Hi,
I need clarification on following process
  user had created returns po and activated the returns column in po.
in MIGO transaction he had selected the options of goods receipt-purchase order.
  my question is that why should we select above combination.since we are not receiving any goods and more ever we r returning to vendor.
plz give me complete explanation.

Hi,
Again my question is in me21n we are selecting po type  of "RETURNS PO". then y should i consider it as regular purchase order for procuring goods from vendor.
  since po type it self is a returns po. and if i require procurement from vendor i create new po which had specifically meant for purchases.
plz clarify.

Similar Messages

  • Consignment returns to vendor-urgent

    Hi,
    what is the process flow for consignment returns to vendor and which mvt type does system will prpose if i can process this returns through returns po??

    Hi Kiran,
    It depends on client process.
    I understand unless we inward to our own stock we can't decide whether the material is good or not (as it is available at the vendor stores) and make a decision to return to the vendor.
    But it is also not necessary that you have to inward the consignment material to your own stock then you decide whether the material is proper or not
    As Some Companies (Automotive industries) will visit the vendor site first to check the stock before using to their own stock.
    rgds
    Chidanand

  • Return to Vendor...negative values preventing from returning (Urgent)

    Hello SAP Experts!
    We are having an issue with Returning to Vendor.  We are on SAP 4.7C. 
    When we are attempting to Return to Vendor (movement type 161), in the PO (ME21N), after entering in the material, quantity, and checking the box for "returns" item, the pet price becomes 0.  We receive a message stating that the net price must be greater than 0.  This only occurs if we check the box for "returns"...if we uncheck it, it works fine. 
    Why is this happening? 
    For example, when we check the box to make this a Return to Vendor PO, the amount is $120.00, but the condition value changed to -$120.00, which is making our net price equal $0.00; and this needs to be greater than $0.  We have a condition type, so we can manually altert the price, however for auditing purposes, we do not want to do that.  How do I fix this?  Is it something I need to look in customizing?...if so, where?
    Points awarded...thank you for your time!
    Best regards,
    WC

    Hi,
    The issue is with your negative discount condition type.
    If you do a regular PO then  if the Unit Price is 0.19 and we have a quantity of 10, (making is 1.90), then after the discount of 51.700%- is applied, we get final net value of 0.90
    If you do a returns PO then all the condition type value will get reversed like positive to negative and negative to positive thats why your negative discount percent is adding up the total value on the unit price.
    say if the unit price is 0.19 for 10 qty it will be 1.9 after adopting this discount it is taking 51.7%+ means adding to
    1.9 + 1.9*51.7% =2.88- which is rounding to 2.9- it will not take 0.9- in this case.
    So based on purchase info record/condition record which is already created with respect to this vendor & material System is picking this discount value as positive.
    So change this condition record/info record for a time for positive and then create the returns PO.
    Your problem will be solved
    rgds
    Chidanand

  • Return to Vendor...negative value preventing completing return (Urgent)

    Hello SAP Experts!
    We are having an issue with Returning to Vendor.  We are on SAP 4.7C. 
    When we are attempting to Return to Vendor (movement type 161), in the PO (ME21N), after entering in the material, quantity, and checking the box for "returns" item, the pet price becomes 0.  We receive a message stating that the net price must be greater than 0.  This only occurs if we check the box for "returns"...if we uncheck it, it works fine. 
    Why is this happening? 
    For example, when we check the box to make this a Return to Vendor PO, the amount is $120.00, but the condition value changed to -$120.00, which is making our net price equal $0.00; and this needs to be greater than $0.  We have a condition type, so we can manually altert the price, however for auditing purposes, we do not want to do that.  How do I fix this?  Is it something I need to look in customizing?...if so, where?
    Points awarded...thank you for your time!
    Best regards,
    WC

    Hi WC,
    I think movement type used will be 122,124.....
    Before you enter a return delivery with reference to a purchase order, you have to determine whether the goods were posted to stock or to consumption, or whether they were posted into goods receipt blocked stock. If you posted the goods to a particular stock type at goods receipt (for example, quality inspection stock), you have to return them from the same stock type.
    Also chk the link provided below :
    http://help.sap.com/saphelp_47x200/helpdata/en/a5/63351643a211d189410000e829fbbd/frameset.htm
    BR,
    Krishna

