I have a question related to quality inspection that suppose I have five master inspection characteristics in my inspection lot out of which I record the result only for three master inspection characteristics and approve the same. Is it still possible to go for the usage decision of the inspection lot without  entering the result of two master inspection characteristics?
Please do guide me. Thanks in advance.

Hi,
Yes you can enter the UD without completing teh results recording.
the system will display a meesage some characteristics are open.
Thanks,
JK

Similar Messages

  • Multiple results recording for Delivery inspection lot

    Hi Gurus,
    My requirement is to configure for quality results recording for sales delivery document. Where client wants to record Customer, supplier, Umpire, etc results record for inspection characteristics.
    I got response from few Sapiens that I should use Inspection point concept for multiple results recording. Could anyone cna tell me how can I do this.
    Your help will be highly appreciated.
    Thanks,
    Kumar

    Hi Kumar,
    Okay!
    First of all letu2019s try to understand whether inspection points are really suitable for your requirement or not. Accordingly further errors can be eliminated. I just try to understand.
    A- Using Inspection Points
    1.     Inspection points are used when you inspect the same parameters again and again.
    2.     When you click on results tab in QA32, system asks you put some identification number. Letu2019s say you put A1 and then press enter. Thereafter you record the actual results (LENGTH, WIDTH etc.) You save this without giving UD.
    3.     For the next time when you again click on results for the same inspection lot, system again asks you to put identification number. This time suppose you put A2. Then again you record the results (LENGTH, WIDTH) for A2.
    4.     Likewise you can retrieve the inspection results from system with respect to inspection point (identification point).
    5.     Typically this can be used for chemical industries where you record the temperature of the same chemical after every ½ an hour. Here 10:00 am, 10:30 am can be used as identifications numbers. As a result of which you can get the information that at 10:00 am temperature was 40 Deg and at 10:30 am it was 75 degree Celsius.
    If your requirement resembles this situation, then only the use of inspection points would be fruitful.
    B- Without Inspection Points
    But if you want to record the readings by various agencies like customer, umpire (refer following pattern)and want to compare them there are other ways.
    1.     Reading by your inspector
    a.     LENGTH u2013 100, 101, 102mm (average is 101mm)
    b.     WIDTH     - 10.50, 10.50, 10.60mm (average is 31.6mm)
    2.     Reading by customer
    a.     LENGTH u2013 100, 101, 102mm (average is 101mm)
    b.     WIDTH     - 10.50, 10.50, 10.60mm (average is 31.6mm)
    3.     Reading by umpire
    a.     LENGTH u2013 100, 101, 102mm (average is 101mm)
    b.     WIDTH     - 10.50, 10.50, 10.60mm (average is 31.6mm)
    You can achieve this without using inspection points also. For this in QP02 you need to create 3 operation; Inspector, Customer and umpire respectively. Feed the MICs in each of these operations. When you click on result tab system will throw pop up for these 3 operations. Double click on Umpire if you want to record results noted by umpire. Likewise for rest of the operations. You can do this even after UD also (after 1-2 months also). You need to use MIC with control indicator as long term characteristics for this in QS23.
    Regarding averaging of results u2013 This can be achieved using single result recording MIC with or without inspection points. Use appropriate sampling procedure. When you feed results in QA32 system automaticaaly averages out the reading. This can be viewable against phi symbol.
    Finally you did mention that u201Chere I am not getting the newly created inspection lotsu201D. Does that mean inspection lot (10 origin) has not created?
    Regards,
    Anand Rao

  • Result recording for quantitative inspection characteristic

    Team
    Greetings!
    Please find the following requirement.
    We are using quantitative characteristics inspection.
    Inspection lots are created automatically and the sample size for each characteristics are determined based on the sampling proceedure.
    when we do result recording for a characteristic, say the sample size is 5, even if any one of the sample does not fall under the limit, we need the characteristic to be rejected.
    How can this be addressed.
    Gobinathan G

    .

  • Multiple result recording for Manual inspection Lot using inspection point

    I want to record inspection result for inspection type 89 against *inspection point*. Then I create new inspection point and assign it in quality plan. Then I have done the multiple result recoding against one manual inspection lot in DEV server. But when it is going to QAS server then error is coming during result recoding. Error is "The results transaction cannot be used for
    inspection" Message no. QE094.
    Plz give me the solution to record the result.

