9818263889

    Hi,
    Say your purchaser is plant A, vendor is plant B. STO can make by spl.procurement key 40 in MRP2 view in plant A.
    If you create requirement in plant A, system will create planed order for that material.In plant A, system will consider only planned delivery time of 10 days.
    In plant B, system will create dep requirement. suppose if stock is not available that time system will consider to replinishment the material as 3 days.
    This 3 days will not consider in Plant A.
    Regards,
    Dharma

  • During MRP run unwanted plant and storage location include and exclude

    Hi There,
    During MRP run how to include and exclude the unwanted plant and storage location pls let me know the required configuration settings.
    Thanks in advance.

    HI,
    To control whether a particular storage location will be included or excluded from the MRP run.  (MD02/MD41).
    To exclude it from MRP run :-
    OMIR - Define storage location MRP per plant
    Put the MRP ind. as.         1 - storage location stock excluded for MRP
    To include it from MRP run:-
    OMIR - Define storage location MRP per plant
    Put the MRP ind. as.      space - storage location stock also planned at plant level and save it
    Next go to transaction MM01 - tick only view MRP 2
    Key in Plant and Storage Location
    Look at the Storage Location MRP section
    change the SLoc MRP indicator to space  and save it
    MMD1 - Create MRP Profile - MRP profile is a useful entry aid and makes it easier to manage MRP data.
    You define which fields are filled with values when MRP data is entered in the material master record, which of these values can be overwritten and which not.   You use the information stored in a profile is standard information that is needed again and again in similar constellations when material master records are maintained.
    Regards
    KK

  • DURING MRP RUN MATERIAL IN QI STATUS HOW TO GET MATERIAL OUT OF QI

    HELLO EXPERTS:
    DURING EVERY 24 HOUR MRP RUN 1 OR 2 MATERIALS SHOWS AS BEING IN QI STATUS WHEN IN RESTRICTED STOCK..... MY UNDERSTANDING IS MATERIAL IN RESTRICTED STOCK IS NOT IN QI.....CAN YOU EXPLAIN WHY

    Dear in SAP generally there are 3 stock statuses are in use most of the time they are Unrestricted,Blocked and QI stock.
    When you have activated any inspection setup in MM QM view based on the setup when you do any movement for that material it will create an inspection lot with stock posting to QI,based on your results you can send that QI stock to unrestricted or blocked through Usage Decision(QA11).
    Now during MRP run if you don't want to consider the QI stock for net requirement calculation check this badi as in standard SAP You would be able to define only the following stock types not available for MRP run.
    1. Stock In Transit
    2. Blocked Stock
    3. Restricted Use stock.
    This you need to configure in OPPQ transaction in the available stock section for the plant.
    So in standard it is not possible to restrict QI stock from not considering as available stock, if required you need to look for Implementing BADI "MD_CHANGE_MRP_DATA ", please check with your technical consultant(Abaper).
    Cheers
    KK

  • Reservation of stock at Storage Type level in Warehouse

    Hi Gurus,
    My client is currently using ORACLE ERP system and they are migrating to SAP.
    In ORACLE there is a flexibility wherein reservation can be activated for warehouse stock.
    However, in SAP we are mapping the multiple warehouses present in ORACLE as Storage types.
    So, I would like to know whether there is a way to reserve the stocks at storage type level.
    According to my analysis direct reservation is possible at plant and storage location  level.
    However I would like to know from you whether there is a direct way to reserve the stocks in storage type in warehouse or any in-direct way possible to reserve the storage type stock?
    Thanks & Regards
    Subhasis

    However, in SAP we are mapping the multiple warehouses present in ORACLE as Storage types.
    That's probably a bad move. A physical warehouse should be at least one storage location, and storage types should only be used for sub organization inside a warehouse.
    For example if Storage types are used for High Rack, Bulk, etc (what they are supposed to be used for) there is no reason to reserve stock in a specfic storage type.
    Storage type vs Storage location. A "type" shouldn't be used to separate different warehouses.

