Reservation to be created from another plant

Dear All
I have a scenario where stores person has created one plant as engineer stores ,which is different from maintenance plant, When executing the work order i can able to specify the plant which is corresponding to the engineer stores.from which i can issue the material .
But if the plan for the material  using tasklist the reservation are getting generated in the maintenance plane, whereas the MRP run in done in engineer stores level .
Is there any way we can create reservation in the engineer stores plant or any user exit available for transfer of reservation from one plant to another
regards
thyagarajan

There is a field "Iss. Pl." available in the component overview section of task list. In standard configuration it is deactivated.
Online help Document for the field is as under and it show that the purpose can be served.
Issuing plant
Area of validity of an item relevant to plant maintenance which is different from the validity area of the BOM (Plant).
Use
This entry is only taken into account for plant maintenance activities in the department responsible for plant maintenance.

Similar Messages

  • Withdrawal from another plant

    Dear Experts,
    there is an SAP standard process in ECC defiend as withdrawal from another plant, when for example creating a planned order in ECC, the dependant demand of the component product is placed on the plant assigned e.g the alternative plant.   We are using SCM7.0 and SNP as part of our supply chain solution.  Can someone advise how and if it is possible to replicate the standard process of withdrawal from another plant in APO SNP?, what settings are essential etc?
    Basics of withdrawal from another plant are as follows:-
    - create a special procuremnt key and populate the  flag withdrawal from another plant, assign to the material master in ECC.
    Cheers
    Paul Martens

    Nandha,
    thank you for the OSS note reference.  Very useful.  One more question, from this note it suggests that the functionality of withdrawing from another plant is only designed to work with PPDS, is this correct?
    Cheers
    Paul

  • Copying Plant from another plant.

    Hi all,
    I am creating a new plant referencing another plant from the same company code.
    I completed that and found that the plant was not correctly coppied for some
    Now is it OK if I delete newly created plant and try to re-create it in the system again by copying it from the other plant.
    Or is it possible to get me the list of all the tables which are normally coppied when you copy plant from another plant.

    If there are few accounting documents existing for the plant
    Just copy the existing plant and rename it in ox10
    thanks
    G. Lakshmipathi

  • Material planning from another plant

    Hi,
    Can anyone answer me
    I am planning for X in plant P1
    There is a material in Plant P2 and the same material added in BOM for X but the material is not maintained in plant P1
    How this can be managed
    shrish

    Hi,
    For that u have to create same material in both plants.
    If it is in BOM of X, you can use special peocurement key for component, i.e.production in alternate plant,purchasing from alternate plant, etc.
    So dependent requirement will be created in another plant for that material.
    Regards,
    Suhas

  • Reservation not getting created from shopping cart for stores order.

    Hi experts,
    Reservation not getting created from shopping cart for stores order,process used is some custom BADI.Extended classic scenario is the procrss .
    Please help me
    Thanks in  advance.

    Hello,
    please check below wiki:
    Determination of the follow-on document type
    Regards.
    Laurent.

  • I am unable to open PDF files created from another PGM.

    Is there an ADOBE pgm that will properly read in PDF files created from another pgm and convert them to ADOBE PDF so they do not error when they are opened to be viewed by ADOBE pgm?

    There is no way to know all the different scan/fax/pdf printers that are used to make the original PDFs...
    CAD-KAS PDF Editor 2.6 is used to edit the files
    doPDF 5 is used to modify pdf file.
    Interesting, I can use the free CAD-KAS PDF reader to open & read the PDF file that the ADOBE XI reader
    gives me the above error message.

  • Duplicate contacts when created from another application like Mail

    When adding a contact to Address Book from another application (from an email signature for example) two of the same contact are always created.  This does not happen when creating a contact from within Address Book.  Anyone have this problem and correct it?

    known bug, please send feedback to apple about your situation. http://www.apple.com/feedback/macosx.html
    Address book has a feature "look for duplicates" under Card in the menu bar. This will merge duplicate entries into on. But now I have some weird double names (but they're one contact/one card).

  • Refurbishment process - want to repair material from another plant

    Hello All,
    In a Refurbishment process, we can do repair either Internal resource(control key PM01) or with External resource(control key PM02) by sending out material to vendor with material outward slip. But in my case, i have to send material to my another plant(2222) for refurbishment & after repair want to take it back to my plant(1111).
    Can you plz guide me over here, how i can achieve this? which are the things need to be taken care? whether any other process(SD-Shipment process) need to involve here?
    Thanks to all in advance.

