Dear Gurus,
We have scenario in company that we want to run MRP for sales order & generate requirements. But while doing post goods issue for same sales order, sales order stock need not be present.
Please tell which planning strategy, strategy group or else should be used here.
Thanks in Advance !!
Thanks,
Vishwas 

Hi,
Please configure in the following manner..
create a strategy group say Z9..in this maintain main strategy as 20  and alternate strategy as 10... Now assign this strategy group to material in material master in MRP3 View..
Now create sales order say A and run MRP with MD50..after completion of production you will get Sales order stock.. now convert this sales order stock unrestricted use stock..
Now before you are doing PGI for sales order A... go to sales order change VA02 and change the requirement type to KSL from KE and then system will all you to do PGI with unrestricted use stock...
Thanks
Kumar

Similar Messages

  • Problem when creating planned order with MRP run

    Hello,
    I create a material with a fix reorder point, MRP type VB. When I run MRP with MD03 on this material I have several problems :
    - planned order is created with an opening date in the past, so I have error 'Opening date in the past' in MD04. How can I generate a planned order with opening date not in the past
    - when changing manually opening date, after running again MD03, I have error 'No BOM selected'. Material is configurable, has a text BOM, a routing and a configuration profile. What is the problem? When modifying planned order, I have message :
    Material requires configuration
    Message no. 61259
    Diagnosis
    Orders and requirements for a configurable material must have characteristic values.
    Usually, you should create a variation for configurable materials managed in inventory management which has the default variant configuration.
    System Response
    MRP: Requirements without characteristic values for a material cannot be planned in MRP.
    Procedure
    Check requirements or orders.
    Create a configuration evaluation for the material in the material master record if necessary.
    Thanks in advance.

    Hi
    I am facing the problem. Could you please tell me if you have resolved the above problem? If yes, Could you please provide me as how you resolved? Thanks in advance.
    Thanks
    Nagesh.

  • No sales orders with MRP-relevant requirements were found MD04

    Hello MM Enthusiast,
    We are in process of EHP upgradation and I need to replicate the following error message,
    No sales orders with MRP-relevant requirements were found
    Error message MF 336
    Please let me know how to get the above message in S environment.
    I have gone through the already discussed thread (http://scn.sap.com/thread/3460655) but couldn't able to get the message MF 336.
    Based on your response I can replicate and apply the causing / resolving note given by SAP AG.
    Looking forward to your valuable input to proceed further on this issue
    Cheers,
    Kumar S

    This issue was solved using a different availability checking rule in MRP3 of the material master.
    the old checking rule  had a requirements summary, while the new was for individual requirements, this setting is defined in OVZ2 customizing transaction.
    Hence you need to enter a checking rule in your material master which has a A as sales requirement in OVZ2.
    then create 2 or more new sales orders for this item for the same delivery date.
    After that you should get the error in MD04

  • Production orders in place of planned orders in MRP run

    Hi,
    Please help me with this senario,
    we receive saleorders through CRM interface then these are chnged to redistribute to different plants by changing the plants in saleorders.
    we want to run and create production orders directly for these saleorders without creating planned orders.
    I tried using strategy 82 but it makes the production order online, but we want it to be created after mrp run.
    Is there a way to create production orders instead to planned orders in MRP run.

    Hi You used Right strategy only.Use Strategy '82',  Transfer requirement from CRM and execute MRP run in Background.It will generate Production order.But i didn't understand what you mean by 'Online' 3
    Pl.  Correct me If I am wrong.
    Edited by: Velmurugan S on Mar 4, 2008 10:02 AM

  • My new Tecra A11-11K comes with w7-64bits, but I need w7-32bits

    My new Tecra A11-11K comes with w7-64bits, but I need w7-32bits due to an old program I use for professional purpose.
    I've bougth a w7 license with 32 and 64b.
    My question is how to install w7-32 over 64. I think it's as easy as plug the CD and go. yes?
    But I'd like to preserve Toshiba Utilities other programs that come with the w7-64 pre-installed. Where can I get them? From Toshiba download center?
    And which of them I need? All?
    Thank you for your help.

