Hi,
I am basically from PP background and just started working in APO SNP. after running SNP optimzer,not able to see the operation details in SNP planned order ( SNP planned order has only receipts, requirements ). could you please help me how to get operation details in SNP planned order.
Thanks
Krishna.

Hi,
SNP Planned Order:
1 . SNP Planned Orders wil give details about Order start date and finish date .
2.  During  SNP Planned Order creation a basic scheduling will happen.
PPDS Planned Order
1.  PPDS Planned Orders will give details about when the actual production is start and finish.
2.  During PPDS Planned creation the Machine time details defined in the routing routing or recepie will be take into account.
3.  Leadtime scheduling will be carried out to calculate the exact production start date and finish date.
Thanks,
nandha

Similar Messages

  • How to Change Component on a SNP Planned Order ( Just 1 time )

    Hello,
    We are trying to change a component on a SNP Planned Order just 1 time.
    So we do not want to change the PDS since this is one time change only.
    We tried changing it in R/3. Once we do that, R/3 shows new component but APO still shows dependant demand on old component ( May be because APO SNP Planned order is still connected with the PDS ) .
    Then we went to APO and tried to change the component in /sapapo/rrp3. Here you can delete the old component but doesn't let me add new component.
    Next thing we tried was to convert it to PPDS Order. Once converted, we went to change mode and tried to remove old component and add new component. It lets me do this. Only issue with this route is that, it puts correct start and end dates on the order dependning on the order quantity and so order moves the dates which we do not like.
    Is there any other better way to fix this issue ?.
    Thanks.
    Ketan Doshi.

    This being a very unique requirement, I would use one-off approaches usually not followed. You may need to explore the use of BAPI BAPI_MOSRVAPS_CREATESNPORDER. This will help you point the source of planned order to a PPM or a PDS that you may want to create in APO system on a one-off basis. PPMs can be maintained in APO, however PDS are usually CIFed from R3. You can try to create PDS (based on the new component) in APO system only using backend tables. Try do some little research on /sapapo/curto tables to create the PDS in APO. Then use the BAPI to point the source to this new PDS. (better you also try the PPM approach since there are no issues keeping the PPM in APO)

  • SNP planned order availability date difference between APO and ECC

    Hi,
    I have observed that SNP Planned order availability date is not matching between APO and ECC. Details are as follows.
    I ran SNP Optimizer with bucket offset of 0.5. After publishing the optimizer created planned orders to ECC, only start date is matching.
    Example:
    I am using PDS as a source of supply.
    Fixed production activity in SNP PDS is 1 day.
    GR processing time: 3 day
    After running optimizer planned order is created with dates explained below.
    Start date/time: 09.05.2011 00:00:00
    End date/time: 12.05.2011 23:59:59
    Availability date: 16.05.2011 00:00:00
    Because of bucket offset defined as 0.5 optimizer planned order availability is start of next monday.
    After publishing this planned order to ECC dates on the planned order is as follows.
    Start date: 09.05.2011
    End date: 09.05.2011
    Availability date: 12.05.2011
    I have not maintained any scheduling margin key in ECC. Also if I dont define the GR processing time, planned dates between APO and ECC always match. Can anyone explain the impact of GR time on the availability date.
    Regards,
    Venkat

    Hi Venkadesh,
    What's "state stamp"? Do you mean different time zone?
    note : 645597  mentioned by Nandha is very helpful:
    In standard, CCR will use duedate - "the available date of the output product".
    Nandha's words "In SAP APO, if the receipt date of the primary product deviates from the
    end date of the last activity of the order, the receipt date
    always identifies this as inconsistent. You cannot rectify
    inconsistencies of this type by using CCR."
    I guess in your PDS or PPM, the output product is not assigned to the End of the last activity. Someone changed it?
    Please CIF the PDS or PPM again.
    If you really want to apply a note, please use note 815509 as you're using planned order,
    and system will use order end  date in CCR instead.
    GR time is always considered. BR/Tiemin

  • SNP planned order deleted in APO, but not in R/3.

    OK Guru's,
    We have a situation where during the weekend SNP planning runs, SNP Planned orders are deleted in APO, but the order is never deleted in R/3.  The change pointer is not in CPP and there are no failed queues.  Also, when you run CCR on planned orders, we will get an error on some orders saying "Not in APO" and the only option to reconcile that order is to "Send to APO".  The option that should exist is "delete in R/3" becuase the deletion never occured in R/3.
    If you send the order back to APO, the order will show in the "Production Confirmed" line of the Planning Book.  This is because APO is thinking that this order is an order that was created in R/3 when in fact is it really is a SNP planned order.
    Any clues to why this would happen?
    thanks,
    Brian

    How are you getting the SNP Planned Orders to R/3 in the first place.
    If you are transferring them using /SAPAPO/RRP7 then I guesss its a manual transfer and system does not consider SNP Planned Order deletion flag relevant for transfer to R/3.
    You will need to look into CIF enhancement to send the deletions to R/3.
    Normally SNP Planned Orders are not relevant for transfer to R/3 unless its replaced or converted to a PPDS planned order.
    Somnath

