Sales pricing from Project Simulation Version

hi.
Has anybody created sales pricing for the project using transaction DP 82? It does not create the sales pricing for the simulation version, even though I have provided the version key.
The status of the simulation version of the project is CRTD. I am using the network cost planning in the simulation version of the project. Am I missing something here? I am hoping to get an answer from this community. Thanks for your help in advance.
Regards
Mey

Hi
The following are the prerequisites for the sucessful fuctioning of sales pricing for simulation versions of the project.
1. A dynamic item processor profile (DIP profile) must have been maintained in the customer inquiry.and must be Customized for Project System.
2.The same DIP profile must have been entered on the Sales B tab page of the item detail view in the SD order.
3. A customer inquiry with at least one item that has to be maintained and assigned to a billing element must exist. The system determines the SD data for sales pricing from this inquiry item.
4.You have planned costs (in concordance with cost elements) for your project version.
If these prerequisites are met, i think it will work
Reward if helpful
Regards
Murali

Similar Messages

  • Quotations from Project Simulation Version

    Hi experts,
    We are creating project quotations using DP81. We create multiple quotations for the same inquiry using Project Simulation Version.
    We would like to know from which version the quotation document has been created, is it possible?
    Or can you suggest any workaround?
    Thanks

    Hi,
    Both options, as in DP81 we are able to select simulations versions.
    But onces the quotations has been created we can't know the source. we know the project as is informed in the account assignment but not the simulation version we have used.
    Has anybody faced this issue before?

  • Project Simulation Version

    Hi,
    Is there any Function Module or BAPI to extract all details of PRoject Definitions and WBS element and Network Activities for Project simulation Version/Version key.
    Thanks
    Ramesh

    Hi,
    Both options, as in DP81 we are able to select simulations versions.
    But onces the quotations has been created we can't know the source. we know the project as is informed in the account assignment but not the simulation version we have used.
    Has anybody faced this issue before?

  • Sales Pricing in projects - DP81

    Hi
    I am trying to create quotation from planned costs in project.
    I have configured DIP profile but getting the error “no expenditure items found” when I run sales pricing
    Please update what can be the possible cause of this problem or solution to rectify.
    Regards
    Ramandeep

    Hi
    I meant Dynamic item processor profile only.
    Regards
    Amal

  • How to create Sales Quotation from project through DP81

    Dear Guru's,
          How to create Sales Quotation(VA22) from project through DP81, what all the customization settings are required for this functionality; please explain me all the step those are required for this process.
    Regards,
    Sai

    Hi,
    You can use DP81 and DP82 to create Quotations .
    If you want to use DP81 then you need to link Sales Inquiry with Project by entering the WBS Element in Account Assignment Tab of Inquiry and also enter the DIP Profile in Sales B View.
    Else you can carry sales pricing without the creation of Inquiry.Enter the DIP Profile ,Dist Channel,Division in control data tab of project and also enter Sold to party in Partner tab.
    See SAP help for customisation of DIP Profile .
    Muzamil

  • Comparison between Opreative Project & Simulated version

    Dear Colleague,
    I have one query regarding simulation version, may I know how I will compare operatioe project with any simulation version by using SAP standard reports like CN41N. I already maintained version check box ticked in DB profile. As I know that we can easily compare Project version with operative project but do not know how to compare operative project with simulated version. Please just advice...
    Regards,
    Ashok Sangal

    Hi Ashok,
    Simulation versions are compared with operative versions in the same manner in which project versions are compared with operative project. The simulation versions for the project appears in the "Project version" selection. Select the required Simulation version to include it in the results.
    regards
    Sejo

  • Sd depot sales pricing from me21n to vfo1

    i want automatic pricing at vf01 through me21n.
    pricing should flow from me21n to vf01

    Hello Prasanna,
    In Stock Transfer Cases there is no Sales document in SD, but still the basic Sales Order Functions like Item Category Determination, etc happens.
    This is due to Default Order Type assigned to Delivery Type (NL or NLCC). Thus system uses settings in Sales Doucment Type DL to determine basic SD Functions.
    Now coming to your question, in the copy control records Price Source is not required to maintain becase you are purely using SD Pricing Procedure itself.
    In Billing Type, the Pricing Procedure will be simply SD Pricing Proceure with normal Price Detemination settings. But when it comes to maintaining Condition Records (in VK11) you will not be able to do so. This is because you have set Reference Condition (& aplication) in Condition Type (V/06).
    The use of this setting is that you cannot maintian Condition Records in Sales Module, but System will access the Condition Record of the Referred Condition Type & Application (M - Purchasing). Thus if the Price components (Basic Price + Tax + etc) are exactly same in SD & MM Pricing, then values can be copied from MM Pricing. Means say for Basic Price (ZR00) you have set Reference Condition Type as ZN00 which is defined in MM Schema (Pricing Procedure), then system will search value for ZR00 in Condition Records of ZN00.
    We are using this in Sales Order & Shipment Document. We have a requirement that the Freight paid to Shipment Vendor should be eaxtly same as one charged to Customer in Sales Order / Invoice. Thus Reference Condition is a perfect solution here without any Z-Development.
    Hope I have managed to clarify your doubt to some extent.
    Thanks,
    Edited by: Jignesh Mehta on Feb 15, 2012 1:11 PM

