Rework process for Customer returns in process Industry.

Hi Gurus,
We are working in a process Industry. The process is here we do
Sales order
MRP run
Process order
Process order confirmation
delivery
billing.
Now the scenario is, once delivery done, customer returns the goods for rework.
To complete this process, how can i go ahead and whether this will reflect in the PP module or not & how can we interrelate the SD with PP in this regard.
     Note: we dont have the CS module now
Thanks.
Thyagarajan.
Message was edited by:
        thyagarajan krishnamurthy

Hi amith,
for return process you have to follow RE document type and LR for pgr
while coming to excise you should have to do J1IEX without purchase order the the values of excise will be reversed .
it should resolve your issue
bvdv

Similar Messages

  • AFE process for Customer and Investment Project

    Hi All,
    My client want to have AFE process for Customer as well as Investment Project Creation.
    Once, AFE is approved a project should be created along with project plan valueswith approved values in AFE request. Also, in case any supplement need to project also should have a similar AFE approval process. For this client, there is No IM module implemented as such.
    Want to know how we can map this scenario in SAP.
    Thanks in advance.
    Regards,
    Atul R. Rajmane

    IYou can make use of simulations...create simulation version before creating operative project...you may create more than one simulation for various cost plan scenarios..you can plan revenue in simulation also for customer project...whoever gives approval for project expenditure.... they may compare the cost of the simualtion version and approval can be transfer of simulation version to operative version....Also, you can use this for supplements...create simualtion during course of project...then add actvitiy, material..etc., do the cost analysis...and provide the supplement budget accordingly to the new planned cost.

  • QM steps for customer return material (mvt 655)

    Hi Qm Guru
    When material return from customer due to some defect (material defect some reason like moisture or rain).then material comes in quality inspection. As for example
    after Return from vendor (movement type 655)  material comes in quality inspection. suppose  50 kg comes in in quality inspectionu2026and I want to send 10 kg in unrestricted and 40 kg for reworku2026what are steps and how I will do this process
    Kindly suggest me pleas
    Regards
    aqueel

    Hi,
      1. Maintain Inspection Type 05 in Material master.
      2. Don t Maintain any Inspection lot Origin in SPRO  > QM > Quality Inspection > Inspection Lot creation > Inspection at shipping > Assign Inspection lot Origin  to Delivery type.
    3. Create Inspection Plan for Customer return with usage 5.
    4. Then create return delivery with respect to sale order no or Document no.
    5. Do PGI.
    6. Now a lot will be generated with stock posting option.
    Regards,
    Muthamil

  • Import declaration for customer returns

    Hi! Does anybody know how to create import customs declaration for customer returns (return sales order --> return delivery --> GI for returns) in GTS? Standard GTS can handle only the PO --> inbound delivery --> GR process, as if this would be the ONLY import process. BR Martin

    Hi Martin,
    The System is smart enough to recognize if a document is inbound or not. Just set it as Relevant for transfer to GTS (in the ERP Plugin)  and in GTS map the document type to an Inbound document type (SAP Global Trade Services / SAP Customs Management / General Settings / Document Structure / Assignment of Document Types from Feeder Systems / Assign Document Type at Feeder System Level (or Assign Document Type at Feeder System Group Level) and map it to CULOIM) and it should do the trick.
    If it does not work send me the error messge from transaction SLG1.
    Regards,
    Marc

  • For Customer return, other adjustemnet or Add. excise required ?

    Hi All,
    While my customer return the finished goods I am making sales return order ,did the PGR & make the credit note.
    Now I want to adjust the excise duty through J1IH
    In j1ih which option I have to choose <other adjustemnet> or <Add. excise>
    In Add. Excise tab. the Gl account detremine are :
    C 0013113920 115.00 CENVAT clearing
    D 0024822000 5.00 CENVAT Input SECess
    D 0024820000 100.00 CENVAT Input BED
    D 0024821000 10.00 CENVAT Input ECess
    Whereas In case of Other adjustment tab GL account determine are
    C 0024822000 5.00 CENVAT Input SECess
    C 0024820000 100.00 CENVAT Input BED
    C 0024821000 10.00 CENVAT Input ECess
    D 0013113920 115.00 CENVAT clearing
    Please suggest me which option is correct.......Other adj or Add excise tab.
    In my opinion it should be <Add. Excise> where Clearing account is credited and all rest debited.
    Please Give me the solution
    Regards
    SAGAR

