Hi ,
We have new requirement for import PO
While doing advance Miro against import PO ,system should not allow miro more than PO qty or PO value .
Please let me know , if any badi or user exit can be used in this...!
Thanks ,
Pradeep

Hi,
Go to OMRM and set the message 087 (Invoice quantity greater than PO quantity) (item without GR) as an error.
also you can set message 504 (Quantity invoiced greater than goods receipt quantity) as error message
Regards,
Manish Jain

Similar Messages

  • GR Qty more than Delivery Qty in Production Order

    Hi
    there are a amazing Production order that GR Qty more than Delivery Qty of finished goods in this production order.
    there are some data in this production order as below:
    Order Qty = 2680
    Delivery Qty = 2680
    Tolerance = 0
    However, to my surprise, Material documents list there are 3500 Qty has been received related this production order. I have check all material documents related this production order. the total GR Qty is 3500 more than 2680.
    I know when I do GR for this production order if Total GR Qty exceed Order Qty, So, SAP will not allow me to do. because the Tolerance = 0.
    Anybody can tell me, how to deal with this error?
    Thanks
    Henry

    Hi Henry,
    If you do not want to restrict the quantities while confirmation, make the changes as required.
    Related to Material master, work scheduling view the under/over delivery tolerance should be zero and unlimited delivery tick should not be active
    While creation of production order (if manually created) under delivery or over delivery tolerance should be zero and unlimited delivery tick should not be active.
    regarding configuration, in OPK4 for plant and order type the following confirmation parameters are to be maintained
    Hope this will solve yours, come back if required.
    with regards
    Ram Kumar

  • GR Qty greater than Confirmed Qty

    Hi All,
    We have created Purchase order with Internal order as account assignment. When ever we are doing MIGO, System is giving the error " GR Qty greater than Confirmed Qty".
    Please help.
    Thanks
    Subrato

    >
    Subrato Chowdhury wrote:
    > The MIGO is happening whenever we are deattaching the internal order. The PO Quantity is same MIGO Quantity.
    Can you expalin more this line whenever we are deattaching the internal order ?

  • Requirement Qty more than BOM Qty

    Hi,
    I have a scenario, in my Component Overview of Prodn Order, Requirement Qty of Components in Prodn Order is Different than BOM Qty.
    I checked the exploded Qty in CS11, CS12 and CS13. But the Reqt Qty vary with BOM Qty.
    Note: No Scrap is maintained
    Please guide.
    Thanks in advance,
    Harris
    Edited by: Harris Panchal on Feb 17, 2010 6:58 PM

    Hi,
    1. surely there is a mistake happening at your end.
    2. System is robustic on this kind of transactions
    Check the below items
    1. if any scrap has been maintained at the assembly level for the header material in the material master
    2. If any scrap has been maintained for the materail at the BOM item level.
    3. check if the unit of measure is same and any relationship is maintained.
    4. Also do re-xplode your CS11 and check if it works fine as per your expectation..if it is giving any issue in the production order , it should also give the same here..
    kindly validate and let me knwo the feedbakc
    reg
    dsk

  • Picking qty less than Delivery qty

    Dear All,
    I want to enter less picking qty than delivery qty during delivery process.
    Now system is not allowing for this fuctionality.
    How to achieve this?
    Rgds,
    Senni.B

    Dear Senni.B,
    > I want to enter less picking qty than delivery qty during delivery process.
    As per the standard functionality picking quantity should be equal to the delivery quantity.
    And not advaisable less picking qty than delivery qty during delivery process.
    Can you plse give more details In which scenario you require this functionality and what is the use of that.
    I hope this will help you,
    Regards,
    Murali.

