RRB - DP90 - DMR Billing and Material reverse

Hi Experts,
Our client issued materials against a Service order and created Debit memo request and Billing document. For Some reasons (decided to send the materials after a month to the intended customer since the sames materials are required to some other customers as it is critical requirement)they want to reverse the materials back to stores by cancelling bill and DMR.
1. We cancelled the billing document (VF02), set Reason for Rejection in DMR.
2. We reversed the materials back to stores by MB11, 262 movement type.
3. After a week, we issued the materials against the same Service order MB11,261.
When we try to create DMR(DP90), System shows that "No data was changed".
Am I doing right SAP steps for this scenario? Any help would be appreciable.
Babu

PeteA,
Thanks for your response. After setting OLI Flag in RFR, system generates another DMR.
I. Standard flow
1. created a Service order with a material (10 qty)
2. Issued materials against the Service order MB11, 261 Mvt.
3. Generated DMR (DP90) w r t Service order
4. Created a Billing document w r t the DMR
II.Material reversed back to the stores
5. Cancelled the Billing document
6. Set RFR in the Sales document (DMR) item
&&> I could generate a DMR here <&1&
7. reversed the materials back to the stores MB11, 262 mvt. (10 qty)
&&--> If I run DP90 here, system generates Credit memo request --&&
8. After some time, I issued the materials against the same Service order (10 qty)
&&> I am not able use the button To order in MB11 initial screen... the materials are not listed out as they have been issued in step 2. <&&
9.   Created DMR (DP90) again w r t Service order
10. Created another Billing Docuement w r t second DMR
Is my flow correct?
Is it necessary to create a Credit memo request (CMR) after reversing the material back to the stores (MB11,262 mvt)?
I have confusion in the flow. What is the standard SAP best practice for this scenario?.Please help me out.
Babu

Similar Messages

  • DP91(RRB) Restrict DMR Billing value to Sales Order Net Value

    Hi Experts,
    My Requirement is, while creating a DMR using transaction DP91 (Resource Related Billing), I need to  restrict the DMR value to the sales order Net Value. i.e If there are already billed DMR'S we should check all the billing documents value, sum it up with present DP91 billing value (Say X). Check it against Sales order net value.
    IF Sales order net value is more than already billed value or to be billed value(X), then optimize the DIP items within available billing value (Planning to use bin packing algorithm) and postpone remaining items for next billing cycle.
    If Sales order net value is less than already billed value or to be billed value(X), postpone all DIP items for next billing cycle ie dont allow any billing.
    I found the Enhancement AD010007 Change DI Processing Information (EXIT_SAPLAD15_015). But it triggers for each item and here sales order related data is not available neither all DIP item data. All DIP data is flowing from WBS assigned in Sales Order item into DP91.
    Regards,
    Mahesh

    Hi,
    You can make use of data transfer routines in copy control from billing document to sales document.
    Data transfer routine - 403 (FV45C403) is used for copying billing plan dates from from a reference billing document into the target document.  This routine can be assigned to the FPLA copy rules for the item category from a billing document to a sales document.
    You may enhance this routine to add net value field to be copied into credit memo document. In your case, net amount (100) can be pulled from invoice into credit memo document. 
    Regards,
    Vaibhav

  • Material cost updating in COPA at the time of Billing and Delivery 2 Time.

    Hi All
    I had created sales order( MTO).
    Sales Order No 61224069 u2013 50
    Sales Order line item 40 created > PR & PO created (MD02) > MIGO > Delivery of Order (VL01N) > Settlement (VA88) >Billing( VF01) > Settlement (VA88).
    I have two COPA Document and Material Price updating 2 Time in COPA report.
    Please let me know Its Process error Or Configuration error.
    If Process -- Please let me know the correct process
    If Config -- Please let me know where to check
    Thanks In Advance.
    Alok Dixit

    Hi Ajay
    Thanks for the reply.
    The COPA Documents Generated 2 Times through settlement.
    *When document generated.*
    1 After Delivery Sales order is settled
    2 After Billing  Sales order is settled
    *What sort of value*
    There i maintain the PA Stracture as same as CCS. But in the COPA report system is updating Material Cost 2 times.
    *Record Type*
    Record Type for documents is C in both cases
    Settlement after Billing  & Delivery.