    Dear Lakshmipathi,
    As directed by you I did & come to know that it's triggering MRDY EX TT if I go through J1Ih < Other Adjustment>.
    So now I Created one Sub Transaction Type -
    CR - Customer Return.
    & in Specify Excise Accounts per Excise Transaction I  Maintain
    MRDY    CR    Credit     Cenvat Suspence Account
    MRDY    CR    Debit      RG 23 BED Account
    MRDY    CR    Debit      RG 23 ECS Account
    MRDY    CR    Debit      RG 23 At1 Account
    & maintained thier GL's.
    Checked in
    Is this right for Customer Returns????
    Regards
    SAGAR

  • Rework order for FG return from customer

    Hi Experts,
    Please help me in following scenario :
    I have made delivery & Invoice for sales order for quantity 800 unit. Out of that customer returned 600 unit bcoz of poor quality.
    I made return order & did post GR to rework storage location.This stock is return stock in MMBE. Now I have to process on same FG and bring its to unrest.use stock. How to map this in PP
    Regards.

    Dear
    Try the following rework order scenario:
    1)Normally rework order is created by t-code CO07
    2) in CO07, give plant then order type (rework order type) then enter
    3) Material description, quantity to be reworked then date enter
    4) system will ask u reference operation set (it should be created before only in CA11)
    5) then give the reference operation set Number then system will take u to settlement Rule
    6) here for CAT give as order, then in settlement receiver give your header order number then percentage as 100 %
    97 then click on component overview icon, then give your BOM components (which to re-worked & assign an operation to it)
    8) then save the order
    9) then do the confirmation to re-work order
    10) then do GR to header order & settlement will take place to header order only not to re-work order
    Note : for rework work, GR will not take place

  • Customer return material process

    Hi,
    I want to know the the process for below 2 cases we have a manufacturing plant
    1:For factory sales we follow the process
       VA01 > VL01N > VF01 > J1IIN > VF02 release to accounting
    now after some days  if customer dont want the material they send the material back,  thhen wahat is the std. process to take the materila back in stock  also customer balance should also get reduce for that invoice.
    2:Some time for exibition we want to send the material out of factory for tempoprary basic  after completion of exibition we want to take that stock back in our own stock is it possible withotu any customer to do this process,  what is the std. process for this.
    regards,
    zafar

    For customer returns, you need to create a return order referencing the parent billing document, do return delivery for the goods received and raise credit note to that extent so that system will take care of necessary adjustments in FI.
    With regard to exhibition, check my suggestions in the below threads
    [Re: What is the use of the T code VLMOVE|Re: What is the use of the T code VLMOVE]
    [Re: Exhibition |Exhibition]
    thanks
    G. Lakshmipathi

  • Customer return - automatic processing

    Dear experts,
    At my customer there is a requirement to automatically create a customer return delivery, goods receipt posting and credit posting when saving a customer return order. The process should be as follows:
    1. Create customer return order (VA01) with reference to the original invoice
    2. Create a return delivery (automatic) with reference to the return order
    3. Post goods receipt against return delivery (automatic)
    4. Book credit note (automatic)
    I'm not sure if this is standard SAP and where I should configure the above,
    Your comments are much appreciated,
    Kind regards, M

    Hi,
    This not possible in std SAP although you may have a return delivery created automatically by checking Immediate delivery in VOV8 for RE order type, you will have to do PGI and Credit memo manually or by using function module/BAPI.
    Take the help of your ABAPer to find out how it can be done.
    PGI can be created using BAPI_GOODSMVT_CREATE
    Billing document/Credit memo can be created using BAPI_BILLINGDOC_CREATE
    You may also schedule PGI as a background job through VL06O and Billing through VF06 which would run everyday and check return deliveries pending for PGI and completed deliveires pending for credit memo creation.
    Make sure you dont have any delivery or billing block in your return orders and automatic posting in credit memo so that accounting document also gets created.
    Regards,
    Amit
    Edited by: Amit Iyer on Jun 8, 2011 2:45 PM

