S_ALR_87013644 - Cost Centers: Cost Component Split

Dear SAP Gurus,
I am executing Cost splitting in KSII, and the values are coming correctly while doing the test run. However in the report S_ALR_87013644 - Cost Centers: Cost Component Split , price per unit is getting doubled. For example
Cost center X actual costs 20000
Activity unit for this cots center 2000 hrs
After splitting the value per hr=10
However in this report, per hr cost is coming as 20.
Is this a standard way of calu
Thanks

Hi,
Pls check the cost centers that you entered when executing the report.
If there are more than 1 cost center was selected, the system will sum the activity price per unit of all selected cost centers then display..
So the value maybe different from your expectation.
Regards!
Edited by: The Cuong Than on May 6, 2010 4:57 AM

Similar Messages

  • Define Time-Based Fields for Cost Centers

    Dear All!
    I would like to know , how I'm abale to cahnge the setting
    of business area for Time-Based Field of Cost Centers to period
    Transaction is OKEG
    Would be thankful

    You can maintain master data for cost centers, cost elements, activity
    types, and business processes with time dependencies. You can make
    changes at any time for any given time interval. Data storage also takes
    place with a time reference. In this way, a master data record can have
    multiple database records storing different information.
    The smallest interval is one day. To ensure data consistency, you
    cannotchange each field daily. The timeframes in which you can change a
    field depend on the field functions, which are fixed by the SAP R/3
    System and cannot be changed. Master data maintenance includes an
    automatic check for each field's time-based consistency, resulting in
    individual time-based maintenance for each field.
    Regards
    Prabhu

  • Report cost center/cost element in Business Warehouse

    I have report in SAP CO including: rows - cost centers / cost elements; columns - periods /months/, created using trans GRR1;
    I need the report including: rows - cost centers / cost elements; columns - divisions /that are defined in cost centers - 2010400000 - 04 is the division/;
    I'll do it in BW but I have to write every row separately /the report consist over 500 rows/
    Are there any way to do this easier?
    Pls advise
    Katya

    Hi,
    How do you solve the problem?

  • Primary cost component split not happening

    Hello Experts,
    I am trying to create a Primary cost component split for Products with following settings
    1. Creation of Primary cost component structure "1N" and marking it as Primary cost component
    2. Assigning the Primary cost elements to the Cost component structure
    3. Assigning the Primary cost component structure for the Company code and Plant
    4. Assigning the Primary cost component structure to "Version" under "Price calculation" tab.
    5. Activity type with Activity type category "1- Manual entry, Manual allocation" and Price Indicator "1 - Plan price, automatically based on activity"
    6. Activity output planning for Cost center
    7. Primary cost planning for the Cost centers
    8. Activity price calculation. (Update run) - Prices are changed in KP26 also
    9. After all the above steps I checked report S_ALR_87013644, Plan price is existing in the report as mentioned in SAP note: 1658589
    After all the above steps, I tried running Cost estimate for a product. I am getting the error message
    Cost element 90001 is not assigned to a cost component
    Message no. CK239
    Also, I am getting a message
    No structure could be determined for internal activity TEB (M0001)
    Message no. CK694
    Therefore the Cost component is showing only the Material component.
    Where "90001" is a secondary cost element. I am not sure why system is still searching for Secondary cost element where we have assigned Primary cost component structure. I also ensured that Primary cost elements used in planning are all assigned to a Component in Cost component structure.
    I checked for SAP note "1736332", which is not applicable for my system version. Current version of SAP_APPL is  Release 606 and Support package SAPKH60607.
    Please help. Am I missing any settings.
    Thank you in advance.
    Muneer Ahamed N

    Hi Muneer,
    Please check whether you have maintained cost center splitting structure properly and assigned to the respective cost center for which you have maintained output planning and input planning.
    This splitting structure is much required because there only we maintain the relationship between primary cost elements and activities.
    Coming to your first message, yes system expects maintenance of secondary cost elements also in the cost component structure which is not primary CCS.
    Inorder to show primary cost component structure view:
    First, system calculates the direct activity cost in terms of secondary cost elements...
    Next, it verifies the cost center splitting structure you made,
    Then, system is going to convert the direct activity cost in terms of primary cost elements based on the splitting structure and Finally displays the primary cost component view
    I suppose second message speaking about cost center splitting structure only, please go through it carefully
    Other than these whatever the process you specified is right only..
    Regards...
    Jose

  • Actual Cost Component Split for cross company code transfers.