  • Billing Document and Material Document Relation

    Dear all,
    i need to know about the relation between Billing document and Material document.
    Please let me know if there is any Function Module or Some View available to get these details.
    my only requirement is to get only Material document From Billing Document.
    Thanks In Advance.
    Pradeep.

    Hi
    So the material document should be linked to the delivery
    The document flow:
    Delivery->Outgoing moviment->Delivery->Bill->FI invoinces
    If you start from FI:
    - Get the bill number from header data: BKPF-AWKEY
    - get the delivery number from bill item VBRP-VGBEL
    - get the document flow for the delivery: VBFA: here you can find out the material document
    Max

  • Resource Related Billing: Time and Material Scenario

    Can we use internal resource time through CATS for Resource Related Billing: Time and Material Scenario instead of external time of resources through service entry sheet

    Yes you can
    Please read sap help for more details

  • Material number with Incomplete setup was billed and Invoiced

    Hi All,
    Though the material has incomplete set up status the material was allowed for billing and invoicing.
    I have checked the materials Sales Org. view and found the DChain-spec.status was changed from *99 to 01(*01 stands for Discontd w/o Replace & 99 is Block all Logist ).
    Awaiting for your valuable feedback asap.
    Thanks in advance!!
    Regards,
    M Ravi

    what feedback do you want? you saw already that the status was changed.
    The change history for material master will tell you who changed the status.
    The material master is not incomplete if it was possible to create order, delivery, goods issue and billing.
    If you are the opinion that the 01 status shall restrict something, then let me tell you, that statuses are subject to customizing. In detail of the status to tell SAP how it shall react under certain circumstances, e.g. warning or error.
    IMG > Logistics general > material master > setting for central fields > sales relevant data > define sales status

  • I signed up for auto pay and just received my bill with last months bill and $5 late fee.  would like late fee reversed and last month credit applied.

    i signed up for auto pay and just received my bill with last months bill and $5 late fee.  would like late fee reversed and last month credit applied.

    << Duplicate post, see Re: Problems with Auto Pay Activation >>
    This discussion is over two years old and will be locked to further replies.

  • Difference between billing and invoice?

    Hi all
    can anybody say Difference between billing and invoice?
    thanks

    Hi Ipsit,
    Invoice is document indicating to delivery goods and Billing is a receipt of payment
    Tables are VBRK & VBRP. For flow, go to transaction VF03, enter document number and hit 'Display Document Flow' button on toolbar
    VBRK and VBRP holds billing/invoice details..
    Billing Document:
    Generic term for invoices, credit memos, debit memos, pro forma invoices and cancellation documents.
    The tables are VBRK and VBRP.
    2) -- once u do PGI the delivery document will be created. There is no way to stop it.. The thing u can to do go to the list of created deliveries in VL09. Select the delivery doc which u created. There u have the option of reversing the goods or canceling it.
    Billing is generic term and u can say invoice is a type of billing document.
    After PGI only way left is to cancel it by Using TCODE MBST as this Tcode is used to cancel any material document.
    Please Reward If Really Helpful,
    Thanks and Regards,
    Sateesh.Kandula

  • Contract Management, Resourse Related Billing and Revenue Recongnisation

    Dear SAP Experts,
    Can someone help to provide me in  details such as configuration step by steps, Billing types, Billing plan with T. Codes  about the below.
    Contract - Service/Maintainace Contract, Quantity and Value contract configuration and billing document type with Transaction codes.
    Configuration steps for Resourse related billing
    Configuration steps for Revenue Recongnisation and Billing plan. This is urgent.
    best regards
    Nain Chand

    hi,
    The Price of a Customer-specific services are not determined by Standard Prices .
    For example
    Make to order production
    Plant maintenace
    Resource related Billing is used in the CUSTOMER SERVICE and PROJECT SYSTEMS
    We use the RRB process to bill the customer for the Material consumed and the Costs incurred in the customer project.
    The flow is
    Create the Sales order in VA01 which has the DIP profile assigned
    Now Using the Sales order create the BILLING REQUEST in DP91
    now create the Billing document in VF01 using hte Billing request in DP91
    VA01DP91VF01
    this is the flow
    Please check and revet.
    regards,
    santosh

