Hi,
To have transfer prices we have activated material ledger and multiple valuations.
As material ledger only works with valuated stock, we have moved the Project structure (ETO) from non valuated to valuated.
Our client requirement was to recognised revenue based on cost. With non valuated project stock, cost is upated as soon as we received the stock for the project and we were able to acheive the RA (revenue recognisition) as per the clients requirement.
However after changing to valuated, during goods receipt stock is upated and not cost. So we asked the client to consume the purchased material if they have to recognise the revenue.
Then the question came that if the SFG is received back from the assembly/production order, all of a sudden we will not have cost but revenue & stock. After looking some SAP notes on statistical cost elements, we have created the stock account as a statistical cost element (category 90) and implimented the following SAP notes which helped us to reverse the stock value and update it to P&L (by reading the balance in statistical cost element linked to the Project).
a) Note 78420 : To activate Function Module EXIT_SAPLKKAG_005 (contains include ZXKAGU05).This Function module takes into account the actual & plan costs of the assigned Production orders & Networks
b)Note 616869 : Provides source code to be copied to  include ZXKAGU05
c)Note 616960 : Changes to include ZXKAGU05 to read statistical cost elements in RA
d)Note 26002 : To activate Function Module EXIT_SAPLKKAG_001 (contains include ZXKAGU01).In this include we can make the necessary modifications to RA calculations. Through this include, stock will be reversed during RA.
e)Note 785626 : Provides source code to be copied to include ZXKAGU01
Hower if we have purchased parts which are not consumed, still the RA (FM EXIT_SAPLKKAG_001) reads the value in statistical cost element and posts a debit to RA P&L and reverses the stock. Therefore now i have cost but no revenue (as no consumption).
As per last paragraph of sap note 785626, if we have purchased parts and we want to exclude them from stock reversal, we have to use a filter with customer enhancement 3 (SAP note 67423). It also says that the goods receipts and issues of purchased parts has to lead to a different valuation class and assigne a different stock accout. Now can any one give some guidance on how a project specific purchased parts (receipts and issues to prod order) can be linked to a seperated valuation class.
We have same material which is sometimes purchased and sometime produced.
Regards
Raghu.

Hi
I can say something from theory but not much from sap config. perspective. You have not mentioned actual revenue since POC is calculated from
R(a)/R(p).How you have considered 100% poc?
From your data,it looks to me that you have met the target revenue from actual cost which is less than planned one.Inventory indicates that you can generate revenue in next accounting period (unlike WIP).I feel that unlike plant stock,RA is not perfomed on project stock Murli, can ammend my view if it is wrong.
You can post this problem to Fi/Co.
Regards
Adwait

Similar Messages

  • Table for Valuated Project stock

    Dear All,
    Can any one  suggest form which table I can get value of valuated project stock for whole project.
    I can get it through table QBEW (Project Stock Valuation), but it gives value for individual WBS only.
    Regards,
    Nitish

    Thanks for your reply.
    Basically I am using it in Yreport and initial input parameters are only Project definition and version.
    So accordingly how we can built programme, so as to pick value for whole project(all WBS) .
    Regards,
    Nitish

  • Results analysis for a project to be settled to sales order rather than PSG

    Hi Experts
    My client has two company codes.
    CC1 executes project construction for CC2. This is to be mapped as a customer project.
    As far as project settlement is concerned, since PA is not activated, it is proposed to settle to sales order item.
    In this situation, what would be effect of results analysis.
    With out PA, how the postings need to be handled with WIP, Reserves, Inventory and Revenue.
    warm regards
    ramSiva

    Hi,
    I have had this problem earlier, If PA is not abailable you have put in the settlement rule as not to be settled.
    And for the postings have to be managed using the GL accounts that we give in the result analysis configuration.  There is not much flexibility for customization here in this scenario. But you can do as much as possible using the diffrent result analysis categories.
    So for the reserves WIP inventory and revenue use result analysis category to segregate them by GL account
    Thanks
    Naveen