  • Return to Vendor...negative value preventing from completing return(Urgent)

    Hello SAP Experts!
    We are having an issue with Returning to Vendor.  We are on SAP 4.7C. 
    When we are attempting to Return to Vendor (movement type 161), in the PO (ME21N), after entering in the material, quantity, and checking the box for "returns" item, the pet price becomes 0.  We receive a message stating that the net price must be greater than 0.  This only occurs if we check the box for "returns"...if we uncheck it, it works fine. 
    Why is this happening? 
    For example, when we check the box to make this a Return to Vendor PO, the amount is $120.00, but the condition value changed to -$120.00, which is making our net price equal $0.00; and this needs to be greater than $0.  We have a condition type, so we can manually altert the price, however for auditing purposes, we do not want to do that.  How do I fix this?  Is it something I need to look in customizing?...if so, where?
    Points awarded...thank you for your time!
    Best regards,
    WC

    Hi WC,
    I think movement type used will be 122,124.....
    Before you enter a return delivery with reference to a purchase order, you have to determine whether the goods were posted to stock or to consumption, or whether they were posted into goods receipt blocked stock. If you posted the goods to a particular stock type at goods receipt (for example, quality inspection stock), you have to return them from the same stock type.
    Also chk the link provided below :
    http://help.sap.com/saphelp_47x200/helpdata/en/a5/63351643a211d189410000e829fbbd/frameset.htm
    BR,
    Krishna

  • Exchange rate in header of acc.doc after posting return to vendor

    Hi Gurus,
    in accounting document, when i recalculated amount in doc.currency & amount in local currency in item line was not same with exchange rate in header section...Anyone can explain to me why this miscalculation can happen ?
    Thanks

    Hi Zafar,
    exchange rate in header of this acc.doc was take automatically from table OB08 & the problem is in item line this acc.doc which is generated automatically after posting return to vendor the calculation amount in local currency was not take the exchange rate from header but from exchange rate when GR ( FLow : mvt 101--> mvt 122 ). so this is normal behaviour or there are bug ?
    thanks in advance

  • Return To Vendor process

    Hi ,
    Currently the business use two different process for sending parts to Vendor.
    1. First is the standard Sub contracting process where Raw materials is send to vendor ( 541 ) and vendor process the material and sends back ( 543 ) .
    2. Second is where the parts are send to Vendor due to defect ( 541)  and vendor will either send the material back after fixing ( 542 )or will inform to make credit memo if the parts send cannot be fixed . Althougth this process can be done from Return to Vendor process ( 122 ) , but the business had issues with open PO line item for the return part and raising the Credit memo as Vendor may sometime take time to  return the part which may be in months . Also there is no way for the business to know how much of material is lying with vendor at given point of time which is possible by ME20 in this case.
    The material planning is such that it consider the Stock at Vendor for Scope of check and hence for the first process this works out properly as it considers stock qty at Vendor's place  berfore generating PR , but for second process this becomes the issue as it also considers this stock at vendor place and does planning , but it should not coz this is part return to vendor for fixing and will come again not as assembly .
    How best the 2nd process be mapped without the 122 movement and is there any movement type which can take care of the second process and also we can have a seperate MRP planning accordingly .
    Regards,
    lawrei

    See 11.5.10 RECEIVING OPEN INTERFACE를 통해 RETURN처리하는 방법

  • Po-gr-ir and return to vendor

    Hi all
    I was create the PO and after I raise the  GR finally I was create the IR also after that some quantity rejected I want to return to vendor
    What Is the process and in mm module point of view  pls tell me the steps

    Hi
    there are two ways to return to vendor.
    You can create a return PO ensuring that you tick the 'R' field and then do MIGO as normal and the system will automaticallt do a return
    You can find the original doc number that was created when the 101 GR took place and do a MIGO against that using Return Delivery > Material Document.
    The movement type that will be used against the Return PO is 161
    The movement type that will be used against the mat doc is 122
    I hope that this helps