  • Resource related billing and service quotation

    Dear gurus,
    can anyone explain the process of resource related billing and service quotation in step by step.
    if possible mail me the screen shots also in this email-id
    [email protected]

    hi,
    Maintaining Profiles for Sales Order and Billing Request
    Use
    The Dynamic Item Processor (DIP) profile defines and controls resource-related quotation and billing for service orders and sales documents. It may be maintained in either the Customer Service or the Sales and Distribution section of the IMG. The DIP profile allows flexible determination and translation of actual labor, material and other costs into sales materials for appropriate pricing and billing.
    DIP profiles BC10 is used exclusively in the value chain for time and material project.
    Integration
    The DIP profile functionality is closely integrated with the controlling module for the processing of cost objects into sales materials.
    Prerequisites
    Relevant sales document types, condition records, sales materials have been created.
    Procedure
    Access the activity using one of the following navigation options:
    IMG Menu Project System ® Revenues and Earnings ® Integration with SD documents ® Creating Quotations and Project Billing ® Maintain Profiles for Quotations and Billing
    Transaction Code ODP12.
    Activities:•
    In the configuration item Profiles for Sales Order, Billing, Results Analysis, choose profiles BC12.
    • The DIP profile can be used for processing resource-related billing and results analysis, as well as for generating resource-related quotations. To do so, sales document types must be defined for each usage. Access the Usage section of the profile and maintain the following entries:
    DI Usage SD Ty BC12
    1 Billing & Results Analysis Z2TC
    all other fields leave blank
    • Access the characteristics section of each profile. The characteristics are the objects which the system will take into consideration when processing and displaying resource-related billing. For both billing and order usages, set the characteristics as follows (note that other settings are automatically defaulted in by the system):
    Characteristic Charact
    Relevant Material Determ NoSummarizat. Structuring Sequence
    Z2TC
    Accounting Indicator X
    Activity Type X X X
    Object number X
    Period X
    Transaction Currency X X
    Unit of Measure X X
    all other fields leave blank
    • The sources section determines what type of costs will be selected by the DIP profile for each usage. More detailed selection criteria are available, but not maintained in this setting. Access the sources section of each profile and maintain the following entries:
    Line Source Percentage
    1 0001 Actual Cost - Line 100
    • Access the material determination and criteria sections of the profile. Material determination defines the sales materials that costs will be converted into. The criteria defines cost element groups (cost elements are determined from the labor activity type or the component account assignment) that correspond to each material. For both billing and quotation usages, define material determination as follows:
    Material/Service Material Determination:
    Transfer Quantity/Costs Material Determination:
    Conversion Quantity Criteria:
    Activity Type
    Z2TC
    I00342 X (Transfer Cost & Qty) Checked
    I00984 X Checked
    all other fields leave blank
    • To confirm that all entries and settings in the DIP profiles are consistent, go to the configuration item check profile settings. Enter the DIP profile and execute. Green traffic lights should be displayed next to all items for both usages. Otherwise, determine the inconsistency and make the necessary correction.
    Go through t.code DP90
    1.U will get "resource related billing request initial screen.
    2.U enter ur "Srevice order", then select "Expences" button.
    3.u get " Billing request for resource related billing document" Here the columns for "Open amt" and "Amt. to billed" equal the transactions that have posted to the project and have not been billed. To continue, press the "Billing request " button. The system will ask you if you really want to do this -- say "yes"
    Then u will get the overview screen.
    Link service order to a quotation thru transaction DP90. The quotation will be created with reference to the service order. The business scenario is that you are creating a quotation for the job to be done. The line items in the quotation are based on resources and materials planned in service order.
    CHAN
    Message was edited by:
            CHAN HARI

  • Diff b/w Intercompany Billing and TPO.

    Hi SAP  gurus,
    What is the diff b/w Inter company Billing and Third Party Order

    Dear Sabina
    Inter Company Billing
    You can set up your system in such a way that one purchasing organization procures material for a plant from a vendor (plant) that belongs to another company code within the same client (corporate group). This is an instance of an inter-company-code stock transfer with an SD delivery and a billing document
    Third Party Billing
    In third-party processing, you place a purchase order with a vendor to deliver goods or perform a service for a third party (for example, for a customer).
    This means that your company does not deliver the material. You forward the order to an external vendor instead, who then sends the material directly to the customer and invoices you.
    Third-party processing is carried out in the components SD (Sales and Distribution) and MM (Materials Management). By creating a third-party item in a sales order, purchase requisition, or purchase order, you can request that the vendor sends the goods directly to your customer. A document can consist of one or more third-party items.
    Thanks
    G. Lakshmipathi

  • How to create BOM(Bill Of Material) item data from flat file?

