Routing & rate routing

hello everyone,
myself rekha bamgude,i want to know difference between routing & rate routing?

Hi rekha to get a quick (or any) response, create your new discussion in a space related to your query.  This way it will be visible to topic experts who will then see and reply to it.   
Please move this thread to the relevant forum Enterprise Resource Planning (SAP ERP)
as you mention
i want to know difference between routing & rate routing?
Many times we told this word (Search before you post ).
please see this thread for more details.
Difference between routing and rate routing
poorna

Similar Messages

  • Difference between Routing & Rate Routing

    Hi All,
    can anyone tell me difference between Routing & Rate Routing? can we use routing for REM? if no, then what will be the effect?
    Thanks,
    Rinky

    Hi Rinky ,
                   Routing and rate routing are task list in broad manner .
    standard task list: Describes the worksteps necessary to produce a material or perform an activity without reference to an order.( that means they are created without reference to order )
    Essential objects of a task list are header, operations, material component allocations, production resources/tools and inspection characteristics.
    Together with specific dates and quantities, task list data forms an important part of the order.
    The following task list types exist in the R/3 System:
    routing
    reference operation set
    rate routing
    reference rate routing
    inspection plan
    maintenance task list
    standard network
    master recipe
    Routing is created with ca01 and rate routing by ca21 .
    Routing is used in discrete manufacuting and rate routing in repetitive .
    Rate routing generally has only one operation  and prod line instead of work centers and operations in routings .
    Both routings can be used for scheduling , cosing and capacity planning .
    Hope this was helpful answer !
    Neal
    Edited by: Neal Gibson on Jun 30, 2008 11:46 AM

  • What's the difference between routing and rate routing

    As we all know that routing normally used in discrete manufacture, and  rate routing used in REM, one of my client, the just use routing for REM instead of rate routing, are there any gurus can tell me some detail information about them?
    Thanks!
    Eric

    Hi,
    对于routing和rate routing来说,区别并不是很明显,但从流程的角度来说,routing适用于所有的离散型制造业,而rate routing适用于重复制造业!
    如果非要找出差别的话,就是routing可以定义并行序和可选序,而且rate routing只能定义并行序!
    具体的使用差别可以参考如下链接:
    http://help.sap.com/saphelp_45b/helpdata/en/03/bb1d0ca6e811d189010000e8323492/frameset.htm

  • Problem in automatic rate routing selection

    Dear all,
    I am using REM and according to that I have maintained REM profile in Material Master, rate routing, line hierarchy, production version, but the time of scheduling of planned order, system is saying " The automatic selection of routing is not possible".
    I suppose I am missing some configuration.
    As also, I have already done the same scenario in other server.
    If u have any suggestion then pl. forward me.
    Thanx,
    Das

    Dear SAP PP,
    1.Check whether have you included the check box for REM allowed indicator in the production version.
    2.Also ensure you have assigned the rate routing option for detailed planning and the correct group and
    group counter in the production version.
    3.Check the valdiity dates of the rate routing,try to create a planned order in some advanced future date
    so that your rate routing is valid for the planned order start date.
    4.Check the status and the usage of the rate routing.
    Regards
    Mangalraj.S

  • Problem during Rate Routing Upload using BDC.

    Dear Sir/Madam,
    I am uploading Rate Routings using a BDC program which is working perfectly but having a single problem.
    In the initial screen of the transaction CA21(Create Rate Routing), I need to enter only the Material Number and its Plant and all the other fields should be left blank.
    But, here the group number field is automatically getting filled with the previous value and it is incrementing the group counter number. 
    I want the system to allocate different group number for  each Routing. I want the group number to be unique.
    Thanks,
    Ranjan.

