Dear All,
My client want to revaluate production orders at actual prices, but we have only one costing version for plan and actual. Exactly I don't know how to revaluate production orders. As we have only one version, I want to change the activity rates with actual rates in KP26 in order to revaluate the production order. But even I change no revluation is taken place. Any customizing has to be done or what is the procedure to revaluate production orders. I changed the costing version settings to allow revaluation with own business transactions.
Please help me.
ramesh b

Use transaction CON2 to revaluate the production order.
But before revaluation you have to run KSii to calculate the actual activity price. The price  calculated here will be used for the revaluation.
I dont think there is need for any configuration if you have the plan activity prices set up and ready to go.Manually changing the price in KP26 will change th plan price but not revaluate it.
Keep us posted on the results
Happy to Help
Naveen

Similar Messages

  • Revaluation of Production Order

    Hi,
    Revaluation of Production order.
    I am trying to revaluate the production order with actual activity price.  Done KBK6 to enter manually to update the actual price.  MFN1 is done to revaluate the order. But Actual activity value not changed in Production order.
    Activity type property : -  price indicator 1, Actual price indicator 7.
    ML activation :  option 1, selected ( update price but not relevant for price determination)
    Please help
    neeraja

    Hi
    Check your Plan Version OKEQ - Version 0 > CLick on Settings for Each Fiscal year > Select current fiscal year
    Go to PRICE CALCULATION Tab
    Check if you allowed REVALUATION.. (Select "Own Business Transaction")
    Br, Ajay M

  • How to get Production Order wise Actual Values

    Dear CO Experts,
    How to get Actual Values (Raw Material Issue, Activity Confirmations & OH Calculations & Goods Receipts from Production) each Production Order wise ?
    My Scenario is Product Cost Collectors (PCC)  with Production Orders.
    If we select above scenario Production Order is Statistical and PCC is real cost object.
    For PCC is Period wise we can track the cost Periodically in individual Material.
    But my client is asking how to see the each Production Order wise Actual values. Is there any T.Code ??
    In Production Order I am able to see only Plan values (CO03).
    Waiting for your favorable reply.
    Regards,
    KBR.

    Hi Bhaskar
    You are in Alaska and you wanna eat vegetarian food
    You cant get values at Prod order level if you have chosen PCC as cost object.... You will only get Qty at Prod order level
    To get a bird's eye view of costs incurred in PCC, execute report MCRY with PCC as the input...  MCRX shows only Qty info for components
    br, Ajay M

  • Report for production order with actual and target cost for each

    Hi
    Is there any report that gives me the list of all production orders in a month with its respective actual and target costs?
    I can use COOIS to get a list of production orders, then double click on the prod order, then click on goto and then to cost analyis.. but can i avoid going through all this and get a report with the details i need?
    thanks in advance

    Thanks a lot for that.
    I'm a little confused with the columns in the report.
    Which columns should I keep for my requirement? -
    Production Order
    Total Target Cost
    Total Actual Cost
    Total Actual Qty
    Total Target Qty
    Thanks

  • CALCULATION OF ACTUAL PRICE CALCULATION  - KSII

    Dear Friends,
    We are using Make to Order scenario and NOT USING Sales order based costing, I would like to calculate Automatic activity price calculation and revaluate my production order with actual prices (MFN1), for this I need to create & assign splitting rules to cost centers & follow the t.codes KSS2, KSII, KBK7 (DISPLAY) and finally MFN1.
    For Calculation of KSS2, how Plan Quantity has to be decided, this because for calculating Operating rate system take the formula as below, whether the below formula is correct?
    Actual quantity/ Planned quantity * variable price
    If for a cost center, postings are happened in FI for 10000/- then how system calculate & segregate this?
    if possible with an small example, when checked in KSS2 it shows the amount of postings from FI with cost elements.
    But when we checked t.code KSII it was showing the some different Actual Activity and variable price. How system takes the Actual activity and Variable Price and is there any report to check this?
    please guide me
    Regards,
    Sandeep
    Edited by: sandeep jain jain on Nov 2, 2009 4:15 PM