  • Picking qty less than Delivery qty alert - Urg

    Hi Guys,
    We have done a configuration for order to cash scenario on ECC6.0 now we have one requirement that if picking quantity less than delivery quantity it should send an alert to customer representative.
    I have few questions below before start up configuration for that process.
    1. How do i configure to the system to send an alert when there is short pick in delivery document? 
    2. When customer representative receives the notification he or she make the necessary changes manually change in delivery document of delivery qty to picking qty.
    3. How do i say the logic to ABAPer to do a coding, I think there is no standard configuration to do that or if it is please write back to me.
    I posted few questions but none of the questions answered to me.
    Please go through and reply me back... Urgent.
    regards
    rc gopi

    Dear Senni.B,
    > I want to enter less picking qty than delivery qty during delivery process.
    As per the standard functionality picking quantity should be equal to the delivery quantity.
    And not advaisable less picking qty than delivery qty during delivery process.
    Can you plse give more details In which scenario you require this functionality and what is the use of that.
    I hope this will help you,
    Regards,
    Murali.

  • A/R Invoice Qty Greater than Delivery Qty

    Hi All,
    Can I post A/R Invoice with the qty greater than the Delivery Qty????
    I came across a case where I have a delivery Document of 10Kgs But Qty changes to 10.5Kgs at the time of A/R Invoice posting.
    Is there any std feature available of we need to do any work around. Pls suggest.
    Cheers,
    Sree.

    Great.......
    Then the way is clear.
    You can manully edit the Qty at AR invoice row level.
    try this in Test DB first whether your effect goes right or not.
    But as per my knowledge it goes perfectly  even if you edit.
    It will increase your stock by 0.5 kg from GRPO stock.......
    Regards,
    Rahul

  • Invoice Qty Highr Than GR QTy

    Hi;
    WE have received a GR for qty of 10 and value of 100 for a PO. Accounting user entered invoice for Qty 15 and value 100 by mistake. Vendor was paid. Now we need to clear this additional IR qty. What are the steps to correct this problem??

    please post a account maintanance document for qty 5 at MR11.

  • Invoice Qty greater than PO qty

    Hi,
    During invoice verification of customs duties, system is taking excess quantity than, PO quantity. Can anybody suggest, how to avoid this.
    Regards,

    Hi,
    Check the tolerance limit set for the vendor.
    Materials managementLogistics Invoice verificationincoming invoice--configure vendor specific tolerances.You have to the tolerance settings here.
    Regards,
    Nitin Amritkar

  • Commercail invoice qty should not be greater than PO qty.

    Hi,
    We have a requirement where, system should check for the commercial qty with PO qty and if commercial invoice qty exceeds than PO qty, system should give an error. This is required to avoid duplicate payment of customs duties.
    This functionality should work for parking and posting of commercial invoice both.
    Please suggest relevant solution.
    Thanks & Regards,
    Bhargavi.

    Hello,
      You can use the function exit EXIT_SAPMM06E_012 to carry out this validation.
    Thanks,
    Venu

  • To restrict Issue for production than planned qty in production order

    Hi Experts,
    In my scenario, the production staff will prepare production order and right click in production order document and select "Issue Components" option to Issue raw materials for production floor. After issuing the raw materials to production floor closes the "Issue for Production" document and now we have "Production Order" document open in screen. When he again select "Issue Components" option and issues the raw materials once again. Materials are issued once again wrongly. This happens since the production order document is not getting refresh after "Issue for Production" document is done.
    Is there any way to restrict issue of raw materials than the planned qty.?
    I have tried lot of ways to restrict this through SP. Please revert me an solution to this issue.
    The procedure should trigger immediately when the "Issue Components" option is selected second time (If the raw materials are issued in full in first time itself). And it should allow only the qty which is to issued to production order qty (if they issue part issue to production order)
    Thanks in advance
    Raja.S

    Hi Neetu,
    Thanks for your quick response. I have tried this query. But it is not blocking the issue for production document even the raw materials are issued already for the production order.
    I'll explain my work flow again. The Production staff will prepare production order and then release the same and update the production order after changing  the status for "Release". Then he will right click the Mouse button and select "Issue Components" option and perform the Issue for Production process. He will issue the required raw material completely in one shot and add the Issue for Production document.
    After adding the Issue for Production document he will close that document and now we will be in Production order document. Now our production order document will not get refreshed. Now the Production staff go for "Issue components" option, then it should not allow him to issue the components once again. But it is allowing him to issue components any number of times. there is no control.
    If we browse the production order document to previous record and browse back to the same record then my Production order document get refreshed and now we can control the issue. But what should i do to control in the earlier case. Since they want to perfrom lot of production order, there is a chance to issue components for same production order more than one time before the production order document get refreshed.
    Please provide me the SP to control this scenario.
    Thanks in advance.
    Raja.S