    Hello
    The Toshiba tools like Value Added Package, Eco Utility, etc. can be downloaded on official Toshiba website:
    http://eu.computers.toshiba-europe.com/innovation/download_drivers_bios.jsp
    Some preinstalled tools like Nero only available on preinstalled Windows version and cant be downloaded but there is a small freeware version of Nero that can be downloaded from Ahead directly:
    http://www.nero.com

  • Somehow, I created 2 Appe ID's...1 from home and 1 from work.  I purchased additional space on iCloud with one ID, but I need to transfer it to the other.

    Somehow, I created 2 Appe ID's...1 from home and 1 from work.  I purchased additional space on iCloud with one ID, but I need to transfer it to the other.

    Having read some other posts I think I have answered my question. If I was somehow able to terminate my old (unwanted) account and Apple ID I would no longer be able to access the material I bought with that ID-  so I'm stuck. I have to learn how to manage that situation.
    This is unfortunate for Apple consumers. Life is complicated for families these days and this "rule" although it is in place to prevent cheating and fraud makes things unnnecessarily difficult for me and my family as in my niaevity (sic) with the online world I bumbled into this situation. Not everyone is out to rip off Apple - one of the worlds richest corporations- or the entertainers who market their work through iTunes.I would just like to be able to enjoy the entertainment I pay for where and when I like to on whichever computer is available to me. And I'm not terribly computer literate.   
    It would have been nice to have had the opportunity to speak just once to a real person in the employ of Apple to explain my situation to them.

  • HT4236 what determins order photos are transferred, photos have been numbered and appear in the correct order on the laptop but transfer in a random order in some albums

    Can anyone assist witth the following query
    What determins order photos are transferred, my photos have been numbered and appear in the correct order on the laptop but transfer in a random order in some albums irrespective of title or date taken.
    Can i alter any setting to ensure photos will transfer in a logical order to track the history of the events in any particular album folder.

    Thanks for this, I have checked the dates in case the camera settings had been lost unfortunatly in this instance all pics are dated in correct order but not transferred in date order, or date modified order, or is the date config based on US date atyle?

  • Process order required for each sales order without mrp run

    Hi, it is mto scenario. wants system to create a process order for each sales order without running mrp. please advise is it possible? if possible please guide what settings need to be done. Thabk you.

    HI
    You can create production order with reference  to sales order using t code CO08.
    Check and revert
    Regards
    Anupam Sharma

  • Sales Order Assignment not seen in Production order after MRP Run

    Hi,
    I am running a Scenario with Strat 50.
    I am maintaining Strat 50 thru MRP Group in MRP 1 View.
    Creating Production Order through Sales Order.
    When i am running MRP thru MD02 I am able to convert it to Planned Order but when i convert Planed Order to Production Order, i am not able to get Sales Order assignment in production order
    Please guide me,
    Thanks in advance,
    Harris

    Dear Harris,
    Sales order planning is done via MD50 not MD02.Hence,please execute the MRP run via MD50.
    This will copy the requirement from SO and the appropriate procurement proposal will be generated,say planned order.
    Here we will be able to view the sales order assignment.
    Regards,
    Joseph Charles Vaikathussery
    Edited by: Joseph  Charles on Nov 3, 2010 4:26 PM

  • MRP Type V1 does not consider Ext. req. Sales Order after MRP run

    Hi Buddies
    My client wants to use MRP Type V1 which should consider re-order point as well as external requirement (i.e. Sales Order) for net requirement calculation.However when i tried using V1 in material master and ran MD03 it only considered re-order point  and ignored Sales Order.Sales Order didnt even reflect in MD04.Moreover in OMDQ for V1 under additional ext req there is no Sales Order for selection.
    Please reply how i can have ext req sales order for MRP Type V1.
    Regards,
    Sachin Narvekar

    Hi
    MRP Type V1 creats the requirement when the need exceeds the Reorder Point, where as the MRP type VB creats the requirement when the stock qty goes below the reorder point.
    Regards