    Hi,
    My issue is as follows.
    Production process spans across 2 company codes.
    Goods are produced in production company code, transferred (via stock transport order) to marketing company code and sold to customers from marketing company code.
    Stock transport order follows sales scenario i.e.. marketing company code creates purchase order for goods from production company code and production company code bills marketing for the goods.
    Actual costing / Material ledger is implemented in both company codes.
    We would like to roll-up (transfer) actual cost component split from production company code to marketing company (in a similar way as in product cost planning in cross-company scenario).
    However, due to the fact that the transfer between the companies is in fact a "sales" the goods in marketing company code are seen as externally purchased and the only cost component we can create is based on PO conditions. But we want to get the info about production cost component split.
    Once again this is for ACTUAL cost component split.
    I would be grateful for any ideas.
    Thanks,
    Szymon

    Hi Udo / Szymon.
    I have a question about this issue.
    In the sap help  about multiple valuations / group costing:
    http://help.sap.com/saphelp_46c/helpdata/en/7e/cb848443a311d189ee0000e81ddfac/content.htm
    Its not clear if this can roll up the Actual CCS? or what it do? My question is because i read the documentation of  bussiness function: LOG_MM_SIT,and also the book *Actual Costing with The SAP Material Ledger*
    states that we can handle the rollup of actual cost component split inter-company only with this BF active.
    Could you clarify about this?
    thanks!!
    Arturo.
    Group Valuation
    Goods movements between affiliated companies not involving intercompany profits are processed using the group view. This view determines the actual cost of goods manufactured for the group, and does not include any intercompany profits. You can, however, display internal profits as delta profits in the legal and/or profit center views.
    When you define cost components, you can specify that internal profits between company codes and/or profit centers are shown in detail in the cost component split. You activate these delta profits for the group valuation in the attributes of the cost components.
    For each cost component structure, there can only be one cost component under which the delta profit is shown. This means that neither the legal view nor the profit center view can have more than one cost component for the delta profit.
    To cost multiple values, you define a costing type for each valuation approach in Customizing for Product Cost Planning. You use the costing type to specify which valuation approach you require. You define each costing type in a new costing variant and carry out a cost estimate with this costing variant.
    Group Costing and Multiple Valuation Approaches
    In-Depth Detail of the Value-Added Chain: Partner Cost Component Split
    You can display in detail the costs of materials and services of every company department in the value-added chain for every stage of the production process. The partner can be traced for every material used. To do this, you define a partner version, which enables the value-added portions of each manufacturing level to be displayed in detail. For further information about this, see Partners and Direct Partners.
    The group cost component split can be displayed according to your partner definition. You can display the cost structures of the partners hierarchically according to your requirements, such as the company code segments on the highest level and the plant or profit center segments underneath.
    To display partner cost component splits, define a partner version in Customizing and enter it in the costing type.

  • How to delete the one of cost centers in Splitting Structure(OKEW)?

    Dear All,
    I have a question about Splitting Structure as below? Could I get favor from you? Thanks a lot.
    How to delete the one of cost centers in Splitting Structure(OKEW)?
    Jocha

    Hi Chang
    Welcome to SDN! Its our pleasure to help you here
    Step 1: Select your Cost Center in OKEW which is assigned to the Splitting Str
    Eg: Cost Ctr 1001 is assigned to Splitting Str Z1... Tick the Check box against 1001 under Z1 Splitting Str
    Step 2: Do a Single Click on the text "Non Assigned Cost Centers"
    Step 3: Press Shift +F6 (Or Click on the Assign Button, next to the Pencil icon)
    Br, Ajay M

  • Report painter/writer for actual cost component split

    Hello Gurus,
    Any of you guys ever explored possibility of creating a report using report painter or writer that can give both Standard and Actual cost component splits in one report? Is it even possible without custom ABAP involvement?
    Thanks
    RG