  • Schedule lines are not getting generated during MRP Run

    Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
    Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
    Can any one help me and suggest me what to be done in this case .
    Thanks & Regards ,
    Nirmalya

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • How to rename the XML file generated during payment run

    Hi,
    We have a requirement to rename the XML file during payment run, format some fields of XML file and upload it onto Application server with the new XML file name. All these activities need to be performed during payment run F110.
    Please let know if there is any User exit or Enahancement to achieve these functionalities.
    Thanks !
    Regards,
    Ravinder

    Hi,
    We have achieved the second functionality also i.e. populating the additional nodes or custom nodes of an extended tree.
    This is what we have done...
    We have copied the standard exit FM: DMEE_EXIT_TEMPLATE_EXTEND_ABA into a custom one and assigned it to each (custom) node in 'Source' tab. Line item text FPAYP-SGTXT will not be returned via this FM, so we fetched it explicitly from BSEG table using the input FPAYP-DOC2R (this field will have the company code, document number, fiscal year and item no, all concatenated).
    Thanks,
    /Ravinder

  • Picking up invoices during APP run in F110

    Hi everyone,
    Could anyone help me out in clarifying. During APP execution in F110, some of the invoices in the proposal list are showing exception for payment i.e, in red. when i checked those invoices are blocked with payment block B. So in order to pay those invoices i used FB02 & removed the payment block in the respective documents. How can i identify whether these invoices are automatically blocked by the program during APP run.
    Thanks & Regards,
    Ram,

    Hi Ram,
    payment block comes different ways.
    1. automatic payment block which comes from MM when invoice i.e MIRO get trigger.
    2. from payment terms.
    3. manuall block.
    if it comes from MM to remove use t-code MRBR other than this you can remove manually in F110 or at line itme level.
    Regards,
    Raman

  • BTE 2040 is triggering during F110 run.

    Hi,
    2040 BTE is not triggering during F110 run. I have copied the SAMPLE*2040 FM and kept infinite loo to catch switch the debugger in background process at SM66. But the BTE is not at all triggering after I run F110.
    Any other way to fix it?
    all my settings @FIBF is fine and I have cheked few threads all process is fine.
    Is it any configuration issue?
    Regards
    Kasturi

    Hi Kasturi,
    See SAP Note 556924 - RFFOD__V - Alternative payment advice form.
    See in tcode FBZP what RFFO* report you call when you run F110 (check it in F110). The BTE is triggered by this RFFO* report, that it can be triggered by F110.
    I hope this helps you
    Regards
    Eduardo
    PD: see also SAP Note 836169 - Consulting: Payment advice notes by email or fax
    Edited by: E_Hinojosa on Sep 12, 2011 6:07 PM

  • How We Can Change Page Size During Report Run Time

    Hello !
    How We Can Change Page Size During Report Run Time .
    How can we stop to change the column name when we amend a sql in report data model.
    Thanks !
    null

    hello sohail
    1. question - i'm afraid this cannot be done ... bit in report 6 and newer you have posibility to divide your report in 3 parts (former header, body, trailor) and each part can have diferent page siz, orientation , ...
    2. question - best is give each column in your statements in one report diferent alias. when you have to chnge something, alias will remain same ...
    try this: select 1 as fist_column, 1 as second_column from dual
    hope this helsp

Maybe you are looking for

  • ICloud not streaming music to iPhone 4s

    For some reason, my iPhone 4s will not stream songs directly from the cloud. Instead, it will attempt to download every song any time I attempt to play one...emphasis on the word attempt. Most of the time, the song won't play at all. Other times, it

  • Payroll Journal in a single line

    Hi Experts, My client requirement is that all the payments n deductions need to come in a single line for every employee in the form of a report. Is there a solution for this ?? Plz help. Thanks & Rgds, Vishwas

  • Converter boxes

    My Fios converter box on one of our tv's stopped working at all!!!   How do I reset it?  I've tried the standard, unplug to reset to no avail.   Any help is appreciated. 

  • My iPod Touch pauses randomly. Can anyone help me?

    Hello! So my iPod has this strange tendency to pause randomly while it plays music. It has gotten to the point where it makes listening to music impossible (and therefore the iPod useless). I have tried everything: -the 5 or 6 R's that Apple is promo

  • Smart collection drop down does not include keywords

    I must have gotten this right once, because I have a smart collection whose only condition is a keyword, which is at the top of the drop down for that collection.  Likewise there is a default smart collection that LR must have created, which is calle