  • GR Slip for Customer return Orders *(Order Type : RE)*

    Dear Experts,
    Please help me out in below requirement.
    Customer return Orders (Order Type : RE) are entered and Goods Reciept done through Outbound Delivery.
    Now, how can I do the set up to rpint the GR slip (WE03)?
    I can see that it aleardy works fine for Goods recipet against a PO. But how is it done for Sales Orders?
    Also let me know can I use MB90 only to process the GR slip?
    Please guide me
    Regards,
    Shetty

    you can  reprint the output in VL03N, check for the output types & reprint using issue output to.
    Rgds
    ilango

  • No valuation for customer returns material

    HI,
    when goods receipt is done for the returns and repair process thare should be no valuation done for the material returned by the customer as the material is a returnable material to the customer.
    how to track this in SAP.
    REGARDS,
    RAJESH KUMAR RAJU,
    9986085455

    You cannot use the same material (the material that has been billed) in returns order because if you do not want the material to be valuated then you have the material type as UNBW.
    Hence create a new material with material type UNBW and use this materia in the sale order.
    Regards,
    GSL.

  • Down payment process for Poland, new business process or not ?

    Hello,
    I'm a little bit confused about implementation down payment process for Poland.
    The OSS-notes 818079 and 1007635 describe a solution for this.
    How do I have to implement the correct down payment process for Poland ? Do I have to create an extra business process with new sales order type, new billing type, separate calculation procedure, new output type and so on ?
    Or is it possible to use existing business processes in sales and distribution for down payment processes ?
    Thanks in advance
    Holger

    hi,
    Check the process for down payment processing
    The following Customizing settings have to be made for down payment processing:
    Settings for the billing plan - To activate the billing plan function, maintain the materials, for which you wish to process down payments, with item category group 0005 (milestone billing). This gives the item type TAO via item type determination. The item type TAO calls up the billing plan function.
    You need to implement the following activities in the billing plan for down payments:
    Maintain deadline category - This determines the billing rule (percentage or value down payment) for the down payment request. The system assigns billing type FAZ (payment request) defined in the standard system with billing category P. (For the billing type FAZ there is the cancellation billing document type FAS in the standard system).
    Maintain the deadline proposal - Use the down payments that are due for the proposed deadlines.
    Maintaining a Pricing Procedure with the Condition Type AZWR:
    In the standard system the condition type AZWR is delivered for the down payment value already provided but which has not yet been calculated. You must include this condition type in the relevant pricing procedure before output tax.
    Enter condition 2 (item with pricing) and the calculation formula 48 (down payment clearing value must not be bigger than the item value) for the condition type AZWR.
    Before the condition AZWR you can create a subtotal with the base value calculation formula 2 (net value). If the condition AZWR is changed manually, you can get information on the original system proposal from the subtotal.
    Maintain the printing indicator - The pricing procedure can not be marked as a transaction-specific pricing procedure (field Spec.proc.) The condition type AZWR has the calculation type B (fixed amount) and the condition category E (down payment request / clearing).
    Maintaining the Billing Document - In the standard system there is the billing type FAZ (down payment request) and the billing type FAS for canceling . The down payment is controlled using the billing category P of the billing type. A billing type becomes a down payment request when the billing category P is assigned. You have to maintain blocking reason 02 (complete confirmation missing) for the billing documents and assign it to billing type FAZ.
    Copying control - Copying requirement 20 must be entered in copying control at item level for the down payment request. In the standard system the order type TA for copying control is set up according to the billing type FAZ for the item category TAO.
    Copying requirement 23 must be entered in copying control at item level for down payment clearing. In the standard system the order type TA for copying control is set up according to the billing type F2 for the item category TAO.
    Financial Accounting settings - A prerequisite for down payment processing is that the account is assigned to the underlying sales document. To do this, change the field status settings in Customizing as follows:
    Set reconciliation accounts (transaction OBXR) - For the `received down payments' and `down payment requests' from
    the G/L accounts you have selected, you should assign the field status definition G031.
    Maintain accounting configuration (transaction OBXB) - For the down payments (posting key ANZ in the standard system) and the output tax clearing (posting key MVA in the standard system), you must maintain the posting key.
    You must also carry out a G/L account number assignment for the tax account.
    Maintain the posting key (transaction OB41) - For posting key 19, set the sales order as an optional field !!!
    Maintain the field status definition (transaction OB14) - For field status variant 0001, field status group G031, set the
    sales order as an optional field !!!
    Assign the company code to the field status variants (transaction OBC5)
    chandu

