Sales Order Costing-Information/Message

Dear All,
At the time of sales order costing, if the Component Cost(material Cost) is 70% of Total cost , SAP system should display information or warning message.
Please give your valuable suggestion

Hi,
CK869 is introduced after 46C to inform you that the total of the cost component is different from that of itemization.
The message CK 869 is normally generated correctly. This is clarified in note 168238. If an assembly component is subsequently costed again, the new costing results are updated to the cost component split as this information is dynamically called, unlike the itemization.
Please check if any of the sub-components have been costed after the header material has been costed.
Once the header material is also re-costed (after all sub-components have been costed) message CK 869 will no longer occur.
The issue arises due to the make-up of the cost component split; the system must read this information dynamically, therefore the most up-to-date is always visible. The itemization always reflects the data at the time of the original costing.
To avoid such problems in the future, you should do the following:
-> Always cost the header material again if a material component with  changed values is being costed.
-> Cost all materials again after price calculation is run for a  PARTICULAR period.
regards
Waman

Similar Messages

  • Sales order cost objective vs OKB9  Internal order cost object.

    Hi All,
    we facing an  issue with sales order cost objective vs OKB9 cost object.
    For IC PO service material, we assigned account assignment category 4.Reasonis Service material was not showing on G\R account.
    The G\L account 7898788, we assigned to Service Item (material type DIEN)  , for G\Cost 7898788 cost element is assigned in OKB9. Combination business + order 3478787.
    Now conflict with sales order cost objective vs OKB9  internal order cost object.
    While posting intercompany IR posting system thronging below error messageu2026
    Enter only one true account assignment
    Message no. KI249
    Diagnosis
    You made assignments to several objects in CO (cost center, order, project etc.). 2 of these have been created as true objects.
    System Response
    You are allowed only one account assignment for each cost-relevant account
    How to resolve this issue.. Do I make any config changes in the system to overcome this issue?
    Or any sub account to assin in VKOA config for internal orderu2026
    Regards,
    Adi

    Hi Waman,
    Thanks for your inputs.
    Issue :  IR failed to post for wax  Sales Order -> ICPO  - Error:  Enter only one true account assignmentu2019.
    Background:
    Original setup  in  Test system   & Productionu2013 account determination for servive (DIEN) account assignment category u20184u2019 was linked to G/L Account  34444444, As part of project orange u2019, account determination was linked to account u201889710100u2019.
    Account u20188970100u2019   34444444 was replaced with 8970100 ,is not linked to any cost center & always post with reference to IC Sales Order as per config in OKB9 based on company code (US99) + cost element (89701100) + business area (9yyy). This caused a conflict while posting IR, system could not determine exact order for posting financial value.
    Conflict:  Actual Sales Order 34789343 is  linked to PO via account assignment category & IC dummy sales order (8014331) is determine via config setting. Two cost objects cannot be linked to one IR G/L account booking.
    Regards,
    Adi

  • Sales order cost estimate not happening because of GIT B/S account

    Hi,
    Requirement is to have Goods in Transit account in PGI and reverse it in Invoice no issues iwth it.
    For the same sales order user wants to get cost using sales order cost estimate.
    When i run that am getting following error
    Item 00001 : Cost element 14001212 does not exist in CO area 0010 for 10/07/2011
    Message no. KK689
    Even though i maintain the CE for Balance sheet account with Cost element category 90 its not accpeting.
    Can you please help me on how to proceed for sales order cost estimate.
    Thanks,
    sudha

    hi,
    if you give a balance sheet account in obyc , you will not be able to create a cost elementin category 01 , accordignly system will give error in sales order costing , as its not able to get correct cost element in cost planning.
    if your requirement is just to post  cogs to a balance sheet account which is goods in transit and when invoice is done cogs to be posted.
    you should actually use  revenue based RA functionality on sales order instead of assinging a balance sheet account in obyc.
    in this approach;
    - first assign a p/l account in obyc and create cost element in cateogry 01.
    - create revenue based RA and assign RA key in requirement class.
    - in OKG8 for RA category  WIPR and your ra key assign , goods in transit account and give a offsetting account which is not cost element (credit entry in offsetting account nullify debit in account given in OBYC when GIT is posted , when billing is done system will automatically post a oppsite entry in both account).
    -in OKG8 for RA category COSR give the COGS account and a offsetting account without cost element (credit entry in offsetting account nullify debit in account given in OBYC when COGS is posted).
    regards
    rajesh