  • Converting SNP Planned Order /Purch Req to Prod.Order/Purch.Order

    Guys
    What is the standard process to Convert the SNP Planned Order /Purch Req. into a Prod.Order/Purch.Order ?
    Can the conversion indicator be set in APO for SNP Planned Order /Purch Req.and then transferred to R3 as Prod.Order/Purch.Order  or can the convesrion of Planned Order /Purch Req to Prod.Order/Purch.Order  can be done in R3 itself ?
    I am not clear on how exactly this works. Would appreicate if you could provide me with the standard process and any config involved in the same such as Number Ranges and how to set the conversion indicator automatically through SNP planning runs ?
    Thanks

    When you set this indicator for a planned order or a purchase
    requisition, the system automatically converts the order into a
    Production order or purchase order after the transfer to the
    connected SAP R/3 system.
    The converted orders are then retransferred to the SAP APO system with a
    different category; a purchase requisition with category BS-ANF becomes
    a purchase order delivery schedule line with category BS-EIN.
    Please check configuration setting in SPro for transfer setting to R/3.
    1. Configure Transfer to OLTP Systems(SNP)
    2.Maintain Global Parameters and Defaults(PPDS)
    Also on R/3 side you can see it in MD04/MD07 collectively for a product . or individually on
    MD13 : planned order
    MB51n: PR
    Manish

  • Creating SNP planned order using ''BAPI_MOSRVAPS_SAVEMULTI3'

    Hi Experts,
                      I am new to SAP-APO, kindly clarify my question. I am using 'BAPI_MOSRVAPS_SAVEMULTI3' with source of supply PDS for creating SNP planned order by passing 'EE' in the  table parameters 'ORDER_HEAD-MASTER_ATPCAT'. It is creating a planned order which is PPDS planned order with number range starting from '1000...' rather than creating SNP planned order with number range starting from '8000..'. Please let me know what might be the reason for the BAPI misbehaving incorrectly. Also kindly let meknow what are specific parameters to pass to above bapi to create SNP planned order.

    Hi,
    The BAPI BAPI_MOSRVAPS_SAVEMULTI3 is used for creating PPDS inhouse orders.
    You will have to use BAPI_MOSRVAPS_CREATESNPORDER for SNP inhouse orders creation from SNP PPMs( there is no explict mention of SNP PDS- you may please check).
    Regards
    Datta

  • SNP Planned Order Date

    Hi Experts,
    May I ask for your help. I have a gr processing time of 1 and In-house production of 1 day as well. But whenever I run heuristic, it results in 4 days from start date to availability date. Say April 16 start date and availability date is April 20. Are there other factors on how this is computed?really hoping for a reply from you.
    Thanks! Sincerely, Ria

    Hello Ria,
    Have you maintained any GR time in ECC?
    I faced a similar issue (in PPDS order though) in which it was computing the availability date
    first based on the GR processing time maintained in APO, when the order goes to ECC it would pick up the GR processing time maintained in ECC, and move the availability date of the order in APO.
    We are working on code to stop this transfer back to APO.
    Note 508993 gives more details about the FM.
    You may try an option to stop the transfer from SAP R/3 since you are working with SNP planned orders:
    https://help.sap.com/saphelp_scm50/helpdata/en/80/e8bc0f629af14db213108bb6fa7515/content.htm?frameset=/en/b3/32c5d32970834dadf53cac0aa2b5b4/frameset.htm&current_toc=/en/9b/954d3baf755b67e10000000a114084/plain.htm&node_id=147
    Hope this helps you!
    Regards,
    Subhash

  • SNP Planned order - Doesnt get the complete BOM when CIFd to ECC

    Hello,
    When we create SNP Planned order in APO and sent to ECC, the Planned order doesn’t get the complete BOM, it works for the most part, except if we have Materials from multiple plants within the same BOM (sourcing from multiple plants).
    Do we have to do any separate Configuration for this scenario?
    We are planning only the End item in SNP, and we are generating the production version and PDS transfer to APO. We are not transferring all the materials to APO.
    if we go to the Change mode of the Planned order in ECC and re-explode the BOM, I get all the components from the BOM, its just that when the planned order gets created thru the CIF we have this issue.
    Any help would be appreciated.
    Regards
    Gk

    Hello Marius
    Thank you for your quick response.
    I looked at the SAP note you mentioned, the description seems to be matching with the issue we are having. Recently we had SNC implemented, and the note states that that can be the case why the components are getting deleted during planned order creation.
    The only thing about this note is its very old, and we are having the SAP 6.0 and SCM 7.2 ,
    Do you think this would be still applicable.
    I will look into the details and let you know whether the note is applicable for us.
    Regards
    Gk