  • Error while doing Return to vendor (122) against PO through QA11

    While doing Return to vendor (122) against Purchase Order through QA11 we are getting the error as Deficit of PU GR quantity 20,000.000 TH: RPO1010 FCHN 007A.
    Steps we are followed.
    1. Created Purchase for Quantity 20 TH with activation of Unlimited Delivery.(TH Means UOM (Thousand)
    2. GR has taken for 20,000 TH instead of 20 TH because of Unlimited Delivery as activated.
    3. Usage decision as given total Quantity accepted based On Inspection Lot generated at MIGO.
    4. Stock has come to Un-Restricted.
    5. For Short fall of  Purchase Order Quantity Increased the PO qty to 20,020.
    6. For Return to vendor we transfer the stock from Un-restricted to Quality by MB1B Mvt type 322.
    7. While Transfer Inspection Lot has generated.
    8. Based on that Inspection Lot we try to do return to vendor through QA11 against the same Purchase Order.
    While doing the Last step we are getting the above error.
    Pls. Kindly look into this and tell me whether this steps are correct, if correct any settings needs to be done to over come the error or tell the Correct Logic to return the Material.
    Thanks & Regards
    Sathish
    Ph:9940518715

    My thoughts on this is that the original PO was for 20TH.  therefore you will only be able to return 20TH against it regardless of what you receipted.  This is because SAP copies from the original PO document for the return and not the GR material document.
    You can try to edit the original PO and increase the amount to 20,020 and try again.  But I don't think you'll be able to edit that since it was fully receipted.
    Your probably going to have to do a return for 20TH and then a separate, stand-alone return for 20,000 TH.
    Craig

  • Moving average price and returns to vendor

    Hello gurus,
    I’ve got a question concerning material valuation and returns to vendor.
    E.g. we have got 200 pieces of a material with a moving average price of 2 $ each.
    Now, what happens if I return 100 of those to my vendor who pays 2.10$ each for them?
    In my view, there are several possibilities:
    - Nothing happens, the moving average price is not changed at all, value of the goods is 200$ afterwards.
    - New value of the goods is 400$ - (100 * 2.10$) = 190 $. This would mean that the moving average price is 1.90 $.
    - Last delivered price was e.g. 2.20$, more than 100 pieces were delivered, so the new value of the goods is 400$ - (100 * 2.20$) = 180$, new moving average price is 1.80$.
    So my question is: What is standard in SAP?
    Thanks
    Jens

    This is what my thought is
    When you return the material to vendor then system take the same valuation as your MAP
    and when you buy new goods then it will count based on the
    e.g. existing stock is 100 and value is 1000 means valuation is 10 a peice
    in you but another 100 at 1200 then valuation is 2200/200 = 11
    When a material is subject to moving average price control, the system calculates values for goods movements in the following way:
    check this link
    http://help.sap.com/erp2005_ehp_02/helpdata/en/8f/d1de34e4cb2300e10000009b38f83b/frameset.htm

  • Delivery type determination in case of returns to vendor without return PO

    Hello Gurus,
    When we create Return PO, and when we want to created delivery for this PO , we assign delivery type RL to the PO in SPRO.
    Now when I return the material thorugh MIGO (without return PO) with delivery check box active, system determines different delivery type than RL. My question is that where do we assign this delivery type and how the system determines this delivery type in case of returns to vendor without return PO.
    Thanks
    Pravin

    Control parameters at movement type level determine the delivery type created. I guess you are using MvT 161. Try configuring delivery category for MvT 161 in OMJJ.
    Hope this helps.
    Rajiv..

  • Material return to vendor ( line rejection)

    Dear MM gurus,
    i have a scenario where material received is accepted at the time of Quality inspection. Same material issued to production but if found faulty has to be returned to vendor. Such line rejection occur daily and at the end of the weak rejection quantity are enough to be sent back to vendor.
    we are using two step process for GR i.e 103 followed by 105. following process does not allow material return through purchase return order i.e 161. creating return delivery via migo with movement type 122 against GRs is not viable as such returns will need reference to around 30 goods receipt for single return delivery creation.
    kindly suggest a solution were return delivery can be created  without reference of GR. Please ask for clarification if information here is insufficient.
    regards
    Avinash

    Hi Avinash,
    Please check the link
    http://help.sap.com/saphelp_470/helpdata/en/a5/63351643a211d189410000e829fbbd/frameset.htm
    Regards,
    Bijoy Kumar

  • CIN for Goods Return to Vendor

    Hi
    Could some one can let me know how to update the RG23 D register in case of return to vendor from depot plant.
    1.. ME21N - Create a Returns PO (Activate "Returns" indicator for PO line item)
    2. MIGO - Goods Receipt > Purchase Order (Returns PO) (Here system will hit Mvmt type "161" and you can also select Un-restricted/blocked stock from where you want to return the stock)
    3.. MIRO - Credit memo w.r.t. Returns PO.
    Please let me know the process in case of depot plant with respect to updatation of RG23D register.