    Hi Paolo,
    You were exactly right that it was rounding off.
    But still am not able to get the calculation working for me.
    In Cost Center Report Actual/ Plan it shows
    Debit Assessment Cost Element 10000
    Credit Machine Hour 458.16-
    Credit labour Hour 124.96-
    over/under Absorption 9,416.88
    This are all actual cost.
    When i run KSII the result is as below
    Oty  Object                        Name                    AUn              Activity Qty Total Price     Price(Fixed) PUnit
    ATY MBX273/L1                Testing CCTR         H                 1.666         3,001.20         3,001.20      1
    ATY MBX273/M1                Testing CCTR         H                 1.666         3,001.20         3,001.20      1
    I am not getting how this value  3,001.20  is calculating.
    Kindly help me to under stand this
    Edited by: lolu jo on Oct 28, 2011 3:57 PM

  • Actual activity price not updating in production order

    Hi All,
    I am facing one problem, that actual price for activities are not updating in production order while plan price are updated. Earlier both plan and activity prices were getting upadated but now actual price is not updating for any material. I have tried at the same material also but it is not getting updated. Actual hours are updated in confirmation of production order but not price. If somebody could suggest the reason it will be great.

    Dear Nitin,
    Thanx to all for valuable input. Problem is solved.
    Nice to see That your problem is solved
    But Can you let the Forum Members know
    where was the exact problem & how it is solved
    Regards
    Madhu Kumar

  • Revaluation of Activity type is not getting updated in Production Order

    Hi,
    I have run KSII , for actual activity price calculation. After this , the revalution of production orders was done.
    But I am not finding any entry in Production order with a value of variance between Actual Price and Plan Price of the Activity type.
    It sould come in the production order.
    What can be the reason?
    In OKEQ, for the Version '0' and the fiscal year, Revaluation has the entry ' 1.Own Business Transaction'. I hope this is correct.
    But still the revalaution line item is not showing in Production Order.
    Please help.
    regards
    Kamlesh

    Hi Paolo,
    Yes, MFN1 ran perfectly and I am also able to see the details in the screen.
    My concern is, this revaluation should also have affect on Production order, thats what not happening.
    Or let me know where can I see the affect of revaluation on Production orders.
    regards
    Kami

  • Actual Costs for Production Order

    Hi All
      I have a scenerio where they dont want any product costing methods say WIP,Variance calculation & Settlement.
      When the Goods receipt is done for production order the actual costs and the Activity costs to be valuated.
    Regards
    Jayshankar.A

    Hi,
    In our case the Standard price is updated in the material master. For this, you need to create a costing estimate using T-Code CK11N and update & release in CK24.
    When CK11N is executed the standard price is calculated for the material by taking Moving Avg Price of RM (Price indicator V) and the activity costs are calculated as per data given in KP26. These cost components are added and a final cost estimate is prepared, which is updated using T Code CK24.
    the pre-requisites are:
    1. BOM should be maintained.
    2. Routing should be made.
    For executing the same procedure for all the materials, you can use T Code CK40N.
    Hope this is what you were looking for.
    Revert for further details.
    Regards,
    Rohit.

  • Material price getting picked incorrectly in production order

    Hi,
    The FG is maintained with price control V. However, at the time of GR for production order, the standard price is getting picked instead of moving average price. Why can this happen? Note that the material quantity was zero before the GR for production order. Can this be the reason?
    I checked that there no current std cost estimate for the material and the transfer control is also deactivated. Valuation variant is set up to read price as per price control.
    Moreover, when I changed the price control on material master to 'S', system picked up the moving avg price, which is even more surprising. Note that at this time the stock of material was existing in the plant.
    Can someone explain this behavior?
    BR
    Abhinav

    Dear Abhi
    Just to add Ajay Sir's reply: at step "Define Goods Received Valuation for Order Delivery" you need to select your valuation variant.
    Further using price control 'V' for inhouse manufactured materials i.e. FG and SFGs may seriously distort your price in material master. As at the time of settlement of orders system looks and compares stock of material with individual orders and post the variance accordingly. If suppose you have  10 orders in a period and  each order for 10 qty and at the month end you have a stock of 11 qty, and your each order is having a variance of Rs10/- then at the month end you will end up with a mat price of Rs.20/- (say base MAP) + 10x10 (variance value for each order) i.e. total MAP will become Rs. 120/- for this material. So kindly have a serious look and then go for this kind of decesion.
    For this reason apart from other reasons SAP recommend 'S' for in house materials.
    Regards
    Rajneesh Saxena

  • Revaluation at actual price

    Hi Experts,
    I want to revalue multiple production orders but not all, that's why cannot run revaluation at plant level (CON2 or MFN2). Is there any program or transaction code to execute revaluation on multiple production orders?
    Regards