  • Regarding user-exit for customer return order in sales order creation

    Hi,
    My problem is when sales order type ZRE(Customer return) is created with refrence to Invocie i have to check the quantity in the return order is less than the original invoice or not.If quantity in return order is greater than invoice quantity then i have to raise error message.For this which user-exit is suitable in sales order program SAPMV45A.
    Thanks,
    shyla kumar

    Hi
        Use can use MV45AFZZ AND MV45AFZB userexits
    Within mv45afzz USE CAN form related to VBAP or
    save_document_prepare.
    Please reward if useful.

  • Automatic Batch Creation at  the time of GR for Customer Returns

    Hi All,
    We are using batch management with functionality of automatic batch creation for variuos movement type 101/103/105/561 etc. with updation of classification in foreground. 
    We are even using automatic batch creation for Inbound delivery. By configuring IMG object "Batch creation Control for Inbound"
    Now we have a new requirement of automatic Batch creation for GR of Customer Return against Customer Return SO (Movement type 651). And updation of classification in foreground.
    I have tried a lot but couldn't find how to configure the same.
    Can I create GR custmor returns 651 thru transaction MIGO?
    Any suggestion how to achieve this.
    Thanks
    Sanjay

    Hi,
    What Sairam said is correct, the idea of automatic batch creation is so that when you manaufacture or create an item you can allocate the characteristics to that batch and give it a number.
    You then sell that batch to a customer.
    When the customer returns the item the system should NOT automatically allocate a new batch number to it because this is breaking a VERY important audit trail.
    In batch management (in some inductries more than  others) it is VITAL to have a full audit trail of a bathc so that any problems concerning that batch can be traced back to their origin. What you are trying to do is to break that audit trail (although I can fully understand what you are trying to do).
    I would leave the batch allocation for returns as manual and then when you transafer the item from returns to unrestricted (or quality etc.) tyou can then input the new characteristics.
    Steve B

  • Parallel processing for ABAP prorams in Process chain.

    Hi All,
    In one of the process chain, we have added the ABAP program. In Backend,the job is running as "BI_PROCESS_ABAP".
    I just want to know, same like DTP, can we keep parallel processing for the ABAP programs also. Please suggest.
    Thanks.

    Hello Jalina
    Also check with BASIS if the memory allocated to run this program has not overflowed and the selections you have in your ABAP program is in small chunks and use variants to run them in parallel OR series
    Thanks
    Abhishek Shanbhogue

  • Inspection type for customer return of returnable package material

    Hi Guys,
             I send the returnable package to the customer , while reciving that material to my stock (when the customer return to me ) i want to create outbound delivery with out order refference .
    I want system to create inspection lot after doing PGR of the outbound delivery .
    The inspection lot sould have the option of result recording and stock posting when i do usage decission
    This requirement not met by inspection type 06 , i want to create new inspection type to met above mentioned all requirement .
    please provide the steps to be performed to met the same.
    Thanks and regards
    Thamizhchelvan G

    Hi,
    The 06 - Inspection type is not stock relevant and also it is not possible to change because it is SAP std.
    1. If you want inspection for Customer with stock, active 05 - Inspection type in Material Master, and move the stock from customer return to QI by using MB1B with Movement type 457 Stock transfer returns to QI. After that system will create the Inspection lot in 05 Inspection type.
    2. If don't want stock for inspection and directly post to Unrestricted using MB1B with movement type 453 Transfer posting to returns from customer to Unrest.
    3. Customer return to Blocked stock using MB1B with mvt type 459 Stock transfer returns to blocked
    Case2.
    Inspection type 05 is a stock relevant inspection type.
    To use 05 you must assign the 05 inspection type to the delivery item in configuration.
    Follow this path.
    Tcode vov6 - there will be schedule line category DN.
    go to details of DN.In Business data, check which movement type is assigned here.
    I think in your case it will be 651.
    Change it to 655 and try now.
    hope it will work.
    Thanks
    Vinay