  • Sale order costing process : Help required

    Hello All,
    Belatted Happy New Year 2011 to all.
    I have a question related to Sale Order Costing. It goes like this,
    My client is into Pipe coating business who receives the pipe from the customers, coats it as per there requirements and despatches it thereon. There is no concept of FG here as its only the service he is doing on it and also when he receives the pipe there is no raw material cost on it. Raw materials for him would be chemicals etc which he uses to coat the pipe.
    And also this demands variant configuration from SD and PP angel.
    As this scenario is customer specific, it demands Sale Order based costing(Sale order cost estimate).
    My doubt is, how the sale order costing process goes with.
    In general scenarios, Make to stock, we use production order based costing where standard cost estimate is calculated for planned cost and actuals are incurred on PO settling the variance to COPA
    Similarly how the costing goes with if Sale order cost estimate is used. What i think is, here instead of Standard cost estimate for plan, we will go with Sale order cost estimate at sale order level, and incur actual cost at production order and settle the cost of Production order to Sale order. Correct me if i am wrong, and request you ppl there to explain me the process of costing in the scenario said above.
    apart from that, my client wants the flexibility to change the cost estimate at quotation level.
    Please suggest me with solution explaining the process of costing here.
    Thanks in advance,
    Ravi Kumar

    Hi Ravi
    Your understanding of the scenario is very much right...
    In your case, you need to have sales order as cost object...
    Process
    Your stock would be non valuated stock, because the FG is not your stock.. You are just doing a service
    Based on the characteristics chosen in the Sales orders, system would determine the Sales order BOM
    Based on sales order BOM, Sales order cost estimate would be calculated....
    You would receive the Customer pipe in your stock against the sales order... It would be a non valuated GR... You can track the Qty only
    Sales order would trigger a production order... The prod order can have its planned cost, which is only for information sake
    The Customer Pipe, Chemicals would be issued to prod order to coat the pipe... And also Labor/machine hrs may be confirmed
    There after your production order would be settled on Sales order
    Then you would do PGI (Post Goods Isue).. This will not trigger any accounting doc
    Then you do billing... The sales revenue would be posted on the sales order
    Then you settle the sales order to COPA.. This will close the cycle
    Configuration
    The IMG Settings required would be as below
    1. You would use account assignment category (AAC) E
    2. Create a Requirement class with
    a. AAC = E.... (Means sales order is CO Object)
    b. Valuation Indicator = BLANK (Means Non Valuated Stock)
    c. Costing ID/Costing Method = As per your choice to calculate the Sales order cost estimate
    3. Assign this req class to Requirement Type
    4. Give this req type to your PP/SD team.. They would assign it to Strategy group / Item Category to determine it in the sales order
    Regards
    Ajay M

  • Duplicate Overheads in Sales Order costing

    Hi Experts,
    We are facing an issue in VA02 and VA22. Here we are getting duplicate overheads in costing as below image:
    Kindly help. I am an ABAPer and debugged for it but could not find any bug. So this functional approach could help, I thought.
    Thank you so much.
    Jayaprakash

    As Warren mentioned, you need to work with your CO specialist. To analyze the issue, more information on the process is needed. If the process involves sell from stock, then take a look at OSS 1972019 - Sales Order Costing: Duplicate Overhead Rates for Sell-from-Stock
    Or if it is a re-work scenario, you may need to implement OSS 1844495 - Rework for product costing: duplicate overheads and  1204894 - Rework sales order costing: Duplicate process costs
    Regards,

  • Sales Order Costing Error Log Display

    When I look at Sales Order costing thru VA03 or when I run the Multi-level BOM costing for sales order CK87_99 I can not display the costing error log.  I can generate the log thru VA02, but we need to limit the Sales Order change transaction to the Order Management group and did not want to give change order access to the product cost group. 
    Any options to get the costing error log from VA03?
    Thanks

    I cheeked OKY9 and the Update tab had the "Save Error Log" checked, but on the Misc tab the "Log Messages but do not save" on the error message field was selected.  When I changed the selection to "Log and Save Message" this corrected my problem.
    Your suggestion guided me in the right direction. Thanks,