    Dear Ranjan,
    While doing recording CA21. you would pass only the material number and plant (i mean you did recording of CA21 based on material number as well as plant not for routing number (group counter))
    Routing number (group counter) dynamic (In your case Internal number rage has assigned).
    So the Problem is:
    1st record of you internal table update smoothly because you program will pass only material and plant
    group counter (RC271-PLNNR) field is blank, after update 1st record system will regenerates the
    group counter number.
    ones the system updates the data it will generates Group counter number and assign to filed :(RC271-PLNNR).
    after saving the record system will go loop statement of you program. again program will call the call transaction statement with 2nd record of the internal table. call transaction statement pass the material number and plant field at ca21. but group counter number automatically poulated in the screen field because that time system can't be refresh the initial screen of CA21,
    so system will shows previous updated screen ( 1st routing record will show)
    Remove your bdc perform and add this code in your BDC perform.
    *        Start new screen                                              *
    FORM BDC_DYNPRO USING PROGRAM DYNPRO.
       CLEAR BDCDATA.
       BDCDATA-PROGRAM  = PROGRAM.
       BDCDATA-DYNPRO   = DYNPRO.
       BDCDATA-DYNBEGIN = 'X'.
       APPEND BDCDATA.
    ENDFORM.
    *        Insert field                                                  *
    FORM BDC_FIELD USING FNAM FVAL.
       IF FVAL <> SPACE.
         CLEAR BDCDATA.
         BDCDATA-FNAM = FNAM.
         BDCDATA-FVAL = FVAL.
         APPEND BDCDATA.
       ENDIF.
    *                Clearing the Group Counter                                *
       IF FVAL = SPACE.
         CLEAR BDCDATA.
         BDCDATA-FNAM = FNAM.
         BDCDATA-FVAL = FVAL.
         APPEND BDCDATA.
       ENDIF.
    above code: 1st time of call transaction FVAL = space means ( group counter field is blank)
    2nd and rest of the time FVAL <> space. means (previous record group number exists for new call transaction ) so system will be by pass with new record.
    Check with debugging mode. you will come to whats going in you code.
    Even i have go same problem while uploading routing data. i have find out solution after doing my RND.
    Regards,
    Akshath

  • Mass Changes to Rate Routing

    Dear All,
    We were trying to carry out mass changes to Rate Routing,
    by using CA85N we were able to make changes to Normal routing but not rate routing, in CA85N we were able to select only three types of task lists ie N, S & Q. Also checked in CWEB here also only the three types of task lists were provided for selection. Is there any other way for carrying out mass changes to rate rouitng, or settings in the above transactions.
    Regards
    Mithun

    Dear Mithun,
    In my understanding only CEWB can help you to some extent,otherwise you may have to develop some
    BDC's or LSMW's.
    Regards
    Mangalraj.S

  • Rate Routing Changes

    Hi All,
    Is there a possibilty to find out the changes made in the Rate Routing of a BOM regarding to Component Allocation over a period of time.
    Regards,
    R. Vijayakumar

    Dear Rajavelu,
    Try the standard report CA60,for task list type R - Rate Routing,include the check box for for all the options under Detailed Change
    documentation for and execute the report for some date range for any material and plant combination,this will satisfy your
    requirement.
    Regards
    S Mangalraj

  • Rate  Routing

    Dear Sir ,
                   i need sample program of Rate Routing Tcode CA21..Using BAPI or BDC CALL transcation ...........or tell me the BAPI Function module ....
    Pls Help to me ....
    With Regards ,
    Meena ...

    Hi,
    You can check the BAPI: BAPI_ROUTING_CREATE.
    Also you could check the following DI/BI steps in LSMW ( Not sure whether these objects work for Rate Routing Creation):
    Object               0170   Routing   
    Method               0001   Batch input
    Program name         RCPTRA01         
    Program type         B   Batch input  
    Object               0170   Routing     
    Method               0002   Direct input
    Program name         RCPTRA02           
    Program type         D   Direct input  
    But following IDOC could be used for loading Rate Routings:
    LOIROU02
    You can check the documentation in WE60.
    Hope thsi helps.
    Best Regards, Murugesh

  • Sequence selection in Rate Routing

    hi,
    In Normal Routing in sequence overview  - extras - new entries we can find the option of creating a Parallel or Alt sequence, but in Rate routing there is no way to select the type of Sequence. It by default shows Parallel sequence.
    Pl. let me know the step by step proceduer to create a Alternate sequence in Rate routing.
    regards

    Dear Rishi,
    We cant create any alternative sequence for a rate routing.This is one of the difference between routing and rate routing.
    Rate routing supports only standard and parallel sequence.
    If alternative sequence is present in a routing,then at the time of order creation the system gives a pop to select for alternative
    sequence or to skip it and proceed.
    For this under OPL8,for plant order type combination the field sequence exchange should be having value 2 - manual selection.
    Creating production version or sequence in my understanding depends on the business requirement.
    Check and revert
    Regards
    S Mangalraj

  • Rate routing std values not appearing during backflush

    Hi ,
    Rate routing is defined from REM product. The REM profile has check to post activities.
    In MFBF when I try to do assembly backflush the activities are not proposed from rate routing when "Post with correction ".
    What could be the reason for this ?
    Regards
    ShankarR

    Dear Shankar,
    Once after selecting the radio button for assembly backflush>post with correction->click on actual activities and check the rate
    routing details along with the work center,timings etc.
    If you are unable to find the same means,goto KKF6N--->mention the product and plant and click on change mode and click on
    cost calculator button for preliminary cost estimate and save the data,then check in MFBF.
    Regards
    Mangalraj.S

  • Defect Recording for operations in rate routing

    Dear Masters,
    How to record the defects for the operations defined in rate routing of a material once the inspection lot in generated using TCode MFPR in repetative manufacturing?
    Thanks & Regards,
    Ram Kulkarni

    You mean to say tan is available in rate routing itself ?