    Reason is very simple : the  the inspection point definition in the task list header is incompatible with the sampling procedure assigned to the characteristic.Make sure that you select the appropriete radio button in QDV1 while creating sampling procedure and assign the same against each of the MIC's in the task list.
    Make sure that the sample tab in QA02 is pressed while assigning the inspection specification & status of the lot is REL

  • RESULTS RECORDING WITH FREE TEXT IN QUALITY MANAGEMENT

    Hi,
    How can I give free text of 300 chars In results recording? For a process order with batch number & recipe, (in which master inspection characteristics are mentioned which are linked to general characteristics.)
    I created characteristics (type CHAR)(which can be used as free text in results recording ) I have created class, assigned chars to class & finally to material. Also assigned MIC to this class chars.
    When I do results recording I need to have these characteristics to be display as free text of 30character width. But since I have to give selected set for this general chars.(which is the system requirement) I have given  selected set while creation of characteristics.
    Due to this I can only select the codes from the selected set. Is there any process in which I can write free text up to 30 cars during results recording in quality module? & those characteristics I want to assign to MIC so that when process order is executed the first operation of quality can be done for RR.
    With Regards,
    Kareena

    Hi Kareena,
    All of first let me make it clear, if you will assign a Class Characteristic to the MIC, then it will become either Qualitative or QNT.
    Now toeards your questions solution.
    Option:-1
    As suggested by Venkatr, make the control indicator "Docu. Req" in the MIC control indicator set, page:-2. for the line item of MIC in the insepction plan.
    So, the system will prompt you a message to insert a text as described by Venkat, where you can enter the Long text also (Check the button available in the lower part of that small window)
    Option:-2
    Create a document type for this purpose, and assign a file, having 300 char. to the MIC, with the help of the "Object Link" function of SAP, avaialble with RR screen also.
    Reagrds,
    Shyamal

  • Runtime error for Inspection Point Results Recording

    Hi,
    I am changing the already done Results Recording for using already used Inspection Point.
    I am getting the runtime error. Anybody came across such error?
    Regards
    Ramakanth

    Hi,
    In the in-process inspection I am using Inspection Points. Initially I have done Results Recording once with quantities.
    And then again I wanted to change the quantities for the same Inspection Point. So, I went to Results Recording for same Inspection Point and changed the quantities and saving. At this event I am getting Runtime error.
    I  have even deactivated one BADI INSPECTIONLOT_UPDATE and tried again. Even then I am getting same error.
    Ultimately my requirement is this:
    My client wants UD at operation level. They want only quantity which is accepted in Results Recording to be moved to the next operation. In the operation level confirmation the system should only accept the quantity which is accepted in Results Recording.
    Any suggestion in this regard.
    Thanks
    Ramakanth

  • Table for Original Values in Results Recording

    Hi,
    Where are the original values of the results recording of the inspection lot (inspection type 04) stored?
    Or, is there any function module to fetch this data?
    Regards
    Ramakanth

    it's in table QASE
    original value (Data Element- QORIGINAL_INPUT )

  • Change Results recording date

    Hi,
    I am using QE51N for results recording. I want to change  the results recording date for inspection type 14. Is there any BADI or user exit to do the same.
    Thanks & Regards
    V. Devaraj

    There is no user exit to change the Result recording date.

  • Step for Result recording & usage decision

    Hi ,
    I have done the result recording for an inspection lot. the inspection type is IN-Process Inspection for which I have eb=ven taked thew UD. Now my doubt is how to do the inspection for GRfor production. i.e Inspection type 04.
    Please explain.
    Regards,
    vivek

    Hello Vivek,
    The in process inspection '03' is ususally created when releasing the production order and is designed for inspections made during the manufacturing process.
    The inspection type 04 can be triggered at two different time points:
    either at release of the production order 'early 04 inspection'
    or at GR from Production 'late 04 inspection'.
    If you want to work with both 03 and 04 you have to use the late 04 inspection type, this offers you the follwing advantages:
    You don't have to eventually correct the inspection lot size, and you avoid that there two parallel inspections.
    The 04 inspection lot is designed for post production (final production) inspections and is stock relevant as opposed to the 03 inspection type that is not stock relevant.
    Regards,
    Isabelle

