Rotating Off-Days in PM Work Center Available Capacity

Good Day!
Background:
Each Maintenance person is represented by a PM Work Center.
Maintenance person have a rotating off-days which cycle repeats after 21 days.
Requirement:
We want to reflect rotating off-days to PM Work Center Available Capacity.
Options tried but did not worked;
Shift Definition Grouping:   Off-days is in HR's Period Work Schedule but only Daily Work Schedule can be pulled into Shift Definition Grouping and then into Work Center
Reference Available Capacity:   Can be achieved via Shift Sequence Key in interval of available capacity but needs to maintain for each week with on-going maintenance
Do anyone has implemented this similar requirement that we can reapply/build on?
Your valuable inputs are deeply appreciated.
Thanks!

In work center capacity header
click   change intervals
click   insert
Enter manually
valid from and valid to dates
No of ind capacity - 0

Similar Messages

  • Function Module to get a work center's capacity requirements (load) within a given period

    Hi all experts,
    Currently I’m doing a capacity summary report similar to CM01, but with a summarized capacity availability and loading for a period.
    Selection Parameters: Work center range from and to, Period from and to
    List Format: Work Center, Avail Capacity, Loaded Capacity, Free Capacity, Load %
    I have found a standard function module (FM) to get work center's available capacity for a period, but still facing the challenge to find a FM to get a work center’s capacity requirements (load) in a period.
    I have read through all the related threads from the web, and tested the recommended FMs, but still cannot get a right result.
    Please help to provide some leads for a FM or the logic.
    Best Regards
    Philip

    Hello Philip
    The following function modules should be useful:
       - CY_PRIMARY_SELECTION            - Function module for selection of orders for the work center
       - CY_SECONDARY_SELECTION          - Check for additional criteria
       - CR_CAPACITY_AVAILABLE_PERIODS   - Reads the available capacity from work center
       - HR_PERSON_READ_TIME_INFO        - Reads the available capacity from person (modification)
       - CY_GET_PART_CAPACITY            - used only for the first period to read backlog
       - CY_LOAD_DISTRIBUTION            - Distribution key
    Please observe that these are simple function modules, not BAPIs, That means, they were developed to be used on the SAP internal programs and they are not supported by SAP when used in custom programs.
    BR
    Caetano

  • Function with production/planned orders of a work center or capacity

    Hi,
    does anybody know if a function exists which we could use in a tailor made report, which will list all production and planned orders for a given work center or capacity ?  The aim should be to create a report which is more or less equal to the capacity evaluation overviews in CM01-CM07, but then in ALV and with customer specific fields in it.
    Many thanks for any valuable feedback !
    Kristof Wylin.

    Will be done in another way.  Orders will be collected via KBED.

  • Work Center Daily Capacity

    We have a location changing to a plant maintenance schedule where the number of hours worked and the number of available workers will vary each day of the week, however each day of the week will be the same one week to the next, ie., all Mondays will be the same, all Tuesdays will be the same and so forth.  Can the maintenance work centers be configured with unique daily capacities?
    David Macindoe

    David Macindoe,
    Yes, it can be configured. You should be able to set the same up from inside the capacity header by creating a new interval and or shifts.
    Choose the "change interval and shift" push button from the capacity header screen of the work center.Choose Insert new interval from here and insert a date range, for ex starting from Monday of next week till 12/31/9999 or appropriate and make sure to choose length of cycle to be 7 days, and then choose enter.  7 more line entries will be inserted , and for each entry you can specify the start time, end time, utilization factor and number of capacities.
    Regards
    Narasimhan

  • Work center capacity graphical view

    Greetings!
    How do I see work center available capacity in graphical form?
    Also how can I see work center capacity utilization in graphical form?
    -Hemant

    Hi
    I don't exactly remember, the T-CODE is CM02 or CM03.
    Regards
    MUHAMMAD HUNAIN AHMED