  • Sales order to MRP Run

    Hi friends
    How to configure MRP run for sales orders.
    Thanks in Advance
    Rheya

    Hi
    In order configure MRP for sales orders, check on Transfer of Reqirments on the net or check for the same in Gylence book for Sales and distribution
    Few settings for the same are as follows
    In t code OVZI
    img-sd-basic functions-availablity check and transfer of requirements-transfer of requirements--determination of requirements types using transaction
    In this img activity we assign requirement type to the combination of item category and MRP type
    I hope this is what you are looking for
    In t code OVZI if you go the details you should give the source as 1
    Then only it will pick up
    This is the pick up strategy
    In t code OVZI requirements types are assigned to item category and mrp types
    In t code OVZH requirements types are assigned to requirement class
    In OVZG we define the controls for requirement class

  • MRP run but no planned order creation

    Hi ,
    I use MD61 to create PIR , i can saw PIR in MD04 sceen.
    Then i run MRP via MD02 there is no planned order be created.
    But if i run MRP via MD43 , the planned order appear .
    Could anybody can help on the topic ? Thanks !

    Dear Denny Sheng 
    i think you are asking about two different things:
    1) you have enter PIR in md61and those are reflected in md04,but when you take MRP Run( md02) planned order are not created.This is because there must be stock of material available
    2) The planned order are created when you run md43.This means you have selected MRP Type MPS.please check .
    Regards
    Prashant

  • Steps for sales order to MRP Run

    Dear all,
    Could you please explain what are the steps to process after creating sale order to run MRP and delivery?
    Regards
    Rajasekaran

    Hi Rajaseshekhar,
    Following will be detailed end-to-end process steps.
                     Create Sales Order Entering Finished Goods Material
                     Master
    Auto Generate Alert(E-mail) to Production Planner
                    Create ‘Order BOM’ by Copying Finished Goods BOM (Sales
                     Order Item). Amend by deleting/adding Items in Order BOM at all levels
    Auto Generate Alert(E-mail) to Product Cost Controller
    Recalculate 'Sales Order Costing' to reflect changes to ‘Order BOM’
    Auto Generate Alert(E-mail) to Production
    Run Sales Order MRP
    Convert Planned Order to Production Order
    Capacity Leveling
    Release Production Order
    Pick Components (Picking List)
    Confirm Assembly Activities
    Post Goods Receipt (Production Order)
    Delivery Processing for Sales Order
    Create Invoice
    Hope ite helps,
    Jatin

  • Generate Plan Order from MRP Run (MD51) by WBS Element

    Dear All,
    1. I have created sales order with assigment WBS element (VA01)
    2. Then I created Routing & BOM for Material (CA01 & CS01)
    3. Generate MRP Run (MD51)
    The problem the generated mrp run doesnt consume planned order .. i have set the planning strategy 21 or 40, but still doesnt works.. is there any other parameter that i should configure..???
    Help Me...
    MamaRara

    Hello,
    Hopefully, the following link can assist you.
    - Re: After firming planned order, new planned order is generating in MRP run
    - Basic Scheduling in MRP run
    - Re: MRP run
    - During MRP run unwanted plant and storage location include and exclude
    - MRP run does not consider the common stock
    Thanks & Regards
    JP

  • Multiple planned orders in MRP run

    Hi All
    I have a requirement where I need to create multiple planned order for the same material during MRP run. I understand that once I run MRP a planned order creates. If I run again for the same material, the quantity will be changed for the same planned order. Do we have any configuration so that system creates multiple planned orders for same material for each MRP run.

    Hi Adithya
    Planned orders may be changed by MRP until they are firmed. Therefore, what you need to do is to firm the planned orders after the MRP execution.
    You can use for example, transaction MD19 to mass firm planned orders after each MRP run.
    Otherwise, you can user BAdI MD_PLDORD_CHANGE to automatically firm the planned orders created by MRP.
    BR
    Caetano