    Hi Raghu,
    After your reply, I am getting a doubt..
    Have you Activated Material Ledger? When you say Actual Cost Component Split, are you talking about it what you get in Actual Costing/Material Ledger?
    If yes, then you can map your cost compnents for Actual Costing in the path SPROControllingProfitability AnalysisMaster Data Valuation--Setup Valuation using Material Cost Estimate -- Define Access to Actual Costing / Material Ledger
    Further, there are no standard reports available in COPA. Try to build a report comprising two columns, 1st column with the value fields which are mapped for Standard Cost Components and 2nd column with the Value Fields which you have assined for Actual Costing under the above path.
    You will be able to get the comparison...
    Pls don't hesitate to call me for further assistance....
    Srikanth Munnaluri

  • Actual Cost component split - Per PO

    Dear ML Experts,
    We have activated Material Ledger and Actual costing/ Actual cost component split in our implementation. The standard cost is based on delivery costs and there is no manufacturing involved. In order to test ML, we created some POs and did a GR and IR for those POs. When I look at the Material Price analysis on the Price Determination Structure View, I can see the Price differences per transaction (Goods receipt, Invoice receipt).
    But when I go to the Cost component View (Actual), I cannot drill down into the individual transactions. I am able to see the actual cost component split only at the summarized level across multiple transactions. I can see the category Purchase Order under Receipts, but I am unable to drill down to see the actual cost component split for the individual transactions (goods receipts, invoice receipts).  Did I miss anything on the configuration? The client wants to see the price differences per cost component per transaction and actual cost component split per transaction.
    Is it possible to view this information using standard configuration? Would I have to change the controlling level in order to achieve this?
    Can you please provide your advice?
    Thanks,
    Balram

    Hi Balram.
    If you have access to an IDES system, you can see a Cost Component split like this:
    As fas as I know, this is only for educational porpouses. In the standard System, its not recomended have the detail of the split per movement, due to the huge amount of data genereted. There is a Flag that control this, in a Txxx table (i dont have access to the system right now).
    If you really want this functionality, write SAP in the marketplace, and I guess their response is exactly what im saying.
    Arturo.

  • Itemization does not match cost component split

    Hi,
    I need your help or could you please shed some light as to how to fix .
    A new Overhead was created, in order to add expenses to the pricing of the product. For it a variant  of different pricing to which is used currently was created, and so for maintain a historic one of the information.
    In addition, in the cost component Structure an adjustment of the configuration was carried out, this was done because the previous the cost component Structure contained 18 elements of costs, which the most of the elements were specified as fixed and variable costs, therefore the  system only permitted the addition of  2 more elements  (SAP only permits 20 elements of fixed and variable costs), nevertheless was necessary to create a total of 23 elements of costs. For it  the previous elements have to be modified and to change some elements as variable costs, specifically the elements corresponding to the accounts of materials.  using tcode OKTZ
    The addition of 5 more elements of costs, corresponding to overhead  elements, where the type 41 costs classes were configured from the plan of surcharge created. 
    After carrying out the changes and to transport them the client of production, when i execute the T-code ck13n an inconsistency in the previous pricings was generated, because  the cost component Structure was modified and the the following one Nº message was showed:  CK869 " Mat.XXX in plant XXX: itemization does not match cost component split, the report of itemization shows different values to the reports of Costed Mutilevel BOM and of Cost  Components.  Additionally to the error shown by the system, also is observed that to the Cost  Components report    a cost in the new elements of overhead  was added, even when the  calculation of previous cost did not contain the determination of overhead.
    In order to fix the error, I modified the cost component structure as it was before and the created another  cost component structure with the required changes requested by the client specifying that it should start to be current this year. However after that change the error message nºCK869 continue: Mat. XXX in plant XXX: itemization does not match cost component split. Adding to that error message, the cost of the finished product changes with reference to the calculus of the previous product after modified the configuration and that is because the cost of the semifinished product is not being taken the values of the row material, and it is appearing with cost 0 and the only value that is taking on the matter are the costs of the activities types.

    If you want the message to go away then you need to mark and releasse the estimate.  However, there is no requirement that you do this.  The message you are getting is an informational message only.  You can continue without re-costing the item.  If you do re-cost the material the new cost estimate will reflect and changes you've made to the components, so there is a good chance you will get a different value with the new estimate.  So if that's ok, go ahead and mark and release the new estimate.