  • Repetitive milestone copying in the sales order from Projects

    Hi friends,
    A particular WBS element with, say 5 milestones with the invoice percentages adding up to 100%, can be assigned to multiple line items in a sales order. Hence the milestones can be copied to each line item. I want to stop this repetitive copying of same milestones. Since each milestone has a particular number attached to it, I want to stop this multiple copying with the help of this milestone number. Is there any user exit for this? Please let me know.
    bye
    Pratap.V

    Hi Pratap,
    I couldn't find the exact user exit for your query but the below link shows some of the user exits related to milestone billing methods, may it help you .
    http://help.sap.com/saphelp_45B/helpdata/en/22/f62c7dd435d1118b3f0060b03ca329/content.htm
    Thanks,
    Dhruv

  • Explode BPOs or BOMs in Easy Cost Planning from Project Builder

    Hi,
    Has anyone had the requirement to be able to explode BOMs or BPOS (in costing models) while in the ECP screen in Project Builder. Is there an enhancement which one could use to do this, or do one of the Industry Solutions adress this?
    Regards
    Marc

    hi chandra...
    you are doing correct, nothing wrong in process.....
    but as a practice it is not advisable to make any changes in ECP for your operative project.....
    if you want to make changes in ECP then just creat one simulation version and make changes in that.... & then  do sales pricing for that simulation version....
    advantages
    1) you will have track of all quotation you submitted... ( for all operative as well as simulation project)
    2) if any quotation got selected from customer ( say simulation version sim002)  then you just transfer that simulation version to operative one & start workin on that..........
    in your case
    you will keep on changing your ECp you will not have track wich quotation you submitted what was the price what was the strucuture & ECp...... you will not come to know.....
    Please correct me if i'm wrong.....
    Venkatesh

  • ECP with network activities and sales pricing

    Hi experts,
    Currently I have configured the system so that I can plan costs by assigning Easy Cost Planning templates to network activities and WBS elements. However, when I try to create quotation (sales pricing) from Project Builder (CJ20N), the planned costs of ECP templates assigned to network activities does not appear, only the planned costs of ECP directly assigned WBS element appears.
    Thanks in advance.
    Hieu Nguyen

    After extensive testing, I believe doing sales pricing from Project Builder would not work correctly when using ECP with network activity. Sales pricing from Project Builder will only work properly if ECP only assigned to WBS element.
    If you need to use ECP with network activities, you would need to use DP82 to do the sales pricing.
    Regards,

  • Simulation version to Operative project

    Hi experts,
    I am unable to create an operative project structure from a simulation version using project builder.
    My req:
    I have sim version:  T-90001/ SIM001
    I wish to create operative project T-90001
    I can use CJV4 for transfer of project. But is it possible in CJ20N?
    Warm regards
    ramSiva

    Hi Ravi
    Thanks for your response
    Please look at the link http://help.sap.com/saphelp_erp60/helpdata/en/0b/ba853488601e33e10000009b38f83b/frameset.htm
    There is an illustration which depicts that,
    - Project P1234/version 0001 --> Project 1234 --> Project P1234/Version 0002 --> Project P1234
    As per this illustration, the project number remains same.
    As you said, the transaction CJ20N is not allowing me to transfer the simulation version to operative project.
    But, i am experiencing a dump error while trying to transfer simulation to operative in CVJ4.
    At the conclusion, i mean to say that irrespective of transaction code, this may be allowed.
    Please comment.
    warm regards
    ramSiva

  • Proforma Invoice or Quotation from Project

    Hi Experts,
    My client requirement is like this:
    1. Receives request for procurement of goods/service from different user departments.
    2. Will send estimation to the user departments and will proceed further.
    I want to map like this through PS (SD module is not there):
    1. Receive requests
    2. Will create a simulation/plan project version
    3. Will generate the proforma invoice / quotation from the planned costs of this version.
    please let me know exact way to achieve the same.
    Satish