    I found the programs where multiple production orders or product cost collectors  can be selected for revaluation:
    RKAZMFN2
    RKAZCON2

  • Costing of product with last purchase price

    Hi
    how would be possible to get the Costing through CO with the last purchase price of the Product .
    suppose one product is having nos of SFG & RM.
    Rgds
    Pankaj Agarwal

    hi
    Is it that the the system has to pick up the last purchase price cost for standard costing run or while executing the production order, if it is while production order  update material price as planned price in material master using Z program and use planned price as strategy for valuation variant in actual costing variant.  But this is little bit cumbersome every time you have to run the z program for every purchase order for that raw material and if the prices are highly volatile  input price variance will be very high
    krishna

  • Report to view Production order wise atcual cost when PO is assigned to PCC

    Hi All,
    Can anyone help me to get the report for production order wise actual cost incurred when that Production order is assigned to PCC (Product cost collector).
    Is it possible through Summarization hierarchy or Product drilldown?
    If yes, can u explain the steps.
    Regards,
    Durga.

    Hi Bhaskar
    You are in Alaska and you wanna eat vegetarian food
    You cant get values at Prod order level if you have chosen PCC as cost object.... You will only get Qty at Prod order level
    To get a bird's eye view of costs incurred in PCC, execute report MCRY with PCC as the input...  MCRX shows only Qty info for components
    br, Ajay M

  • Validation of material BOM quantity at the time of production order confirm

    Hi,
    I want validation on material BOM ,when i confirm production order.
    Actually when i am going to confirm my production order by tcode CO11, In this screen,i click on "Goods Movement" button. According to confirmed quantity , consumed materials will display. Here i can change material quantities. And here i want some validation. I there any user exit for this screen.

    Hi,
             Exit Name Description
    PCSD0001 Applications development R/3 BOMS
    PCSD0002 BOMs: Customer fields in item
    PCSD0003 BOMs: Customer fields in header
    PCSD0004 BOM comparison
    PCSD0005 BOMs: component check for material items
    PCSD0006 Mass changes user exit
    PCSD0007 Check changes in STKO
    PCSD0008 WBS BOM: Customer-specific explosion for creating
    PCSD0009 Order/WBS BOM, determine URL page
    PCSD0010 Order/WBS BOM, determine explosion date
    PCSD0011 Knowledge-based order BOM, parallel update
    PCSD0012 Customer - Mat. number/mat. number during material exchange
    PCSD0013 Customer-specific processing of an explosion for BOM browser
    PCSD0014 Knowledge-Based Order BOM: Status
    BADI's are
    WORKORDER_CONFIRM
    WORKORDER_UPDATE
    WORKORDER_GOODSMVT
    <b>Reward points</b>
    Regards

  • Error in cost calculation for production order

    Dear All,
    I got error of cost calculation while release of Production Order due to price of some material is not mantain .
    What will happen if I release , save the Order with error & do Good Issue ???
    Ishwar

    Dear Ishwar,
    Check the log's created for costing and rectify the same.
    I feel its better to rectify the cost related errors and then release the production order and proceed to Good's Issue.
    Check whether there is a MAP for all the Raw-materials and an origin group in costing 1 view.
    The Finished product must be having a standard cost estimate that's valid for the current period.
    Revert back in case of any more help needed.
    Regards
    Mangalraj.S

  • Production order settlement info

    Hi,
    In production order settlement category  is MAT.Some times it is CTR .But costing varient is PPP2.In settlement configuration i check that Allocation structure is A1 ,PA transfer sture is A1 butdefault object trype  is blank . So how system take it MAT some times CTR sometimes and wt is the impact and wt is the meaning of this thing when production settlement i is happened  ?
    Thanks &  Regards,
    Debashis

    HI,
    You can check order type in the Production or Maintenance order as Type.
    Check the Order Type in T.code KOT2 and view details for your order type in which you can see the settlement profile. The settlement profile(T.Code OKO7) will have the Default object MAT or CTR etc.
    Costing variant doesn't have any relevance.
    Generally all maintainence order will be settled to cost Center.
    And Production Order will be settled to Material.
    At the settlement all the costs incurred for the production order will be settled (Moved) to respective Finished product if it is MAT and for Cost center if it is CTR.
    The accounting entries for production order will be
    Price Difference F.G A/c DR
          To Change in Stock A/c Cr
    or Vice versa.
    Regards,
    Raj