  • Sales Order Costing Error

    Hallo friends,
      I am getting sales order costing error and it does not allow us to delivery through VL01n. Error shows :
    Object was not costed
    Message no. CK060
    Diagnosis
    The system could not find any entries that are relevant to costing.
    System Response
    The system did not cost the object.
    Procedure
    Check whether the following objects should be flagged as relevant to costing:
    Items in the BOM
    Display BOM
    Operations in the routing
    Control key in the routing
    1. Look at the message log.
    2. Check whether a quantity was specified in the confirmation.
    Kindly give me urgent solution.
    Thanks & regards,
      Samrat

    Hi
    You can just mark your thread as answered
    regards

  • Inventory Valuation based on Sales Order Costing

    Dear All
    My client requirement is the inventory value should happen based on the "Sales Order Cost Estimate"
    Kindly give the configuration steps, if it is possible in SAP
    Regards
    Anilkumar

    Hi rback59,
    The information you have provided is very clear and accurate. Thank you. I am hoping that you can assist with a related problem I am facing: 
    We have sales order costing in place with the Material Ledger and multiple valuation. For financial reporting purposes, we have a legal valuation/local currency variant entered in our requirements class (46) and we are using this to value our sales order stock. The problem we are facing is that the requirements class allows us to enter only one costing variant. This means we are not able to create a cost estimate for our two additional valuation views (group and profit centre). As a result, we are forced to use the material standard price in the material master for the group and profit centre views which is not ideal.
    Do you know if there is a way to create cost estimates in all 3 valuation views for a single sales order line item?
    Any pointers would be appreciated.
    Thanks,
    Ross

  • Mass sales order costing(ck55) error

    hi
    If i do individual sales order costing , no error.But same sales order has done in ck55,error"item is not relevant for billing" ,but in single sales order costing is ok, .what is reason.
    system message
      Item is not relevant for billing
        Message no. CK_MCSO029
    Note
        You can remove this message from the log with the customizing
        transaction User-Defined Error Management for Mass Costing of Sales
        Documents. The item will still not be costed, however.
    Diagnosis
    System Response                   
    reg
    nagesh
    Edited by: nageshrr on Jul 5, 2011 2:01 PM
    Edited by: nageshrr on Jul 5, 2011 2:04 PM

    no replies and my thread was dead.

  • Routing data for configurable products (Sales order costing)

    Hi
    I am runnign sales order cost estimate for configurable product. here I want to confirm the activity quantity with cost estimate.
    Pls let me know where can I check the activity quantity information . Pls help
    Thanks
    Sneha

    Hi Sneha
    I am bit confused with the terms you used..
    you cannot confirm activity qty while doing cost estimate... Activity confirmation happens during Production Confirmation
    Are you talking about missing activity qty/cost in sales order cost estimate?? Contact your PP consultant... You should have a routing attached while creating the sales order.. If that is there, then Activity cost would show up in the sales order cost estimate
    Br, Ajay M

  • Sales order costing release not possible due to Goods in transti account

    Hi,
    Business introduced Goods - in - Transit (Balance sheet account), so PGI will always post to GIT and Invoice it will get reversed.
    For one of the Configuratble material (MTO) scenario we need the Sales order cost estimate to get the Planned cost.
    When i try to execute the sales order cost estimate it says cost element doesnot exist for GIT GL (WHich is right).
    But with maintaining the GIT how to achieve the sales order cost estimate.
    Can you please help me in this regards.
    Thanks,
    Sudha

    Hi Ajay,
    I have created GIT (B/S) account with CE category 90.
    but in sales order cost estimate getting message " inconsistancy in CE category" CE category 90 is not accetable it should be either 01/02
    can you please help to move forward on sales order cost estimate with GIT account
    Thanks,
    sudha

  • Open Balance on Sales Order Cost Report

    Hi SAP Group -
    I have a couple questions about the settlement of manufacturing variance to COPA.
    When our settlement process is complete (production order and sales order both settled to COPA), there is a balance remaining on the sales order cost report which is equal to the manufacturing variance on the production order.
    It seems that the manufacturing variance is posting from the production order to the sales order, but is not being assigned to the PSEG and flowing to COPA.
    I am looking for advice in two areas:
    First, how do we "clear" these balances on old orders that are already settled?
    Second, how do we prevent this from happening on future orders?
    Thanks !!!

    Refer to OSS 183250 and note 186485.
    If you don’t specify in the settlement profile for the production order that the variances are not transferred from the production order into CO-PA, you will settle the variances to <b>CO-PA twice</b>: once from the production order (broken down into variance categories), and once from the sales order item. The settlement rule still references the material and not the sales order item.
    Special Features of Product Cost by Sales Order with Valuated Sales Order Stock
    <a href="http://help.sap.com/erp2005_ehp_02/helpdata/en/90/ba66cc446711d189420000e829fbbd/content.htm">Read the topic on 'Special Features of Product Cost by Sales Order with Valuated Sales Order Stock'</a>
    You may want to check the period of the variance settlement from mfg order to sales order and ensure the settlement of sales order is also done the same period, if the type is PER.