    Hi Satish,
    I am not quiet sure of what exactly is the requirement. It appears that the user department will send the PR to the estimator and  and  then the estimator will estimate the cost and send back to the User. Is your question related to the process of estimation and the way it has to be communicated back to the user?
    Can you please repharse your question for better understanding...Sinces the question is not very clear.
    If you want to Go for Sales Pricing thru projects.and create quotations..then SD module is required.
    Warm regards,
    Srinivas Potluri
    Edited by: Potluri Srinivas on Jul 23, 2011 3:35 PM

  • ECP &sales pricing issue

    Hi
    i have use ECP , plan cost on WBS
    i am getting one Run time error while am doing sales pricing from cj20n..
    INPUT error , DLI not found
    pls help
    Thanks

    Hi,
    The service Mat that you used in ODP1(DIP Prof customising) is not maintained properly for Sales organisation that you are using.Please check and use some other service material in Mat determination in DIP Profile and also create sets and use them in ODP1.
    There is one SAP note for DIP Profile customisation please go through that.
    Regards
    Muzamil

  • Slaes pricing using simulation version

    Hi experts,
    Is it possible to create sales pricing using simulaton version project ?

    Hi Ravi
    Thanks for your response
    Please look at the link http://help.sap.com/saphelp_erp60/helpdata/en/0b/ba853488601e33e10000009b38f83b/frameset.htm
    There is an illustration which depicts that,
    - Project P1234/version 0001 --> Project 1234 --> Project P1234/Version 0002 --> Project P1234
    As per this illustration, the project number remains same.
    As you said, the transaction CJ20N is not allowing me to transfer the simulation version to operative project.
    But, i am experiencing a dump error while trying to transfer simulation to operative in CVJ4.
    At the conclusion, i mean to say that irrespective of transaction code, this may be allowed.
    Please comment.
    warm regards
    ramSiva

  • High Sea Sales mapping in delivery from projects

    Hi,
    I have got a typical scenario where in delivery is supposed to be thru PS.
    Quotation consists of only the predefined Costing heads (non-deliverable & in line items) against which unit cost estimate is made using BPOs. After receipt of order the quotation is copied to create Sales Order  and WBS elements are assigned at line item.
    Deliverable materials are assigned at each WBS level in the designated Project and wrt the Sales Order, deliveries are created and billed. Pricing of the delivered materials is carried out in the billing doc.
    There is a scenario in which imported materials originally planned to be sold from stock and whose delivery was to be created from projects is now converted to HSS.
    Request to advise how to map this business process.
    Regards,
    Rajesh Mohapatra

    Hi Rakesh,
    1. When we do delivery thru CNS0 it Dr- FG Consumption /ac and Cr-FG Stock a/c. Suppose if i have to take this Dr-COGS-Fg and Cr-Fg Stock a/c. will you please suggest the necessary customization steps and user transactions.
    2. In our scenario we have done delivery through CNS0. When we do billing, we are getting an error that Profitability segment is not derived for GL (revenue). I have checked the relevant derivation rules which looks correct. Do u have any idea how to maintain derivation rule to derive WBS element?
    3. In other scenario, intstead of opting PS. We have followed: 1. Cretaed SO (with WBS). 2. MD04- Cretaed Planned Order 3. Converted Planned order to Process Order 4.Goods Issue and confirmation of process order  5.VL01N-Delivery (601 E).
    While doing delivery we r getting an error that create GL (FG-COGS) as Cost element. This is GL is mapped to GBB-VAX.we have for GBB-VAY with cost elemnt. Do we have to create this GL also as cost element? why system is not picking from GBB-VAY? any idea
    Regards,
    Babu

Maybe you are looking for

  • Powerbook hd dying?

    The past day, my powerbook hasn't been sleeping properly some of the time. Anyway, then it started just sitting at the starting up spinny so I went into verbose... it's just sitting here spitting out line after line of IOATABlockStorageDriver::sCompl

  • Which product is best for watermarking photos

    I am new to photo editing software. I'd like to add my logo to my pics in bulk. What product will do this for me the fastest and easiest way?

  • 10.8.4 - Motion 5 - Completely Erratic OSC Controls

    HI... In creating FCPx Templates I have always (Prior to 10.8.4) any Plug with OSC-Controls to control other parameters like Position, via Link. I have used this routine since the dawn of FCPx. Now with this latest version of OS X Mountain Lion - Mot

  • Forms 9i tab pages inside a tab page

    hi, i m using forms 9i, is it possible to set a tab page inside a tab page ie i have a master tab page called 'Office' and i have to add two tab pages called 'excel', 'word' as the sub of this main tab..is it possible.......? if yes how ? thanks in a

  • How to play audio

    Hi, I am developing video chat application.I am able to play published video stream.But I am unable to hear sound which is published along with the video. The video is visible but sound is not comming.What is going wrong.Does anybody could point me i