Revision Level in Material Master

Hi All,
What's the purpose of Revision level in Material Master and some times we see it in PO material tab.
What's the Business Application of this.
Please help.
Thanks

Hello Rahul ,
Please see the following link for more information regarding the Revision Level in Material Master.
http://help.sap.com/erp2005_ehp_03/helpdata/EN/ff/5160a249d811d182b80000e829fbfe/frameset.htm
A revision level identifies a specific change status of a material with reference to a change number. It is used, for example, to identify changes affecting other areas such as Production.
You generally assign a revision level when processing a material BOM (bill of material created with reference to a material master record). However, you can also assign a revision level when processing a material master record.
You can display a revision level assigned to a material by choosing Display revision level on a departmental data screen in a material master record.
I hope this information has been helpful for you.
Best Regards,
Frank

Similar Messages

  • ECM revision level in material master record

    Hi experts
    I need to remove the last revision-number (REVLV) in a a material master record.
    The ECM is not relesead and we have used tcode MM02.
    I have seen that the tcode CCUNDO check the planned changes with tcode MM12.
    Thx in advance
    Marco

    Hello Rahul ,
    Please see the following link for more information regarding the Revision Level in Material Master.
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/ff/5160a249d811d182b80000e829fbfe/frameset.htm
    A revision level identifies a specific change status of a material with reference to a change number. It is used, for example, to identify changes affecting other areas such as Production.
    You generally assign a revision level when processing a material BOM (bill of material created with reference to a material master record). However, you can also assign a revision level when processing a material master record.
    You can display a revision level assigned to a material by choosing Display revision level on a departmental data screen in a material master record.
    I hope this information has been helpful for you.
    Best Regards,
    Frank

  • Header and Item level in Material Master

    Can some one explain abt the header level and item level in Material master.
    Thank you
    Appreciate your Help

    Hi,
    As explained by Jurgen, There is no term like item level and header level as such in respect to material master.
    But just for convenience per say, you may call like below.
    MARA :- Header level --( Client level data)
    MARC,MARD,MBEW,MARM,MVKE :- Item level -- ( Organizational element level data).
    Hope it will help u.
    Deepak

  • Revision level of material automatically assign to purchase order

    Hello all,
    when I create a new purchase order for a material, is it possible to assign the latest revision level of that material (material master - basic data 1) automatically to the Revision level field on item level - Material data for the material in the PO? Meaning when I create the PO with this material, SAP automatically fills this field with the revision information from the material master?
    Thanks
    Anne

    It should pick latest revision level.Becuse PO get all data from material master.

  • Revision level of material

    Hi All,
    I want to find the REVISION LEVEL history of a material.
    Material master (MARA) table stores only the current revision level it does not contain the previous revision level history.
    Can any one please tell me the table name which stores the revision level history of the material.
    Thanks & Regards
    Vijay

    Hi,
    You can check the table AEOI for the history of the revision levels with AETYP = 41 & OBJKT = matnr.
    Hope this helps.
    Best Regards, Murugesh AS

  • Batch Material level and Material Master

    Hello,
    We have defined the batch level on level "Material" because we want the batchnumber to be unique for a material - independent of the plant it is used in.
    I would like to know if with this setting of the config, the material X marked with the flag "Batch Managed" in its master record, should be managed with batches in all Plants or is it posbilbe to exclude some plants (for instance plants belonging to other country) from managing the material X in batches?
    Thanks for any reply,
    Aart.

    you can only exclude plants from managing batches for a common material if your batch level is plant level.
    with material level, all plants have to manage a common material with batches.

  • Read revision Level of material with remote enabled module

    Hi all,
    I want to know, if it's possible to read the latest revision level or the revision level of a specific date of an material via a function module wich is remote call enabled?
    I have found the function modul:
    REVISION_LEVEL_SELECT
    this does exactly what i need, but it is not enabled for a remote call. Is there any other function modul I can call remotely to get the revision level?
    Thanks for any help
    best regards
    Matthias Brück.

    yes, thats right and exactly my problem. I have testet this internal FM via transaction se37 and got exactly what I need.
    So, I'm looking for an FM wich I can invoke remotely and returns the Revision Level of the material.
    But, thanks for your hint!

  • Change sequence of organisational levels in Material Master

    Hi,
    Can we change the sequence or remove any Organisational element such as Plant, Storage Location, Sales Organization, Division etc. before creating Material Master.(Organistional level dialog box)
    Please suggest if it is possible.
    Regards,
    Goraksh.

    Hello
    Go to MM01 and to to the 'Defaults' tab and select the 'organizational levels'.
    Give the default values and tick the ' organizational levels only on request'.
    Then the organizational levels will be shown only if u click organizational levels in the view selection box.
    Hope this helps.
    Regards
    Gregory Mathews

  • Revision level not appearing in material tab of purchase order

    hi
    I have matained revision level in material master but it is not appearing in material tab of purchase order and print preview of purchase order
    regards
    Badari

    Hi, If u have created proper change no in CC01 with assigned object material with proper validity period u can give revision level to material.
    In order to reflect the current revision level on PO printout, the coding in PO print program should be designed accordingly to pick the latest revision level. PO output needs to be re-issued so that the new output can pick the latest information like PO revision level from the master.
    Refer below link also for more information,
    [Revision level in purchase order|Revision level in purchase order]

  • Maintain revison level at Material Serial Number

    Any pointer on how can I maintain and track the revision level by Material Serial Number? 
    All SAP information I have seen is maintaining revision at Material master.