  • Cost component split: incorrect allocation of by-product generated

    Hi everyone,
    I have a question involving the costs of by-products generated and their allocation on the cost component split.
    Suppose that a production order, besides the main product, also generates a secondary product. By-products in standard system are confirmed with movement type 531. In transaction OMJJ this movement is linked to key GBB / ZOF. This key is assigned to a G/L account and this account is assigned to a cost element in OKTZ.
    Example:
    GBB / ZOF > G/L account 1000 > Cost component 10
    Thus, the by-product generated should be allocated to the cost component number 10.
    However, this does not happen. These costs are allocated to another cost component. This is because SAP ERP appears to use the key GBB / VBR to calculate the cost component split.
    To summarize: for accounting purposes the system uses the GBB / ZOF (which is correct!), but in the cost component structure the system seems to use the GBB / VBR (which makes the costs of by-product being incorrectly assigned).
    GBB / ZOF > G/L account 1000 > Cost component 10 (used ONLY for accounting purposes).
    GBB / VBR > G/L account 2000 > Cost component 20 (it seems to be used in cost component split). INCORRECT!
    Can anyone confirm whether that statement proceeds?
    Regards,
    Kelson

    Hi
    This behaviour is corect.... Consumption accounts are used in Cost Comp Str (CCS)
    GBB-ZOF is actualy sort of COGM accounts specified in GBB-AUF which is used to Credit the order at the time of GR from prod order
    Just the way, AUF is not used in CCS, ZOF is also not used...
    You need to maintain separate account in GBB-VBR for the consumption of By Products... For this, the val class of By products need to be separate
    Else, if yu dont wanna do this - have a separate Origin Group in the Mat Master of By products and You can assign the Combo of GL Account + Origin Group to a separate Cost Component
    br, Ajay M

  • Cost component split transfer for Profit center valuation in ke27

    Dear All,
    We have activated multiple valuation/transfer prices. Material ledger is also activated.
    We want to transfer cost component split to CO-PA by ke27.
    We have defined separate costing keys for access to actual cost estimate for legal and profit center valuations.
    But cost component split transfer to COPA works only for legal valution. Even we have defined type of valution for profit center  costing key -transfer cost component split and total costs.
    What should be else customized to transfer cost components splitting in profit center valuation to CO-PA from actual cost estimates?
    With best regards,
    Kamila.

    Hi,
    I have assigned the same value fields used for legal valuation to column 2, which was pointed in message.
    But now I got following message in ke27:
    For actual data, value fields that were already populated before CO-PA valuation cannot be changed in valuation.
    1. As a rule, value fields that were filled before CO-PA valuation - be it from SD or by a manual entry of a line item - can only be changed by means of user exits.
    (Note that for plan data, CO-PA valuation always has priority over the values planned manually.)
    2. The valuation steps in a CO-PA valuation strategy are numbered sequentially. These numbers determine the order in which the steps are carried out within that strategy. As a rule, value fields populated in one step can be used as a basis for calculating values for other value fields in a subsequent step.
    Value fields that were populated in a previous step are generally not overwritten by subsequent steps.
    The exception to this are steps that use a CO-PA user exit. User exits let you change individual value fields.
    3. If you valuate using multiple material cost estimates simultaneously, this means that the values of different cost components within the same cost estimate are aggregated and then entered in one CO-PA value field. However, value fields that already contain data from a previous cost estimate are not overwritten by a later cost estimate. Consequently, you should assign value fields in Customizing so that the values of different cost estimates are entered in different sets of value fields.
    4. When condition values are transferred to CO-PA value fields, note that condition types that are assigned to the same value field are added together. This is also the case when the condition types come from different costing sheets within the valuation strategy.
    So does it mean we should define separate value fields for PC valuation?
    With best regards,
    Kamila.

  • Cost component split datasource

    Hi,
    We recently activated 0CO_PC_ACT_10 Cost Component Split datasource and bringing info into 0COPC_C07 cube for the costing analysis.
    Acccording to the requirement need to extact the cost of finished material and cost of semi finished material into BW. The relevent costs are avaialble in R/3 in T code CKM3N. The finished and semi finished materials are differenciated in R/3 with Prefix C. ex: If material is 10000 then semi finished material will be C10000.
    We modelling as per SAP standard and loaded, we are able to load cost of finished material with sales order but not able to load cost of semi finished material with sales order. (need to analyse cost of semi finished material with sales order in reporting)
    Any inputs on how to bring cost of semi finished material with sales order in BW cubes. Also we are thinking to write new extractor as this standard extractor is not meeting our requirement.
    I would like to know is anybody got similar requirement, or is anybody involved in enhancing this datasource for getting sales order with semi finished materials?
    Please let me know your thoughts. If you need any more info from my side let me know.
    Thanks
    Naveen

