Hi,
Demand Planners role in Implementation Project:
- Business process related requirement provide to the implementation team
- Test scenario explanation
- Unit testing as per the Demand Planner's view
- Report requirements provide to implementation team.
You will work as a Business expert or as a Core team member in the Implementation Project. Your role will be very crucial .. you will Drive the project as per the business processes of Demand planning.
Support Project :
If you are working as a Demand planner and doing day to day Demand planning work then in case any issues come you will send it to support team for correction.
You may be from Business Team work as a single point of contact from Business.
You will gather the requirement for reports/ any new devlopment and for implementation send it to support team.
In the support project you will require to see continous process improvement

Similar Messages

  • How to tell Implementation & Support project?

    Hi experts,
    Could anyone tell me how to present about implementation and Support project(SAP BW) at the time
    of interview? Iam going to attend the interview. What are the points i have to include that presentation?
    Thanks in advance
    Muthu

    Hi,
    Just enable the GLOBAL field for the values which you want to be available for all the implementation projects.
    e.g
    You created a documentation type which is having global field tick so it will be available for all
    Hope it helps
    Regards
    Prakhar

  • Retail:Support project role

    Hi experts,
                      I am in "support project" now.I know how to create article (MM41).After creation of article when and where i will find the IDOC for article (WP_PLU01).After finding the IDOC number of the artilce what i have to do.I want "complete role" of an "support project SAP IS-Retail functional consultant" in support project. Hope you understand my query.Expecting complete and clear answer for SAP Experts.Thanks in advance.
    Regards
    Sandhya

    Dear Sandhya,
    SAP IS Retail Consultant role in ongoing (Post Go-live) support varies from Level 1 to Level 3 as well as client to client.
    Mutually agreed tasks are part of Statement of Works (SOW) reflects in Contract / Agreement. So, you can refer SOW to know complete role.
    In mean while, are you supporting Indian Client or Foreign Client?
    In general, Support consultant should carry out following tasks;
    (a) Trouble shooting in master data and transactional errors
    (b) Training
    (c) Interaction with team on proactive basis
    (d) Facilitating to get MIS Reports
    (e) Preparing FS document for Inhouse reports
    Regards,
    Muralidhara

  • For a beginner to work in Oracle EBS, Which is better start, support project or implementation?

    Dear Experts,
    I have just joined a company which works on Oracle ERP. and i have been assigned to a support project with an idea that there i will have more opportunities to learn and then I can shift over to Implementation project. Since I am a fresher I have no clue How the career growth goes. So my question is whether I should first take support and then Implementation or I should Take an Implementation Project Directly.
    Secondly I want to know what are differences In Roles and Responsibilities as a fresher in Support and Implementation projects.
    Please reply ASAP.

    Dear Experts,
    I have just joined a company which works on Oracle ERP. and i have been assigned to a support project with an idea that there i will have more opportunities to learn and then I can shift over to Implementation project. Since I am a fresher I have no clue How the career growth goes. So my question is whether I should first take support and then Implementation or I should Take an Implementation Project Directly.
    Secondly I want to know what are differences In Roles and Responsibilities as a fresher in Support and Implementation projects.
    Please reply ASAP.

  • Difference between implementation, support & upgradation projects

    Hello Friends,
                    I am new to SAP. Can anyone tell me what are implementation, support & upgradation projects..what are the differences between those projects? what is role of ABAP developer in these projects?
    Regards,

    Hi,
    SAP Implementation: SAP Implementation is the whole of processes that defines a complete method to
    implement SAP software in an organization. It is based on best practices and case studies from various
    literature sources and presents a collection of processes and products that make up a complete
    implementation method to allow any organization to plan and execute the implementation of SAP (ERP)
    software.The SAP implementation process is made up out of four main phases, i.e. the project preparation
    where a vision of the future-state of the SAP solution is being created, a sizing and blueprinting phase
    where the solution stack is created and training is being performed, a functional development phase and
    finally a final preparation phase, when the last tests are being performed before the actual go live.
    ABAP Developer Role is to prepare the Technical Specification (based on a Functional Specification given
    by a Functional Consultant), build the code, Review the code and finally to prepare the Unit Test Cases.
    Sometimes ABAPer may be asked to do a technical research for an optimal solution.
    SAP Support: After a go live, the application needs a maintenance/support to resolve the issues/tickets raised by the users when using the application.Ticket is like a request for changes/bug fixing or a request for a new
    ABAP Developer Role includes bug fixing/change the existing code due to new requirements/build a new code etc.
    SAP Upgrade: SAP Upgrade is nothing but upgrading the software with a superior version which has got more advantages when compared to the earlier version.
    ABAP Developer Role is to go through transactions SPAU/SPDD to compare the old and new version of the change and finally need to activate the relevant one.Some times might need to work on SAP notes too.
    Hope this helps.
    Thanks,
    Srinivas