    Hi,
    you can use standard refurbishment orders and defining your plants and relevent storage locations at header level. just take care of following points:
    - Valuation types are defined for the equipment/ material.
    - movements of material from one plant/Sloc to other plant/ Sloc.
    - operations defined correctly in terms of internal/ external.
    - capture all labour costs in your plant (1111) cost centre related to carrying material from your plant to another plant and back  to your plant.
    - cost centre distribution rules maintained correctly.
    Ragards,
    Lucky.

  • SAP MRP ConRel from another plant

    Hi there,
    I am thinking about setting up this process and need advise on few things.
    1. I have plant A creating Purchase Orders to ship from Plant B - For Eg - 100 Ltr.
    2. We auto convert PO to SO for Plant B
    3. MRP runs and creates Planned order into customer stock for 100 Ltr
    4. Planned order is converted into Production Order
    5. GR done against Production Order and inventory is received into Customer stock for that SO.
    6. Delivery done and inventory sent to Plant A.
    The problem with the above process is, when Plant A is creating Purchase Order for Plant B, ConRel entry is made into MD04 for Plant B. Now when I run MRP for Plant B. It creates another planned order for 100 Ltr along with SO referenced planned order for 100 Ltr.
    So I have two planned orders, what is it that I am missing ? Please advise. thank you

    Hello,
    Your ConRel should get deleted after creating the delivery.
    Check delivery table LIPS has Requirements class transfer of requirement set in OVZG for your requirement class.
    In SM30 table V_161V you can use the "ATP Conf. MRP" checkbox to define that the material requirements planning (MRP) is to refer to confirmation schedule lines only.
    The quantities that are available in the supplying plant, and that were confirmed by the ATP check are considered as receipt in the receiving plant at the confirmed date.
    Please refer KABA  1621912 - Transaction MD04: Requirements of stock transport orders are deleted after delivery is created
    and consulting note 207942 - MRP: Problems with requirements from sales order/delivery
    Best Regards,
    R.Brahmankar

  • Excise duty in Subconrtacting with components from another plant

    Dear SAP Gurus,
    I have a typical scenario in subcontracting. I have a company code 0001 which has 2 plants 1000 & 2000.
    Plant 2000 creates subcontracting PO against vendor XYZ for FG with Excise duty.
    However plant 1000 issues the component  which is excisable Material.
    Just to summarise the component issued from plant 1000 is excisable & FG to be received from Sub contractor in Plant 2000 is also excisable.
    Kindly guide.
    Regards

    Hi
    For plant 100
    1) Create a sub PO
    2) Issue the material th MB1B 541
    3) Create a excise invoice in J1IS reference document is step 2 doc.No need to create a Subcontracting challan as the excise Invoice would serve as a Legal document
    Account entries will be
    ED Suspense Dr
    ED Payable Cr
    ETT OTHR will be called
    4) Recieve the material in MIGO
    5) MIRO for processing charges only
    For plant 2000
    1) Create a sub PO with Excise duty
    2) Issue the material th MB1B 541 create a subcontracting challan in J1IF01 -No excise duty
    3) GR and J1IEX -For capturing and posting Excise duty
    Acc Entry
    ED Recievable Dr
    ED Clearing Cr
    4) MIRO for processing charged and Excise duties
    Regards
    Sandeep

  • Transfer songs from a ipod mini that was created from another account

    I bought a used ipod mini that came loaded with over 400 songs which I would like to add to my itunes MAC account. The ipod mini is in Windows format and I understand that at sometime in the future I will have to restore the ipod mini in order to convert the device from Windows to MAC format thereby losing all the songs and data that are currently on the ipod. My itunes level is 7.6.1. I am running OS X 10.4.5.
    Is there any way to transfer or upload the songs from this device to my IMAC itunes account even though the songs were purchased and downloaded to the device by the original owner using his Windows itunes account.
    Thank You.

    Since you did not purchase the songs, they are not legally yours to keep.

  • How to access my website created from another computer and location?