    Hi Rakesh , 
    The datasource 0CO_PC_ACT_10 uses the extractor - KKBW_CCS_BW_GET_DATA to extract its data .
    And in the extractor - KKBW_CCS_BW_GET_DATA,
    i could locate these tables - ckmlhd and  ckmlmv011 .
    So you can check these tables for your information .
    You can also have a look at this :
    [http://help.sap.com/saphelp_nw04/helpdata/en/02/a2e338d96cd84fe10000000a11405a/frameset.htm]
    Thanks ,
    Lokesh

  • Cost Component Splits

    Hello,
    We're using Special Procurement Keys in order to transfer cost estimates in a production plant to a DC.  These cost estimates currently all come over with a full cost component split.  For plants that do not belong to the same company, we don't want to see the cost component split at the receiving plant. 
    Is there any way to use Special Procurement Keys or Transfer Control so that Intercompany plant relationships don't transfer the cost component splits?
    Thanks,
    Nick

    Hello Nick,
    In SAP Product Costing, the cost will allway be stored in cost components and it will be tranferred in similar way to to higher level and tranfer to another plant. Even earlier we have faced similar issue. The better way is to understand how the system stores and do work around.
    Hope this helps.
    Regards,
    Santosh

  • Cost component split in copa

    Hi,
    I am looking cost component split in copa document ,
    Price for FERT(FG) materil valuation will at manufactured plant level is Standard price(S) and Depo level Moving avg price(V) i am doing standard cost estimate
    for that i have done ..setting.
    1) cost component structure ( Raw material, reprocess cost, additive cost, and overheads)
    2)Valuation Strategy (maintained with Point of valuation 01,02,03,04)
    3)Costing key  (Y01)
    4)Assign Costing Keys to Material Types  ( ROH and FERT, PV=01,02,03,04.)
    5)Assign Value Fields , ( Operating concern & Value fields are Raw material, reprocess cost, additive cost, and overheads)
    6)I have written copa report
    Cost breakup i am geting when i maintained standard price of the material, but
    when i maintain price indicator V (MAP) stock value will be different it depends on Goods movement, i am getting price converted standard price.
    Is their any setting missing to fulfill the same ( meet the requirement if goods movement taken in consideration)
    I am not getting proper cost split in COPA report.
    Please help me i am stuckup.
    Thanks in Advance
    Regards.
    Vinu
    Edited by: vinutha1010 on Jun 17, 2010 7:08 PM

    HI PietStrydom ,
    thanks for your valuable replay.
    could u tel me in detail..how can i achive in this transaction ..ie somthig like SCE access .
    I have taken parameater in t.code KEPC (source =  POV, Record type, material type, plant, Target = costing key, plant, type of error,
    Regards.
    Vinu,

  • Cost component Split not transferring while costing using Spec Prc Key

    Hi Fellow CO consultants,
                                             I have come across an strange scenario in my work could you help me on it . We are using special procurement key to get the prices between cross company code costing while doing costing run the Materials which have the cost component split from KKPAN (costing without quantity structure ) we find an strange behaviour of update of the costing price .
    scenario 1:That is Using KKPAN  the FG materials are costed with fixed and variable cost and are marked (future ) but not released in the Production plant . Now while doing the CK40n at warehouse level the Cost component split is correctly picked up the receiver plant using the Spec Prc key properly the fixed and variable cost split .
    But
    Scenario 2: Using KKPAN the FG materials are  costed and then price is released and the material price is at current standard price .Now while doing the CK40N run the cost component split is not picking the variable and fixed contribution its picking up the Total price of the material .( this behavior is observed only in materials done with KKPAN other materials with quantity structure provides the variable and fixed itemization even in the current price of the material ) The prerequsite of the transfer control statergy is set as fist to check the future price for the fiscal year and next the current price of the material if no future price exist. The cost component split and the costing variant are the same .
    Appreciate your thoughts .. on helping Scenario 2 case why does the cost component split take the fixed and variable cost while the price of the material is in Current.
    regards
    GK

    Dear Prasad
    Try masking costing variant too at assignment to plant and co code.
    Rajneesh