  • Help me,Mass Changes to Reference Rate Routing

    Hi,
    I need to mass changes to reference rate routing.
    but i don't know how to do it.
    by using CA85N i was able to make changes to Normal routing but not reference rate routing.
    so.so.so. i need your helps.
    best regards.
    thanks.

    Hi
    While entering the selection criteria make sure that you are entering the correct selection parameters. Since the routing exist in CA32, it will be come in CA95N also. Please try with correct selection parameters.
    Thanks
    S.Murali

  • Standard routing and rate routing

    Hi All,
    Can someone tell me what tables I should use to get the standard routing and rate routing for the query?
    Thanks
    Edward.

    Dear,
    Yes you are right.
    The main difference between routing and rate routing is you can not create parallel sequence in rate routing CA21 only nothing else.
    There are lot of different opinion on this topic but there is no too much difference in them only we use rate routing in REM and normal in Discrete manufacturing.
    Also check this thread ,
    Difference between routing and rate routing
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Transfer Master Data Rate Routing

    Hello Gurus,
    We need to transfer Master Data (Rate Routing) with ALE. We already configure the ALE connection. We need to know which is the Process Code in the Inbound Table.
    Anyone can help us, please.
    Thanks in advance.
    Best Regards.

    Check this link
    http://help.sap.com/saphelp_47x200/helpdata/en/92/58d455417011d189ec0000e81ddfac/frameset.htm
    For BOM and materials there are transaction codes...but i could not get for WC and Routing...

  • Reduction strategy in Rate routing.

    Hi
    I have a Rate routing with 3 WC for 3 operations
    Each operation take 30 mints to finsh
    If i want to produce 5 qty in the 3 WC.
    time taken for the machining is =  30 mins * 5 qty(WC1) +  30 mins * 5 qty(WC2)  + 30 mins * 5 qty(WC3)
                                                     =  71/2 HRS to finsh the 5qty jobs
    but as per normal -                            w1      w2      w3
                           JOBS          1       9:00 AM       9.30 am     10.00 am
                                             2       9.30 am     10.00 am     10.30 am
                                             3     10.00 am     10.30 am      11.00 am
                                             4     10.30 am      11.00 am     11.30 am
                                             5     11.00 am     11.30 am     12.00 am
    Total it will take 3 hrs to finish
    how to do this reduction in the Routing.
    what REDUCTION STRATEGY WE NEED TO USE . PLS EXPLAIN.
    Can i use the Contioud flow prod in the overlapping tab in the operation details
    Thanks
    vraj

    Hi,
    Yes, U can use Overlap strategy to meet your requirements. Please maintain all the values correctly and do some work around and test properly before doing it in production client.
    Regards
    Suri

Maybe you are looking for

  • Can't get photoshop 12 to stay on screen

    I was editing a photo when my computer shut down...wasn't paying attention to the battery life. Now when I try to access via my shortcut, the organizer will open for a second or two and then click off...do I have to reinstall the whole thing.  I went

  • Placing a multiple page pdf over multiple pages in indesign

    Ok so I do alot of "print presentations," when designing books or manuals etc I have to place the spreads of the document into their own A3 pages in another indesign file So I make a pdf with all the spreads I need. Then I place the pdf and with impo

  • Firmware Update - 1.1.5 vs 2.0

    I was going to update to 2.0 but am a bit hesitant based on feedback, so I may wait a while till the dust settles. However Apple's just released 1.1.5!!! I'm currently downloading 1.1.5 but can't find any information on it. I've searched the web incl

  • Photoshop Elements 11 Quieries

    Im looking to get Photoshop Elements 11 but i need DDS file compatible software and also being a university student need to keep the cost down (hence why im looking at Elements not CS6) so i have 2 questions: 1 - How long do licenses last? i.e. are t

  • How to integrate REST services in Siena?

    Help me to integrate REST service in siena application.  Could anybody help me on this? saravana