    Thanks for responding. My understanding is that ECM only maintain revision level at Material Master but not at the Material Serial Number.  If we use ECM, am I able to track revision level by serial number. I cannot find a revision data field in the Material Serial number record.
    Currently, we create material master id with part-number/rev to track the revision at serial number record.

  • Revision Levels

    Hi,
    We are creating change number using CC01 and using this change number we are creating a new revision level for Material Master in CC12. We notice that only capital letters are available for revision levels. Client requirement is along with capital letters like A,B etc, small letters like a,b etc are required as revision levels.
    How can this be incorporated by standard SAP?
    Thanks & Regards,
    Ramagiri

    Dear
    can you tell me why do you need this?

  • Create Material Master Revision Level using CC02

    Dear oss ,
    Using CC02 for a change number I can view object material and I can insert a new material. The revision level field is greyed.
    Can I have a chance to create  revision level for a material directly using CC02 ?
    Thanks.

    If you want to create revision level of Material then use t-code CC11. I hope it would help you.
    Thanks!!!

  • How to define product revision numbers in the master material data

    Hi,
    is it possible to define product versions or revisions in the material master data.
    Example: A product is produced and is developed on through the years. Their exists a Version 1.0, 2.0 and 3.0.
    Is it possible to map all of these versions to one material number or is there a versioning of products supported in another way?
    Thanks
    Torsten

    Hi,
    many, many thanks. That was exectly what I was looking for!!!
    Bye
    Torsten
    P.S.: the different perspective on SAP NW 7.0/2004s starting from IT-Practices=>IT-Scenarios=>Usages Types is great and should not be restricted to the NW Application stack, but also to SAP ECC and its modules starting from a Business-Practice=>Business-Scenario=>relevant parts of the customizing. IS there something like that out there????

  • Material revision level

    Hi,
    What is the procedure to assign Revisin level to already existing Material .
    and tables where Revision level is reflected
    Thanks

    My requirment is to   assign new  Revision level to material and change revision level of already existing revision levels of material.  and to display Purchase order with material with revision level.
    for already existing material with  revision level , Purchase Order and Delivery Schedule is showing Revision level.
    (Revision level is assigned using CC11 and stored in table AEOI).  it is updated to table ekpo.
    for PO and Delivery schedule , m picking data field from EKPO-REVLV.
    and it is working fine. PO an DS shows REVISION LEVEL field.
    ( above case was during implementation )
    but for last one year no one updated the revision level  of material.
    now requirement is to update the material with revision level.
    But the Problem when i try to assign new revision level to material or want to change the already existing revision level of material then ,it is assigned to material with CC11 and CC12 and  shown in table AEOI . but revision value is not updated to table EKPO for field REVLV . so by thins  PO and Delivery schedule is coming without  revision level.
    how to reflect revision level assigned to material to table EKPO ? may be m missing some step ...
    i checked OS54 table
    my OS54 settings are
    REV LEV ACT                   (active)
    Ext. Revision Level            (inactive)
    Higher REV Level              (Active)
    Rev Lev Automatically      (inactive )
    Effect  Profile                    ECN00001
    Please give me kind suugestions ....
    Thanks

  • How to map revision level materials to already created inspection plan?

    Dear All,
    I have created single inspection plan for many existing raw materials. Now it has been found that each raw material have different revision level as well as valid from date.
    My inspection plan is created on 02.07.2014 and each raw material has different revision level with valid from date which is also very old (like 11.03.2012 for revision level 09).
    My Requirement is:  how to correct my inspection plan?,  so that it will work for each assigned raw material and there will not be any material revision level wise problem created for the inspection lot so that my inspection lot should be created in REL status in QA32 transaction i.e. inspection lot is assigned automatically as per standard SAP functionality.
    Thanks,
    Narresh

    Hi Amol,
    Thanks for your reply.
    In this business scenario, we are not creating inspection plan for each raw material because there is similarity in inspection for 40-50 raw materials and total number of raw materials are around 500. This will be very difficult and unnecessarily data creation in the system.
    As per my understanding revision level is for material master revision and if material master changes then how it affect so much on inspection plan? also is it means that for every revision in future we will have to create new inspection plan?  hence I believe that if I will make back dated inspection plan for raw materials then it may work. Is my understanding is correct?
    Expecting much better solution from QM experts.
    Thanks,
    Narresh

Maybe you are looking for

  • Do I need to upgrade to OS 10.4.10  ?

    From my software updates, I think I need to upgrade to 10.4.10. It says I can if I have a Power PC Mac, or Intel-based Mac. I THINK I have a Power PC Mac. Is this going to cost me more money to upgrade or just time.... (I don't have fast internet ) W

  • Report on Account Balance

    Hello Friends, Please can you let me know, if there is any transaction to generate a report on consumer ledger account. I am aware of FPCC0002, but this generates a correspondence letter. If there is a way out to get a output in report format. Regard

  • Does WCF-OracleDB adapter support XMLType data for table select operation

    I am getting this error When I do the consume adapter service for Oracle table select operation on one of the tables which has XMLType column. It's working fine for other tables.  Microsoft.ServiceModel.Channels.Common.MetadataException: Retrieval of

  • Mighty Mouse Functionality in Bootcamp?

    Hi, I use a Macbook 2.16ghz with Vista in Bootcamp. When I use the side buttons on my wired mighty mouse in Windows Vista, it activates as some sort of back button or "click" for whatever prgram I'm using. Does anyone know how to change the functions

  • MIRO - Credit Memo- Unable to match

    Hi Gurus, One  of our supplier issued a credit memo which relates to two POs. One is a return PO(credit note) and other a normal PO. Vendor has issued credit note with Net figure. Both POs are not related. Normal PO ( GR)   100 Return PO(GR)      (-2