  • Capacity evaluation for internal and external workers in one work center

    Hi ,
    Normally in all Industries you have internal manpower to execute work. Say I have a work center named "Mechanical" , I will have 5 people working 8 Hrs for 5 days in a week. We usually configure this in capacity tab of work center for capacity category "002-Labour".  In scheduling tab we configure sceduling data for a capacity category "002-labour"
    In many industries , depending on load, many time, external labours are hired to give assistance to internal workers. Technically it is like adding one more capacity category "PER-Person" and adding number external labours there and in scheduling tab adding required configuration for "PER" capacity category
    Total capacity for any given day would be available capacity in capacity category -002 + available capacity in PER capacity category.
    However in scheduling Tab , scheduling basis can be either 002/PER.
    How can we add more scheduling basis to refer to more than one capacity category ?
    Any other alternative to above problem statement?

    let us say, you have a work "Pump repair" which is done partly by internal workers say 2 people and 1 external labour. Let us assume the number of people in 002-labour is 2 (internal ) and  capacity in capacity category (PER) which is external work center is 3 (Total 5 ).
    Now if I I leave scheduling basis as blank, then system will calculate scheduling based on 002 capacity category as it is "Major" . But I want system to consider both 002 and +PER .
    You are suggesting two line items "Pump Repair internal" and give 2 numbers and duration as 8  control key PM01 . Create another operation "Pump repair External" use control key PM02 (where in scheduling is enabled)  where 1 number - 8 Hrs duration is maintained with another work center.
    If I maintain 2 different work centers and two different operations, this will work. But for customer this is just one work and capacity evaluation should be based on capacity category 002 and PER .
    How to solve this by maintaining one work center , two capacity categories in same work center  and maintaining one control key PM01 in operation?

  • Work center decision

    Dear all,
    Ex- Reactor is main work center main  , under this we r having different type of reactors like R1,R2, R3
    my client want to maintain main rector(work center) in master recipt, and they  will take a perticular work center decision at time of creation of process order. means they will change work center reactor to R1 or R2 as per avaibility of machin
    I suggested, Initially sytem copy  std. master recipt in process order , then u will make a changes of  work center at process order lavel as per you requirement.
    Is it ok suggetion ? or do u have any different idea?
    Kindly let me know
    thx

    Dear,
    There is one more way to incorporate such requirement.
    Create additional master recipes which includes different work center.Then create different production version to incorporate that different master recipe and work centers.
    Now at the time of production release or creation do the selection of required production version as per the work center availability.
    Regards,
    Dhaval

  • How to find the reporting for work center machine wise

    hi gurus
    My question is . In one work center machine capacity category 2 machines are used. Client is asking the report machine wise. i.e as 2 machines are available .What is the capacity utilisation for each machine.Provide me the information for this. Thanks in advance
    kalyan

    Hi Kalyan
    you have to make some settings in production order & work center first.
    In work center capacity header ,you have to make indiovidual capacities as 2.
    In the same capacity header screen by going through the menu Goto--->individual capacitities  define these different individual machines.
    In the production order operation detail screen goto " capacity reqmt assignment " assign the quantities for different work centers.
    Adfter this in the confirmation CO11N you have to fill the split field accordingly& confirm different wortk centers seoperatley.
    Then you can the report in the CO14 for diferent work centers.
    you try this.
    Regards
    YMREDDY

  • Does EAM Forecasting considers off days mentioned in Workday Calendar?

    Hi EAM Guru,
    I need to know if PM Schedule considers off days while forecasting work orders.
    Requirement: Let's suppose Maintenance Workbench is showing forecasted work orders on 25-March-2013. But if 25-March-2013 is the off day mentioned in the workday calendar or it is mentioned as off day in the exception list then what would be the behavior of maintenance workbench?
    User requires that work orders should not be forecasted in off days mentioned in workday calendar.
    Thanks

    Yes.
    Infinite Scheduler within eAM will do automatic scheduling and it does consider calendar and shift defined for maintenance Org.
    Please note, current capability (12.1) does not consider shift exceptions.
    HTH.
    Kamal

  • Pooled capacity, machine work center can have labour?

    Dear All,
    1) We have eg. a common pool of welders for Location A and Location B welding work centers.  How do we setup the pooled capacity and assign to them?
    2) We have eg. 2 CNC machining work centers (Vert and Horiz) but we have labour support to do machine setup, labour related jobs etc.  If we need to perform labour capacity planning in this machine-based work center, is this done by maintaining a separate work center for this labour support and assigned to the same Cost Center?  Or for machine-based work center, labour capacity planning is not required?
    Thank you for contributing.