  • SAP BW support Project error in implementation

    Dear Friends,
    My company got a support project in Business warehouse Intelligence, with a retail chain manufacturing and selling fashion wear across India through its chain of stores & other resellers.
    This SAP BW was implemented by a SAP partner and no documentation is available and I find following issues to be solved apart from other issue that I have solved:
    1. The datatargets are activated some in 3.5x and some in 7.0 i.e. some having infosource u2014> datasource u2014> transfer rules u2014> update rules u2014> infopackage while others are having transformation u2013> DTP u2014> Infopackage,
    my question is should I convert all datatargets in 7.0? If yes what are the benefits? And how?
    2. For every datasource there are quite a few infopackageu2019s created for loading data.
    Should I delete the unnecessary infopackages?
    3. For infocube 0FIAP_C02 the data is supplied by ODS 0FIAP_O02, the data is loaded correctly but in case 0Creditors which references 0Vendor the master data is available in the system but is not displayed in the infocube and in the query.
    How do I sort this issue?
    4. Quite a few Process Chains is created and active, but as mentioned above the data extraction is happening through a few infopackages.
    Should I deactivate the process chains and carry out data extraction manually till the system is stable and then activate the same after checking the dataflow?
    5. And lastly to create/ change/ view queries though we are having latest patch for SAP GUI 710 we are not able to carry out above activities.
    How do we solve this?
    Waiting earnestly for guidence.
    K Sengupto

    1. It's up to you to use 3.x or 7.x flow If you have enough resources/time you can Migrate them to 7.x Flow
    Ofcourse you will have advantages over 3.x like you will only transformations which replaced Transfer rules and updates rules as well and easier to manage and you will DTP  -> Error stack / Debugging / Rich delta functionality
    2. Normally we will have Auto Infopackage for Delta and also one for Manul infopackage(incase for 'Repair full') .. Check all the IP's If there any filters in each package to upload data to targets .. If you feel they are unnecessary then you delete them or keep them they doesn't impact
    3.You don't need to load 0CREDITOR if it's being referenced by 0VENDOR since MD is shared for reference objects
    4. Try to understand the unused PC's and their purpose sometimes we will have PC's for delta and also for Full loads to avoid manual interaction, and we will have pc\s for full loads as well .. If there are many pointing to the same target anyalze and delete them .. you can remove them from schedule (if they are scheduled) and later you can schedule as per your needs
    5. Check If you have enough authorizations / check SU53 - If you are missing any authorization objects and contact basis team to get access.

  • Re:Role of an Abaper in support projects

    Hi,
    What can be the role of an abaper in support projects and moreover what is production support and development support.How do we handle issues in production supoort i.e., we directly login to the production server and solve or we copy the code in development and solve.
    Plz clarify....
    Thanks
    Vamshi

    Hi Vamsi,
    Abaper role in Support projects is solve the issues of ABAP related in production. it may be data inconsistance, program logic is incorrect, data dictionary issues, Dump error and so on. You can analyse in production server and do necessary changes in develoment server. Development server having program no need to copy it.

  • Abap consultant role in implementation project

    hi
    may i know
    abap consultant role in implementation project
    and implementaion steps

    SAP provides the SUIT but the service companies like IBM & Infosys do two activities to make that suit workable for a perticular client's buisness.
    1. Configuration
    2. Customization
    The abap consultant's role is to customizing the standard suit accoring client's buisness. Also there may be many 3rd party systems involve in for the client along with SAP. To create the interface of SAP and those 3rd party systems and manage the data transfer is also a job ob ABAP consultant.

  • Duration of Implementation Project and Support Project & No. staff in eachj

    Hi
    What is the time duration of an Implementation Project and Support Project?
    What are the number of staff fworking for these projects?
    Can any one of u throw light further
    Regards
    Sunitha

    Hi Sunita,
    Implementation
    Duration of the project depends upon teh project size.
    if it is a small indian company (500 crores) it should take between 5-7 months
    team required: each consultant for each module depending on scope(Apprx:-2 abaper, 1 MM,1 SD, 1 FI, 1 CO and 1 for PP)
    Support Project:
    Duaration of support project will be 1,2, 5 years depending upon the agreement betwween company and client.
    Best Regards
    Ashish Jain
    Pls assign points as a way to say thanks.