  • Actuals for stock valuated materials in a valuated project stock

    Hi friends!
    Iu2019m working with materials in the project, and we are going to do direct external procurement from the project. The material we are using are valuated stock and in the project I have valuated project stock.
    The requirements are that the vendor give us the material prices, and the material will not be consumed by the project(WBS/network). All the material will be collected to the special project stock until we decide to move the material to the unrestricted stock to be consumed by another department in the company. All the actual cost must follow-up in the project.
    This is what I do:
    From the project I create material components and I create the PO requisition I got the same price as in the project. Thatu2019s ok.
    When I convert the PO requisition to the PO I got no price but if I save I got the latest used price for the material and this could varied and it´s ok but should not work like this for this scenario.
    My doubts are when I do the goods receipt (MIGO) and the price of the material in the PO are not the same as the stock valuated price I got the difference as actuals in the project and the valuation of the material are in the project stock. If the price of the PO is the same as the valuation price I got no actuals in the project.
    When I register the invoice from the vendor (MIRO) I got no actuals either so I cannot do my project follow-up costs. When I check the cost they are in accounting (balance sheet account).
    When I do the material movement with 411Q to unrestricted stock I donu2019t get any actuals in the project either.
    Is this a normal behavior when using stock valuated materials in a valuated project stock?
    I SAP help I found this information for non valuated project stock:
    u201CAll the actual production costs appear in the project because no price variances can occur and all external procurement follow-up costs are debited to the WBS element.u201D
    But if the best practice is to use valuated project stock why follow-up costs cannot be done in the project?
    Please give me some ideas of this,
    Best regards
    Jose Marin

    If the mateiral was created using the no stock material material type then yes you can see this material in MM60.  Search using material type 'NLAG' for non stock. 
    Regards,

  • Results Analysis for Projects

    Hi Guys,
    We use Results analysis for projects and also we use RA in Product Costing.
    Can anyone let me know what exactly does this Results Analysis mean ( not in SAP terms ).
    I am trying to look for this over help.sap.com and google but could not find information on what exactly this term means.
    Also how is this related to WIP?
    Please clarify.
    Thanks,
    Srikanth.

    Dear srikusap,
    Calculation WIP through the SAP, RA key will play important role.  Work in process calculation is diferent from industry to industry. 
    In SAP RA key will shows the WIP amount while u running KKAX Transaciton Code.  After when ever u do the settlement then ti will be settled to Financial Account.  At that time A Accounting Document was generaged.  when ever the Order Status is Teco then the provious period WIP will be reversed.
    Revert back if u any calrification.
    Raj

  • Results analysis for POC method with statistical cost element

    Hi,
    We are testing ETO (engineering-to-order) scenario With valuated
    project stock and cost based POC RA method.
    Inventory is updated during external procurement and we have used
    statistical cost elements (Cost element category - 90) for inventory G/L.We want to use a
    Result analysis method which considers this statistical cost elements
    for calculating POC.For this purpose we have implemented SAP Notes
    616960, 616869 and 78420.
    In short, as per SAP note 616869, we created a customer enhancement
    project for customer enhancement 5 of the results analysis (see Note
    H78420). We copied the source code for customer enhancement 5 of the
    correction instructions of note 616869 and then implemented SAP note
    616960 to read the statistical actual costs.
    Then we included the statistical cost as actual costs - Category K in
    OKG4.
    The system is doing POC and revenue in excess of billing calculation
    correctly after taking into consideration the posted statistical cost.
    During settlement of RA (CJ88), system is not giving effect to
    inventory value. On settlement of RA, revenue should be recognized but
    at the sametime the inventory represented by statistical posting should
    be consumed(COS). The system should post a P&L posting which reduces
    the inventory (representing statistical cost) and updates the actual
    costs on settlement.
    In our example, Statistical actual
    posting is of USD 57150, planned revenue USD 100000 and POC is 70.27%.
    Revenue in excess of billing comes to USD 70265.60. Recognisation of
    revenue of USD 70265.60 is not correct as actual consumption is yet to
    happen. The correct posting in FI should be revenue of USD 70265.60
    along with COS of USD 57150.
    Please suggest why on settlement the system is not posting the COS
    along with revenue recognised?
    Thanks,
    BK

    Hi Bijay,
    We are in a similar situation in one project.  Did you get any solution to the problem you posted here? If you can share it, please.
    Regards,
    Gireesh

  • Valuated project stock not allowed with customer stock.