    I have two flat files one is BOM(Bill Of Material) header data and BOM item data. BOM header is already created, now I want to create BOM item data with reference to the header data. Is there any standard direct batch input method in LSMW or Is there any standard BAPI or Is there any standard BDC report program to do the task? CS01 is the TCode to create BOM.

    Hi,
    The DI program works for create step CS01 and not for CS02.
    Perhaps this ( adding items in header by Tx: CS02 ) could be achieved by a Recording step in LSMW.
    Best Regards, Murugesh

  • Billing document not reversed

    Dear Guru's
    I am not  SAP consultant.
    Pls help me, previously i had reversed one  billing document through Vf11 ,then reversed VL09 delivery and cancelled the Sales order.But now billing document not reversed.Again go to reverse throuh VF11 Getting error as No billing documents were generated. See log
    Message no. VF032
    Swamy

    Hi malaini,
    thanks for your's reply.in this regards already i had reversed particular delivery , also sales order and deleted.But only think is now stock was not reversed and billing & accounting posting didn't reversed.customer balance is shown debit wrongly.pls advice.
    Swamy.

  • Difference between billing and invoice?  How to stop PGI?

    can u please help me in these questions.
    Difference between billing and invoice?  How to stop PGI?

    Invoice is document indicating to delivery goods and Billing is a receipt of payment
    Tables are VBRK & VBRP. For flow, go to transaction VF03, enter document number and hit 'Display Document Flow' button on toolbar
    vbrk and vbrp holds billing/invoice details..
    Billing Document:
    Generic term for invoices, credit memos, debit memos, pro forma invoices and cancellation documents.
    The tables are VBRK and VBRP.
    2)-- once u do PGI the delivery document will be created . there is no way to stop it  .. the thing u can to do go to the list of created deliveries in VL09.. select the delivery doc which u created.there  u have the option of reversing the goods or canceling it.
    let me know if i am wrong...
    thanks,
    madhan
    Message was edited by:
            madhan n

  • Billing and delivery address to be displayed in PO

    Dear Gurus,
                          Here client requirement is as follows : There are three plants in three different places- Chennai, Bangalore and Hyderabad. Client is creating PO from Chennai plant and they want the material to be delivered in Bangalore plant. They want this to be displayed( billing and delivery address) in the purchase order. Kindly suggest me how to map this scenario.Thank you.

    Hi,
    For delivery adress you can use the subscreen for delivery adress in the item of the PO.
    Por billing adress, if it's not the same that the adress for the center, you can do a subroutine for the form (Z)MEDRUCK for the company of these center, of you can create a partner 'Billing adress' and write it in form with a subroutine (Z)MEDRUCK.
    I hope this helps you
    Regards,
    Eduardo

Maybe you are looking for

  • APP -  CONFIGURATION & END USER MANUAL

    Hi All I need configuraiton & end user manual of automatic payment programme. If anybody has these document, Plz send me on following e-mail id:- [email protected] With Regards Deepak Garg Mob 9213784161

  • Can not make or receive calls on edge E cellular network

    can not make or receive calls on edge E cellular network Using my iphone 6 plus. Please advise.

  • Looking to upgrade FCP Academic

    Two questions. 1. I have FCP 6 academic. Can I upgrade it at the $299 price? 2. My serial number was voided when Apple did a repair on my computer. When I type in the numbers, it says it's the wrong serial number. How do I fix this? And can I still u

  • I tried to install iso7 and now i cant connect to wifi

    I started to download iso7 this morning i had my iphone 4s connected to my home wifi.  it sarted to download fine but after 5mins it lost connection to wifi and paused the download.  i tried to connect back on the wifi but it wouldnt even see my my h

  • Sync Alert - Change more than 5%

    Hi all, I am currently syncing between a MacBook Pro, a PowerBook G4 and a Sony Ericsson cell phone. Quite often on the laptops, I receive the error that states, "more than 5% of your calendar/contacts will be changed... are you sure you want to sync