  • Abap consultant role in support  project

    hi
    may i know
    abap consultant role in support  project
    and support stpes

    Hi,
       1. Need to check the tickets.
       2. Based on priority find the bugs and rectify.
       3. Check the jobs that daily execute, If any failure then reexecute that with proper inputs...
       4. Update the status in tickets.
      Over all what technical person is doing the same thing needs to be done in Support projects.
    Rgds,
    Bujji

  • Role of Team Lead in support project

    Gurus
    Can anybody share your experiences on the roles and responsibilities , scope of work of a team lead and give some tips and tricks to perform best as team lead in a support project.
    Thanks in advance

    Hi Emani,
    Sorry for a bit delayed response. I am sharing my experience for the roles and responsibilities of team lead in a support project.
    Team Lead mainly performs the following activities.
    Status Reporting: As per the project guidelines he may provide status reporting to both the client and the internal stakeholder of his own organisation.
    (ii)Process Owner Communication / Liaison: he may be required to communicate with the business process owners.
    (iii) Work Assignment: He will be responsible for assigning the work(which is actually the service request or tickets) to the team members and also will continuoulsy monitor their timely closure.
    (iv)Quality Control / Approvals: He will also be responsible for the overall quality of deliverables and will provide approvals if necessary.
    Apart from these he will be responsible for managing the other soft issues like the training and development needs of his team members, their appraisal etc and will plan the resource deployment strategy for future.
    Hope I had been of some help to you. Please assign points.
    Rgds
    Manish

  • Support Project roles and responsibilities.

    Hi Guru,
    I am new in SAP BW/BI support Project. What are the roles and responsibilities in support project as a  BW/BI consultant. plz give details with examples. what are the tools are using in support project. and what are the transaction codes using.
    Thanks & Regards
    Manas

    Hi Manas,
    For Supporting  mainly
    1) We have to do Monitoring of Processchains
    2)Scheduling the Loads
    3)If there is any requirement of new Process Chain we have to Create the processchain
    Transaction Codes Mainly we use :
    SM37 --To know the status of backround job.
    SM12--To unlock the objects
    RSMO--To see how many Infopackages are running
    SM50--To see work process
    SM64--To trigger the event.
    Regards,
    Marasa.

  • Role of a Support Guy in SAP HR

    Hello,
    kindly explain, what is the role of a supportGuy in SAP HR.

    hai rani
    after the completion of implementation that project has to maintained by support team ans their responsibilites lies in creating actions i mean when their is new hire and asn creating vaccancies and positions etc and it is difiicult to say becoz it depends upon ur project secenario and ur client requirement
    thanks
    theja

  • Roles in implementation

    hi,
    tell what exactly people do in implementation project.please explain roles clearly.
    thanks&regards
    anil kumar