    Hi,
    I am trying to create invoice correction request for credit with the reference of invoice
    the invoice data is not copying into sales order. I am getting the error "Valuated project stock not allowed with customer stock".
       My question is can we have any routine in copy controll to fulfill my requirement or do i develop a new routine?
    Thanks in advance.
    Regards,
    Narayana

    Hi
    Did you find any sloution for this problem?
    I am facing the similar error.
    Inputs will be helpful
    Thanks
    Regards
    DDP

  • Subcontracting with valuated project stock

    Hi All,
    We are using MM subcontracting process with project assignment.We have valuated project stock.
    When I try to execute transaction ME2O for issuing components to subcontractor I do not get the PO with project assignment. I only get the PO if there is no object assigned in the PO i.e. account assignment category is blank in PO.
    Am i missing something here or is this SAP standard?
    Regards,
    V S
    Edited by: V S on Jun 30, 2011 4:15 PM

    Hi,
    Please check the following link. This explains how you can manage Subcontracting Process with Project Stock.
    [http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/402891a3-7f89-2c10-3097-91556442b8b5]
    Hope it helps,
    Best regards
    Amit Bakshi

  • Valuated and Non-valuated project stock in same SAP system

    Dear All,
      Can we operate with the system where projects are with valuated and non-valuated project stock at the same time. If yes, are there any precautions we need to take before doing this.
      Currently we are changing to 'valuated project stock' from 'non-valuated project stock' due to advantages of 'valuated project stock'. But since we are implementing this change in already stable system where projects are running with 'non-valuated project stock'. Please suggest of there are any complication with this.
      Thanks in advance !
    Regards

    Hi Muralidhar Lanka,
    Thanks for your time and efforts to share your thoughts with all of us. Hope you will not mind, did you done this kind of changes to profiles midst of the project in the past? or its your guess.
    Because, many times these kind of questions comes from business to change, but we are not sure how it will affect the existing as well new projects. In such circumstances, normally we politely propose to go with two profiles rather changing the existing one since we are not sure of how it will affect.
    It would be great help to all of us if you can share your experiences how the goods movement and value flows have taken in  system for old projects and new projects. What kind of changes you could notice after changing profile in terms of .. a few of them
    1.  Goods movement
    2. Consumption of production orders and internal order.
    3. Settlement and RA (customer projects/ investment projects)
    4. POC calcualtion of projects
    I am sorry if you find my questions are silly and not worth to answer, please disregard.
    Looking forward to hear from you at your convenient time.
    Thanks,
    PSR

  • Non-Valuated Project Stock Report

    Dear Sir,
      I am assigning some valuated and non-valuated materials to the Project. So I have selected Project Stock in Project Defination. So I can see Valuated Project Stock in MBBS but I can't see non-valuated project stock . So where should I come to know these stock also ?
    Regards
    Girish Lashkar

    Hi,
    If you check your project definition control tab you can find which type of stock you are using, whether it is valuated project stock or non-valuated project stock. Since SAP is giving a radio button to select this, it means you can not maintain both valuated and non-valuated project stock.
    In your case may be some of the material code you created as non-valuated material for the particular plant, not for project. Please check it again.
    You can also refer sap help under project system > material to know better.
    Tnx.
    Abdul