    Dear
    We have eg. a common pool of welders for Location A and Location B welding work centers. How do we setup the pooled capacity and assign to them?
    There is no differnce between pooled capacity and available caapcity .Only thing is you can utilised this capacity pool for various work centre level.
    To do that , Goto - SPRO-Production -BAsic Data-Work center-Capacity Planning-Define Capacity categories -Create Capacity Categoery for common pool of welders  , Create Capacity in CR11 and assing them into Work cetre Capaicty tab-Pooled Capacity Catogeries and maintian No of indivuial caapcity in Capacity Header -Standard Available caapcity-Indivual Capacity ( Total Number of welders with working timing , utilisation ) .
    Quest2 : To address this issue  , you can select Setup , Labour and Machine in Defalut tab of  same Work centre with proper Standard Value Key .Now , as they are all part of the Production activity , so you can keep the same Cost Centre ( Production Cost Centre )  in the Work centre tab with Formula Key of Labour ,Machine and setup .Goto CR02-Default Tab and Costing tab .
    Hope this is clear
    regards
    JH

  • Transfer data after Network Confirmation to another Work Center?

    Hi all,
    let me explain my problem:
    I've defined an activity with 3 activity elements(work). Every activity has it's own Work Center.
    Normally a worker uses transaction CN25 or CN48N to enter a Network Confirmation by typing in Network, Activity and Element.
    After this he types in his Personell Number and the Actual days or hours and confirms it.
    If the user takes for example too much days and confirms it, normally i've to correct the Network Confirmation by using transaction CN29 and tell worker to retry his Confirmation. (Because there are only allowed maximum X hours...)
    Is it possible to transfer this too much days to another Work Center by using an transaction???
    Is it possible to transfer this entry to another Work Center???
    Im not a Cost Specialist, please let me note if there are any Threads which discribe the same Problem...
    Thanks for any Answer...
    Regards,
    Tobi D

    Hello Virendra,
    thanks a lot for your answer.
    First of all... There was a mistake in my explanation-it's not I've defined an activity with 3 activity elements(work) it's  I've defined a network with 3 activity elements(work).
    In our Company every Activity has it's own Work Center. I meant the Identification and view selection in Project Builder (CJ20N) tab Internal --> General Section and here: Work center.
    Well, i think my main problem is that i do not know how to correct Network Confirmations without using the delete transaction CN29. For example: Worker confirms on Work Center of Activity A with CN25 oder CN48N, but should confirm on Work Center of Activity B.
    Regards,
    Tobi D

  • Work center capacity or WT generic

    Dear All
    Is it possible to have Work center determination based on Bin capacity ,
    if not then as second option
    Is it possible to  have WT generic for work center determination where in the picker based on the available work center will enter the bin and confirm the task.
    Please confirm with the storage type settings/role to accomplish the above..
    regards
    Saravana

    Hi
    Request you guys to validate the Work center functionality summarized below and provide your feedback/clarification if any.
    Case 1: User decides on the bin during confirmation
    It is realized through POSC setting for OB02 ,,either having storage type or type and section without bin.
    Open Points:
    WT generic setting at storage type doesn't need to be generic ( values 1 and 2) , It can still remain as not generic (=with Bin)
    It doesn't work based on work center determination setting(/SCWM/PACKSTDT) and having rule based checked at POSC..
    Case 2: User will drop the picked items in common work center
    It is done by having common Inbound section shared between multiple work centers and then the pack center user drags and drops the items/HU from common bin to working bin .. If required there can be an additional bin to reflect the completed work.
    Case 3: Based on consolidation group
    It is achieved by having Consolidation group as Put away rule and work center determination based on consolidation group.(/SCWM/PACKSTDT)
    System dynamically determines the bin per consolidation group.
    Open Points:
    If there is no work center available during picking for a particular consolidation group ( means all available  work center are occupied with different consolidation groups) then surprisingly the pick is directed to staging area ( Is this expected behavior??)
    Case 4: Work center determination Based on Remaining capacity
    BADI Development..
    Thanks Juergen for your inputs ,, Now i am convinced with the  validation( error message) at storage type configuration of having both storage type role E and capacity check active..
    regards
    Saravana

  • What is the link between material processing & work-center

    Hi all,
    I have two types of material & few work center.
    How can I determine, that which work centers could be applied over a specific material for the material processing.
    Regards,
    Saurabh