    Hi,
    check these links:
    http://help.sap.com/bp_biv335/BI_EN/documentation/BW_ROLES_SKILLS.doc
    /people/mary.huang/blog/2005/06/01/bw-project-management-as-a-jigsaw-puzzle
    /people/marc.bernard/blog/2005/02/08/follow-me-into-the-world-of-business-intelligence
    /people/arunkumar.sampathkumar/blog/2006/09/08/configuring-ep-for-connecting-to-bw
    Also check:
    http://help.sap.com/bp_biv135/html/index.htm
    Go through these links:
    http://csc-studentweb.lrc.edu/swp/Berg/articles/Managing%20SAP%20BW%20projects%20part-1%20v7.ppt
    http://csc-studentweb.lrc.edu/swp/Berg/articles/Managing%20SAP%20BW%20projects%20part-2%20v15.ppt
    Standard business content queries, cubes etc. depending on application you can find here:
    http://help.sap.com/saphelp_nw04/helpdata/en/37/5fb13cd0500255e10000000a114084/frameset.htm
    Responsibilities of an implementation project...
    For ex, Lets say If its a fresh implementation of BI or for that matter you are implementing SAP...
    First and foremost will be your requirements gathering from the client. Depending upon the requirements you will creat a business blueprint of the project which is the entire process from the start to the end of an implementation...
    After the blue print phase sign off we start off with the realization phase where the actual development happens... In our example after installing the necessary softwares, patches for BI we need to discuss with the end users who are going to use the system for inputs like how they want a report to look like and what are the Key Performance Indicators(KPI) for the reports etc., basically its a question and answer session with the business users... After collecting those informations the development happens in the development servers...
    After the development comes to an end the same objects are tested in quality servers for any bugs, errors etc., When all the tests are done we move all the objects to the production environment and test it again whether everything works fine...
    The Go-Live of the project happens where the actually postings happen from the users and reports are generated based on those inputs which will be available as an analytical report for the management to take decisions...
    The responsibilites vary depending on the requirement... Initially the business analyst will interact with the end users/managers etc., then on the requirements the software consultants do the development, testers do the testing and finally the go-live happens...
    BW Data Architect
    Description
    The BW Data Architect is responsible for the overall data design of the BW project. This includes the design of the:
    » BW InfoCubes (Basic Cubes, Multi-cubes, Remote cubes, and Aggregates)
    » BW ODS Objects
    » BW Datamarts
    » Logical Models
    » BW Process Models
    » BW Enterprise Models
    The BW Data Architect plays a critical role in the BW project and is the link between the end user’s business requirements and the data architecture solution that will satisfy these requirements. All other activities in the BW project are contingent upon the data design being sound and flexible enough to satisfy evolving business requirements.
    Time Commitment
    – the time which must be committed to this Role to ensure the project requirements are met
    Project Complexity Time Commitment
    Low If the BW project utilizes standard BW content and InfoCubes, this role can be satisfied by the BW Application Consultant.
    Medium If the BW project requires enhancements to the standard BW content and InfoCubes and/or requires the integration of non-SAP data, this role may require a committed resource.
    High If the BW project requires significant modification and enhancement to standard BW content and InfoCubes, it is highly recommended that an experienced resource be committed full-time to the project.
    Key Attributes
    The BW Data Architect must have:
    » An understanding of the BW data architecture
    » An understanding of multidimensional modeling
    » An understanding of the differences between operational systems data modeling and data warehouse data modeling
    » An understanding of the end user’s data
    » An understanding of the integration points of the data (e.g., customer number, invoice number)
    » Excellent troubleshooting and analytical skills
    » Excellent communication skills
    » Technical competency in data modeling
    » Multi-language skills, if an international implementation
    » Working knowledge of the BW and R/3 application(s)
    » Experience with Data Modeling application software (i.e., ERWIN, Oracle Designer, S-Designer, etc.)
    Key Tasks
    The BW Data Architect is responsible for capturing the business requirements for the BW project. This effort includes:
    » Planning the business requirements gathering sessions and process
    » Coordinating all business requirements gathering efforts with the BW Project Manager
    » Facilitating the business requirements gathering sessions
    » Capturing the information and producing the deliverables from the business requirements gathering sessions
    » Understanding and documenting business definitions of data
    » Developing the data model
    » Ensuring integration of data from both SAP and non-SAP sources
    » Fielding questions concerning the data content, definition and structure
    This role should also address other critical data design issues such as:
    » Granularity of data and the potential for multiple levels of granularity
    » Use of degenerate dimensions
    » InfoCube partitioning
    » Need for aggregation at multiple levels
    » Need for storing derived BW data
    » Ensuring overall integrity of all BW Models
    » Providing Data Administration development standards for business requirements analysis and BW enterprise modeling
    » Provide strategic planning for data management
    » Impact analysis of data change requirements
    As stated above, the BW Data Architect is responsible for the overall data design of the BW project. This includes the design of the:
    » BW InfoCubes (Basic Cubes, Multi-cubes, Remote cubes, and Aggregates)
    » BW ODS Objects
    » BW Datamarts
    » Logical Models
    » BW Process Models
    » BW Enterprise Models
    BW Project Implementation and Rollout
    Global IDs uses a modified version of the ASAP methodology to ensure a robust BW environment is implemented, tested, and delivered. The project milestones include the following:
    Blueprinting
    Realization
    Roll Out
    Post-Implementation Support
    Organizational Change Management
    BW Maintenance
    Once the BW environment is implemented, tested, and delivered, we can perform the maintenance using both onsite and offsite resources. Our maintenance contracts ensure that the customer can depend on us for:
    Troubleshooting and Error Correction
    Creation of New Infocubes
    Customization of reports
    Archiving and Storage
    Data Maintenance
    Focus
    Also Check the below Links:
    Hope this helps
    ****Assign Points If Helpful****
    Regards,
    Ravikanth

  • Role of XI SUpport pro

    Dear all,
    Could you tell me the roles of XI support guy in a project.
    Regards,
    Ashish

    I have been working XI Support/Development for almost two years now...
    Try here:
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/0b4580be-0601-0010-d3ad-bd6ce51ae916
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/f85ff411-0d01-0010-0096-ba14e5db6306
    http://help.sap.com/saphelp_nw04/helpdata/en/7e/c82c42be6fde2ce10000000a1550b0/frameset.htm
    http://help.sap.com/bp_bpmv130/Documentation/Planning/HighAvailability.pdf
    https://www.sdn.sap.com/irj/sdn/docs?rid=/webcontent/uuid/8e27dcfe-0a01-0010-96bb-a7e9117a0062 [original link is broken]
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/aa8e38dc-0701-0010-2f81-8d3e027bedf4
    http://help.sap.com/bp_bpmv130/Documentation/Planning/HighAvailability.pdf
    Most of it comes through experience, but there is a useful course - TBIT50 and TBIT51 - XI Technical Implementation and Operation

Maybe you are looking for