    I am a beginner.  My nephew made an e-commerce site for me using dreamweaver on a Mac.  I purchased dreamweaver cs5 and have windows vista.  He sent me the FTP address, username and password.  I opened dreamweaver and am asking what to do to access and download the files?

    but it keeps saying that the local files should match exactly to the web which I obviously don't have.
    What's the exact message?
    The whole purpose of connecting is to download remote files to local so they mirror each other.
    It describes how to up load but not download.
    Download is the exact opposite of upload.
    Select Remote View, select all files, click Get.
    When I get to that point, that will download all the webfiles into my local folder rewriting everything there?
    Yes.
    But you don't have any files locally which will be overwirtten, do you? Just an empty folder waiting to be filled with files from the Remote server.

  • Delivery from one plant taking order of another plant

    Hi,
    Please share your view that how it is possible to delivery from one plant taking the order from another plant where production is made in later plant and material is moved by STo to the first plant for despatch.
         So stock is ready in first plant but since the order is of second plant , if we bypass the first phase check in shipping point while create delivery by VLO1N , inside the document the second plant is determined. is there any way around?
    Please explore.
    Regards
    Indranil Saha

    Dear Lakhsmipathi,
    Thnaks for your reply . I will Definitely close the open issues later.
       There is no problem about STO. Problem is that we have to issue the sale order in manufacturing plant and with respect to the same order we have to make the delivery by VL01N from another plant. So MRP will run in manufacturinf plant. Stock will built up in manufacturing plant, then it will be transferred to another plant and from there the same material is to be despatched where the delivering plant in sale order is the manufacturing plant.
        SAP does not allow to do it as the delivering plnat specified in the order is different from thye plant from where it is to be despatched.
       We have thought also to create customized routine for it where we may bypass the check of shipping point in copy control as well as the population of the plant which is to be filled up manually by user in delivery document.
       Is there any other alternative . please explore.
    Regards
    Indranil

  • Notify MRP controler 2 transf Req Qty based on Proces Order from diff Plant

    Dear Experts,
      Material A is Semi Finished goods, in-house produced in plant 1000
      Material B is Raw Material, externally procured from  vendors and stored in Plant 2000
      Material B is the component required to produce Material A, and this has been created as part of the master data in the BOM in plant 1000.
      A plant to plant transfer is done for material B when it is needed for production of material A in plant 1000 from plant 2000.
    On creating my Process Order for material A, a reservation is created containing the required quantity of material B. This same quantity i can see on displaying the Materials List of the Process Order ( in the Requirement Quantity column).
    Material B is only to be transferred  to Plant 1000 based on the requirement quantity of the Process order.
    How do I automatically get the MRP controller of Plant 2000 notified of this Requirement Quantity immediately a Process Order in plant1000  is released?
    I mean how does the MRP controller in plant 2000 gets to know that there is a need of Raw Materials in Plant 1000 as specified in the Process Order created & released in plant1000?
    Thanks for your expected responses

    Bisolaaina,
    Use special procurement key 40:stock transfer for material B at plant 1000. This specifies that the material B is to be procured from another plant 2000. A requirement which arises in plant 1000 is then covered by stock from plant 2000
    The following happens during the planning run: on detecting a shortage in plant 1000, the system automatically creates a purchase requisition for a stock transfer in plant 1000 and a release order for the purchase requisition in plant 2000. The date of the release order is determined during scheduling. When the stock transport requisition is converted into a stock transport order, the release order in plant 2000 is automatically converted into a reservation.
    Tara

  • Material sourced from multiple plants

    Hi all
    I have a Plant A which sources material from Plant B, Plant C, and Plant D. We use STOs to transfer material from Plant B,C,D to Plant A. If I use a Special procurement key then I can only define one of the source plants. What is the solution for this?
    Will Quota arrangement work?
    thanks a lot

    John,
    Special procurement key is mainly useful for planning.  It does not prevent you from sourcing from another plant, it only sets that one plant will be defaulted as a source.
    So, you can set up STOs from all three plants.  Set your SPK for the 'most likely' plant.  If a planner wishes to override the MRP created Purchase reqs, he can do so by manually entering a new source plant in the Purchase req.
    Now, if your intention is to have MRP automatically source from all three plants, according to some fixed ratio, then remove the SPK from the Material Master, and create Purchase Info Records for all three source plant vendors.  Then, enter these Purchase info records into a quota arrangement, according to the ratios you wish to procure by.
    Best Regards,
    DB49