    Dear Saurabh,
    You may allocate one or more capacity categories to a work center.  Capacity categories are defined in customizing.  Examples are labor, machine, energy and so on. 
    You must maintain data to enable the system to calculate available capacity at that work center for that category.  Examples include calendar assignment, start time, stop time, length of breaks, utilization, number of individual capacities. This is maintained in the capacity header screen of the capacity category for the work center. 
    If you indicate that a capacity is pooled, then it may be used by several work centers.  An example is a setup team.  They can perform setups at several work centers but can only work at one work center at a time. 
    Routings within a routing group are used for producing similar materials. One routing group can also contain routings with similar production processes.
    The alternative sequence enables you to select alternative operations for a sequence of operations - for example in the case of different work procedures for different batch sizes or capacity bottlenecks.
    The parallel sequence enables you to process operations independently of others.  
    A routing contains the operations to be performed, their sequence and the various work centers involved to manufacture an item. 
    A routing can include the following:
    *The standard values (times) for activities such as setup and processing 
    *Work centers where the operations are performed
    *The material components allocated to the operations
    *Any production resources / tools necessary to perform the operation
    *Inspection characteristics for operations where inspection is carried out
    *Instructions of what to do at each operation
    *Skills required to perform the operation
    Reward points if it is helpful.
    Regards,
    Naveen.

  • Work Schedule in HR Master Data Feeding Work Center!

    Hi,
    I have several questions on how work schedule in HR master data relates to the work center for capacity planning.
    1. How do we assign the employee to a work center? is that in the HR master data or work center or some other transaction?
    2. If we can assign an employee to a work center, how the work schedule in the HR master data feeds the work center capacity? Is there any button that I can control whether I want to feed the work center capactiy from HR master data work schedule or from manual input directly to work center?
    3. If I can feed the HR master data work schedule to work center, what do I need to do to reflect the vacation time or sick time which is not in the work schedule in the HR master data to the work center?
    Thanks,
    Ting

    Hi,
    For starters, please take a look at the following discussion:
    Logistics Work Center and HR Work center.
    Credits: SDN members
    Hope this helps.
    Donnie

  • Table with all versions of capacities (work center)

    Hi,
    I've created a work center with capacity. This capacity has 2 versions (01 normal capacity" the activ version" and 02 minimum capacity).
    I'm surching a table where I can display the work center A with capacity A1 with the versions 01 and 02. (not only with the activ capacity 01 I need to display all the versions from this capacity)
    Thanks
    Dede

    Dede,
    You will have to use a combination of tables, perhaps a SQVI to join tables
    CRHD - Work Center Header (link work center to capacity ID)
    KAZY - Capacity version
    KAPA - shifts and intervals
    In KAPA the times are displayed in seconds
    Hope that helps,
    ~Sunil

Maybe you are looking for

  • Firefox V33.0 can't find user profile and cant view window content

    Hello I have used Firefox since the old days, wayyy back. Never an issue, always worked, always performed. My Firefox (v32 I believe), automatically downloaded and applied the v33 browser and immediately, everything went wrong... First, the browser l

  • Macbook Air (2014) Built-in Keyboard and Trackpad Freeze!

    My girlfriend's Macbook Air's keyboard and trackpad got freeze suddenly when she was using Safari. Tried to reboot and they work completely fine in login, but freeze again after login. Then I tried to reset SMC and PRAM, but still didn't fix it. Then

  • Phone recieving and sending messages

    Hi there i have configured my apache server servlet to send the message "hello world" to a phne, the phone recieves the message but when i want my phone to send a message back i get nothing just a "null" value, here is the code please take a look and

  • G5 & Dell Monitors

    I have two Dell monitors connected via DVI-D cables to my 2006 G5 power mac. Turning on the mac today the monitor as a sign saying "there is no signal coming from the computer" I have checked all cables. Anyone with any ideas. Thanks

  • Merging 2 DSO data to another DSO

    Have a query w.r.to merge of DSO data. DSO 1 100    10    ABC  24.5 100    20    DEF  35.6 DSO 2 100   10  1001  56.8 100   10  1002  58.9 Now, in DSO 1, 100, 10 are header and item which are keys In DSO 2, 1001, 1002 are document no so 3 keys. Howev