  • Results recording copying from another lot

    Hi,
    Is it possible to copy results recorded from one inspection lot to a newly created inspection lot.
    Please let me know about any possible options.
    Thx
    Viny

    Hi Viny,
    Refer the link.
    [Thread - 1|copy inspection result;
    [Thread - 2|Copying the values of  inspection result from one inspection lot to another;
    Regards,
    Shyamal

  • Single Result Recording

    Hi Experts,
    I have a scenario where the MIC should be created for single result recording, but user wants to record less number or results in system . This can be achieved by putting either no scope or less scope.But once we record a less number, grays of the Inspected samples to lesser number according to the sample results entered.
    The requirement is Single result recording, but the inspected samples should be able to be modified irrespective of the no. of results entered.
    For egs.
    Sample size to inspect: 100 (single values)
    User enters values for only 5 out of 100.
    But user should be able to specify the Inspected samples  as 100. (this is because in this scenario they would record only the results out of spec results, if in spec.results they don't want to record the results data)
    Alternate is to use Summarized result recording, but it does not allow to record individual records for these out of spec. results.
    Thanks
    Jomy

    dear jomy
    Seems difficult. tried with lot options not working. Wait for experts comments
    regards
    gajesh

  • Prevent entering result recording after the production order closed.

    Hi QM Gurus,
    I want to prevent entering the result recording (we used inspection point) after the corresponding production order was closed.
    Please help.
    Cheers,
    Sun

    hi all,
    Enhancement QEEM0015 is only used for individual result, it can not be used for summerized result.
    Enhancement QEEM0011 is the right one for my case.
    It works before the system valuates the inspectoin characteristics' result for both individual and summerized result.
    Thanks all for your help.
    Regards,
    Sun

  • FM for Quality Inspection Results Recording.

    Hello!
    I was wondering if someone can help me out on this one:
    The requirement calls for entering the same set of results for several inspection lots.  Short of using batch input, is there a function module that can enter the results of an inspection lot?
    Thanks in advance.  Points for anyone who can give helpful answers...

    Hi Vidhya,
                     Can you please elucidate the isuue a bit more in detail........ in which tab during result recording you are trying to attach file......So I can help with what ever little I know in SAP...........
    Regards
    Kaushik

  • Three Physical Samples withdraw from inspection lot 04  and then result record for all three

    Dear Gurus,
    We have 3 quality labs and each lab is sent a separate samples to inspect certain characteristics once we receive material from production. I have created an inspection plan and mapped these three labs as  work center in operation and then assigned MICs under each operation to inspect.
    Now my issue is how to map separate 3 samples to inspection lot generated from production  ( type-4) and also how to configure that to inspection plan.
    I have to result record for all these three physical sample as withdrawn from Lot based upon inspection plan as mentioned above.
    I can mention sample drawing procedure in inspection plan but how to map actual sample there.
    Any help will be greatly appreciated.
    Regards,
    Satish

    Hi Satish
    You are creating three operation for depicting three testing Labs.
    Against each lab (operation) you had assigned MICs as per your requirement.
    Now you have to assign a SDP along with inspection point type 200 for physical sample in task list.
    After prod confirmation system will create inspection lot along with a sample by default for 1st operation.
    For other operations you have to create samples manually referring the same inspection lot (QPR6).Remember to click ' Create Insp points' and mention operation.
    Release the samples in QPR4.
    Now when you go for result recording system would ask first for operation, so select the operation , then system will ask for insp point (sample no).There click on assign insp point , so system will provide the Sample no which were created in QPR6 for that particular operation.
    Please follow the steps and revert.
    Regards
    D Mohanty

  • How value with few decimals will be enabled for quality inspection records?

    Hi ,
    my client requirement is in such a way that i need to record the quality parameter( quantitative results) like 3.12 in qa32 transaction. how do i enable the respective MIC settings for the same, kindly suggest me
    regards
    archu

    In QS23 transaction --> Select Button Quant.data  -->Maintain Decimal places.
    All new inspection lots will allow you to maintain decimal places.
    If Inspection lot is already Released, Go to QA02 and reset the sample, Re-assign the inspection plan.