  • User Exit or BADI on saving of Sales order cost estimate (CK51N)

    Hi,
    Can any one share with me what are the User Exit or BADI that gets triggered on saving of Sales order cost estimate (CK51N).
    Regards,
    Bijay

    Hi
    Check the link
    Need Enhancement Spot or BADI for transaction ck51n
    Regards
    Sanil

  • Sales Order Cost Estimates -- Versions?

    In our MTS plant we are creating cost estimates each month with different version numbers so they can easily be compared to review cost changes.
    This concept in our MTO plant is (of course) a problem.
    We would like to create a dummy sales order and on each line list a KMAT and build an "average" configuration.  We use variant config, so the sales order bom is built automatically.  It also costs automatically.  We would like to save this cost estimate and compare it with a cost estimate of the same configuration next month.   I do not have an option for version CK51n, nor do I see a Costing Date in KEKO table.  Either of these items for MTS would create a second cost estimat and allow comparison.
    Is there a way to compare Sale Order Cost Estimates across periods?
    Any other suggestions as to how to obtain the required data??
    Thank you for all suggestions!!

    Any one think of a solution?
    thanks

  • Sales order cost estimate with GIT account

    Hi,
    Business introduced Goods - in - Transit (Balance sheet account), so PGI will always post to GIT and Invoice it will get reversed.
    For one of the Configuratble material (MTO) scenario we need the Sales order cost estimate to get the Planned cost.
    When i try to execute the sales order cost estimate it says cost element doesnot exist for GIT GL (WHich is right).
    But with maintaining the GIT how to achieve the sales order cost estimate.
    I tried to create CE category 90 for GIT, in Cost estimate am getting error CE 90 not supported for Cost estimate.
    Kindly help this is kind of urgent req for us
    Thanks,
    Sudha

    Hello Ashley
    Yes, if you have done your settings correctly, especially Requirements class set up  (see the documentation link),  then the cost estimate will flow to a condition type in Pricing, usually EK01/EK02 conditions. These conditions are used to calculate sales prices (PR00) in cost-plus (mark-up) scenarios.
    Link: http://help.sap.com/erp2005_ehp_04/helpdata/EN/90/ba6da4446711d189420000e829fbbd/frameset.htm
    However Profit margin  as calculated in a sales order comes from VPRS condition  (which is based in Material Master) and is the difference of net value and VPRS condition value in normal circumstance.
    Hope other more knowledgeable experts will weigh in.

Maybe you are looking for

  • Issue in XL reporter on Client machine

    Hi Experts I am facing issue in running XL reporter on client machine aftre upgrading patch 10 of SAP B1 2007 B. System shows following errro Run TIme Error 430 Class does not support Automation or does not support expected interface. pls. help me ou

  • DODGER BASEBALL DODGER BASEBALL..ISN'T ON THE VERIZON LINEUP..STRIKE OUT VERIZON

    WELL IT IS NOW 3 MINUTES UNTIL THE FIRST OFFICIAL GAME ON DODGER NETWORK CHANNEL AND WE CAN'T WATCH IT. NO DODGER CHANNELS THIS YEAR VERIZON?  I RENEWED MY CONTRACT FOR 2 MORE YEARS.  I HAD TO PROMISE TO A 2 YEAR AGREEMENT OR I WOULDN'T GET ANY DISCO

  • Real application cluster

    dear friends, I am stuck in situation. I have 2 Dell Servers with linux os. oracle 10g database is installed on that 2 servers. now i want to configure replacation for these to databases, for this is i preffered RAC. i want to know... how to configur

  • Intraoffice instant messaging software for Windows and Mac

    Can anyone recommend instant messaging software between Mac and Windows platforms? My employer doesn't want to use the traditional IM clients - AIM, MSN, etc., - for security reasons. He'd like something that would only connect members of the same LA

  • Unable to see Default alias in Identity management

    Hi Experts!!!!! I have added a new system in the portal which connects my backend system, I have defined the system alias and in the screen it shows me the alias is ready for user mapping, But i have selected SAPLOGON ticket, then the system is not v