    Dear,
    Please follow below mention cycle: -
    1.ME21N - Create a Returns PO Returns indicator for PO line item.
    2. MIGO - Goods Receipt Mvmt type "161" against return purchase order
    3. J1IS u2013 Excise Invoice Other Movements
    click on create button to create an outgoing excise invoice
    Take ref.doc.type - MATD, Doc Number - Material document NO Series Group, Excise Group, Vendor
    Check BED, ECS and SECess values to be reversed. and click on save button.
    4. J1IV - Post Excise Invoice.
    5. MIRO - Credit memo against. Returns PO.
    Note: - Before all process maintain Material chapter id and vendor excise detail in J1ID.
    Regards,
    Mahesh Wagh

  • Ship-to party for Returns to vendor delivery

    Hi,
    I have a problem for a return to vendor delivery wherein the Ship-to party value is incorrect. The value is suppose to be the one maintained in the vendor master. However in this case, the vendor master has no value. The system does not show any warning or error message.
    I would like to ask if there is no value in the vendor master, where else does the system picks up the value for the Ship-to party during returns delivery.
    many thanks,
    mylene

    For Sales Document..
    SELECT * FROM VBPA
                     INTO TABLE <ITAB>
                     WHERE        <YOUR CONDITION>
                     AND             PARVW = 'WE'.
    PARVW- If Partner Function eq 'WE' then it is ship to party, if 'AG' then sold to party
    Check Value table TPAR

  • PO with return to vendor

    Dear Experts
    Here is the scenario:
    1. inbound delivery is created from a PO with a 101 movement and item is received into warehouse.
    2. item needs to be returned to vendor
    3. Return delivery created using migo with movement code 122.
    4. Vendor is going to send item back and user wants to use the same PO but the line is not longer open.
    Is this normal for the PO? User expected to be able to create a second inbound for this item.
    Thanks in advance.
    Jo Anne

    Hi
    See when you are doing the goods reciept and then sending the material ( return to vendor ) using mvt 122 the result is same as that of what of 102 .
    The system automatically reset the delivery indicator and the n there will be open quantiy in the Purchase order .
    you can do the Goods reciept against this PO as a normal GR.
    Regards
    Sunny

Maybe you are looking for

  • How to load and display the external flv video files in dynamicly and the how to control the flv fil

    How to load and display the external flv video files in dynamicly using AS 3.0 and  How to control the flv file  add the play paus button and add seekbar. I have using to load the flv file following code var flvPlaceHolder1:MovieClip = new MovieClip(

  • Time machine spends too much time backing up

    Even when I have very little changed information to back up - say 15MB - time machine takes 10-15 minutes.   Every hour.   It spends like 3-4 minutes "Setting up", another 5-8 minutes "Backing up XXX of 15.2MB", and then another 3-5 minutes "cleaning

  • JOptionPane localiztion

    JOptionPane localization Hi How can localize JOptionPane Dialog to fit some local I am using Arabic in my application and and I use Arabic locale but JOptionpane is still in English instead of yes no cancel I want another words appera thanks

  • Hd 4000 bootcamp

    Having installed a windows Ultimate x64 on a 100gb patition, in the Device Manager appears only the Nvidia Gpu but not the Intel's HD 4000. All Bootcamp drivers and updates are installed and function properly. Booting to Mountain Lion both Gpu appeae

  • IT Policy and Firewall

    Good evening. I have a Blackberry Curve 8530. I am trying to use it as a PDA only. I am not able to install and setup ePocrates and Skyscape for my medical reference apps. The message that I keep receiving is; "The application EpocratesApp has attemp