  • LIS Reporting of Valuated Project Stock

    We have a scenario where we have materials that are used both as valuated project stock and plant stock.  Plant stock goes to normal orders.  For the projects, the material is manufactured and goes into valuated project stock.  So the same material can be valuated as plant stock and project stock.  An example might be:
        Item A    50 in plant stock
                      10 for project A
                        5 for project B
    Some reporting works well.  MMBE for example faihfuly reports these values.  MBBS is correct.   MB5L shows good integrity between all accounts.
    The inventory LIS reports are messed up.  MC.1 reports odd values including the project valuation class which SAP says it will not report. 
    Does SAP Inventory LIS (MC.1 etc..) handle the situation where a material has multiple valuation classes and can be used in diferent way?  Is there a fix for this problem?
    The ultimate requirement is to have stock history similar to plant stock but for project stock.

    Hi,
    Please try the below report..
    S_P00_07000140
    Thanks
    abdul.

  • Results Analysis for Sales Orders

    Hi
    When i am calculting Results Analysis for Sales Orders as a part of Month End Closing Activities there are some errors for few orders...
    Msg Type: E
    AppAr: KJ
    MsgNo: 216
    Message Text: Planned Cost for Valuation are 0. Please Check the Object.
    Can any one tell me what might be the error..
    Thanks in Advance..
    Sivaram

    Hi,
    The error is offen caused by one or possible more than one of following statements:
    - the delivery block of the order is set
    - the billing block is set
    - the schedule line ( confirmed quantity ) is missing
    - the position has been cancelled
    - price condition is missing
    In case no one of the mentioned options wouldn''t help, set the position status to technically completed, if the position is processed as well ( delivery, invoice, etc. ).
    We often face this kind of issue
    Good luck
    Marian

  • Result analysis for sub-items on SD-order

    Hello,
    I would like to know, whether also the document flow for subitems is being checked while executing result analysis.
    Example:
    We have got an SD order, a higher-level item and a sub-item.
    Both of them have assigned the same result analysis key. Within this key it is defined in customizing (OKG3), that the Sales Order Structure is A-"Summarize Plan and Actual Data of Subitems on Highest Item"....so the result analysis for the sub-item is being performg via the higher-level item.
    The higher-level positions is already completed - the delivery is made and also the invoice is created.
    The sub-item is not completed - neighter delivery is made nor the invoice.
    While executing the result analysis for the higher-level item, the status FNBL (final billing) is recognized and all cost are settled from WIP to CO-PA.
    As far as I know, the document flow should be checked withitn the result analysis and based on this the status should be recognized.
    Therefore It seems, that only the document flow from the higher-level item is being checked. If also the document flow from the sub-item is checked, there would be no way to get the status FNBL as the sub-item is not complete.
    Is it SAP standard delivered behaviour?
    Thanks in advance
    Peter

    Thanks Waman,
    I have tried to delete the result analysis key from the sub-item, but still the same result in result analysis...
    Could you tell my the consequences from the 1A setup from the note? It is adviced withitn the note to not use the 1A setup. But we use this and it works fine. Just some messages during the result analysis, that it could not be performed for sub-items, but this has no influence on the values.
    Regards
    Peter
    Edited by: Peter Jankech on Jun 9, 2010 8:57 AM

  • Results Analysis for Contracts

    Dear Experts,
    My Client requires to do Results Analysis for Contracts.  Please share your thoughts.
    Regards,
    Shareeq

    Dear Ahemad,
    In what would be the output of the result analysis ?I mean from sales point of view if u see then u will have to develop the report accordingly.
    If you are talking abt the MM contract then there are some std reports available.
    If ur talking abt the customer service point of view then we this std transaction IP51.
    thanks and regards
    raghav

  • How to execute Result analysis for a Single order?

    HI,
    I need to execute Result analysis for a single process order. But i found cumulative RA. Can any one provide the Individual Result analysis execution T.code?
    Thanks
    KB

    Hi,
    Use "KKAX"-->individual WIP calculation
    "KKAO"-->Collect WIP calculation
    Thanks,
    Rau