  • Component Qty in PO for Subcontracting is greater than available in stock

    Dear Gurus,
    i have an issue regarding Subcontracting. When i create a Purchase Order, i use Item Category L. In the Compoenent i specify the material and the Requirement Quantity. Req Qty which i specify in PO is greater than the Qty available in Stock.
    How do i restrict the user to enter only the Quantity that is available in Stock for the Component provided to the Vendor.
    Thanks,
    Johi.

    the next MRP run will create a requisition or planned order  to get more quantity for the component., if you are short of material.
    do you just plan to produce as much as you have components for, or do you plan to satisfy a customers need?

  • SP to Block GRPO Qty if greater than PO Qty

    Hi all,
    I need to block the GRPO Document when adding it if the Qty in the GRPO is greater than the PO Qty.
    But this Stored Procedure blocks me even when i raise the GRPO with Qty less than the PO Qty.
    IF @transaction_type IN ('A') AND
    (@Object_type = '20')
    BEGIN
    IF EXISTS (SELECT T1.BaseEntry
    FROM dbo.OPDN T0
    INNER JOIN dbo.PDN1 T1 ON T1.DOCENTRY = T0.DocEntry
    INNER JOIN dbo.POR1 T2 ON T2.DOCENTRY = T1.BaseEntry
    WHERE T1.BaseType = '22' AND
    T1.ItemCode = T2.ItemCode AND
    T1.BaseLine = T2.LineNum AND
    T0.DOCENTRY = @list_of_cols_val_tab_del
    GROUP BY T1.BaseEntry
    HAVING SUM(T1.Quantity) > SUM(T2.OpenQty))
    Begin
    SELECT @Error = 10, @error_message = 'GRPO quantity is greater than PO  quantity'
    End
    END
    Is something wrong with this SP...

    Hi
    Check bellow Sp
    --------------- Validation for Goods Receipt PO Restricting Excess Qunatity ----------------------------
    IF @Object_type = '20' and @transaction_type = 'A'
    BEGIN
    declare  @line int
    SELECT @line = (LineNum + 1)
    From PDN1
    Where PDN1.DocEntry = @list_of_cols_val_tab_del
       and (Quantity > BaseOpnQty)
    Order by LineNum
    If (not ISNULL(@line, 0) = 0)
    begin
      Set @error = 10
      Set @error_message = 'Line quantity' + CONVERT(nvarchar(4), @line) +' is more then open quantity !'
    end
    END
    Thanks& Regards
    AndakondaRamudu

  • Goods Issue Qty More than Purchase Order Qty ( Intercompany Stock trans. PO

    Hi All,
    I have following Issue,
    I can do Goods Issue more than qty which is in Intercompany stock transport
    purchase Order.
    I want to restrict this Process, It should not allow more than PO Qty.
    In the STPO Setting, Checking rule field is blank.Is this the reason for
    the Issue.
    Thanx in Advance.
    Key.

    Hi -
    This is controlled by setting at item level in purchase order / sto creation transaction i.e, ME21N.
    Go to item --> Delivery tab.
    You will see under delivery tolerance and over delivery tolerance.
    Please reward points if youfind this information useful.
    Thanks,
    Ramesh

  • Scheduling Line qty greater than the Scheduling agreement qty

    Hi Experts,
    1. I have a scheduling Agreement (SA), and the qty mentioned against this SA is 1000 (say).
    2. Now when i generate schedule lines for this SA (ME38), I am allowed to schedule more than the quantity that's mentioned in the SA.
    3. Please advise, is it possible to restrict this behaviour. i.e. I want to give an error message if the Schedule Line qty exceeds the SA qty.
    Please advise. Very urgent.
    Regards,
    Manju.

    Hi Manju,
    Yes its possible to restrict the case as u mentioned.
    Check the below settings:
    IMG-MM-Purchasing-Environment data- Define Attributes for system messages
    go to meassage no : 00-06-067 set it as Error message.
    U'll achieve ur result.