  • SNP Planned Order

    Hello Experts,
    Scenario: we plan finished goods in SNP & for component level we run MRP in ECC.
    I need to understand how MRP does planning in ECC based on SNP Planned order. Why MRP run does detailed scheduling on Finished goods planned order which released from SNP?
    I am not getting why MRP in ECC considers material which has X0 MRP type & it does detailed scheduling on finished good planned order & it changes start date & time of planned order which push back or forward sometime in SNP.
    Can anyone explain why MRP does detailed scheduling on finished good planned order? And after sheduling why it changes start Date & Time?
    Thanks in Advance
    Regards
    Sujay Joshi

    Dear manimaran
    I am going through the same scenario as joshi....component planning is done by MRP and planning for final product is done by SNP and PP/DS......say i have planned order from SNP and PP/DS
    1. can i subject those planned orders to MRP run again by bringing back to ECC
    2.If its is possible how do i see what is the screen wherein i will see that planned orders from SCM has arrived to ECC
    3.what tcode do i use to subject those scm planned orders to MRP run
    I have detailed a implentation procedure i would be happy if you can say if it is logically correct,if it is not correct then which is the correct logic.
    Planning will be divided into two parts ,Plant level planning and supply chain planning, for Plant level planning traditional MRP run is mandatory to determine the requirements at the plant level.
    DMS (Distributor management system ) to be used by all customers
    Capture the demand from all the market segment  into DMS and upload the demand in SCM
    Create a demand plan in APO and release it in SAP R/3 Demand management after confirming the demand.
    Maintain material master for all the materials on demand.
    Maintain relevant production version in C223
    Run traditional MRP
    Calculate exact  quantities by creating production order in R/3.
    Transfer the quantities  required for specific time period alone to APO,for example if you want to allocate capacity to run 4 shifts transfer the approximate value of quantity alone to APO, the time period may be for 7 shifts or 1 month ,which is industry specific. 
    Perform simultaneous capacity and material planning in PP/DS  (or)
    After rough cut planning in APO, SNP perform simultaneous planning in APO , PP/DS ,using any one of standard heuristic like PP_001 or MRP_001 or PP_002
    Adopt planning procedure =3
    Confirm the production order in R/3
    thanks
    Saravanan

  • Creation of SNP planned order based on PDS

    Hi,
    I'm a APO developer and I have the following problem:
    I would like to create a SNP planned order based on a PDS (like e. g. in the planning book when you input a number into a cell in the "Production (Planned)" line).
    Up to now I've only managed to create such an order without using the PDS.
    Can you name me a function module which allowes me to do that?
    Thanks in advance.

    Hi,
    I've now managed to create this kind of order.
    I set a breakpoint at the function module /SAPAPO/DM_PROD_ORDER_CHANGE and checked how it was filled in the planning book.
    For those who want to know:
      INCLUDE /sapapo/constants_om.
      CONSTANTS:
        lc_order_type_1f        TYPE /sapapo/om_order_type VALUE '1F'.
      DATA:
        ls_prod               TYPE /sapapo/msnp_prod,
        lt_prod               TYPE /sapapo/msnp_prod_tab,
        ls_sources            TYPE /sapapo/sources,
        lt_sources            TYPE /sapapo/sources_tab,
        lv_matid              TYPE /sapapo/matid,
        lv_locid              TYPE /sapapo/locid,
        lv_vrsioid            TYPE /sapapo/vrsioid,
        lv_tstfr              TYPE /sapapo/timestamp,
        lv_tstto              TYPE /sapapo/timestamp,
        lv_simsession         TYPE /sapapo/om_simsession.
    lv_vrsioid = '000'.
    * Create SimSession
    CALL FUNCTION '/SAPAPO/TSIM_SIMULATION_CONTRL'
        EXPORTING
          iv_simversion              = lv_vrsioid
          iv_simsession             = lv_simsession
          iv_simsession_method = 'N'
          iv_perform_commit       = space
        EXCEPTIONS
          lc_connect_failed        = 1
          lc_com_error             = 2
          lc_appl_error            = 3
          multi_tasim_registration = 4.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
    * Get PDS
      CALL FUNCTION '/SAPAPO/MSDP_SNP_PPM_VALIDITY'
        EXPORTING
          iv_vrsioid      = lv_vrsioid
          iv_matid        = lv_matid
          iv_locid        = lv_locid
          iv_tstfr        = lv_tstfr
          iv_tstto        = lv_tstto
          iv_planstart    = lv_tstfr
          iv_planend      = lv_tstto
        CHANGING
          ct_sources      = lt_sources
        EXCEPTIONS
          wrong_interface = 1
          error_occured   = 2
          OTHERS          = 3.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
      READ TABLE lt_sources INTO ls_sources INDEX 1.
      ls_prod-version       = lv_vrsioid.
      ls_prod-matid         = lv_matid.
      ls_prod-locid         = lv_locid.
      ls_prod-plobid        = '9AMALO'.
      ls_prod-tstmp         = lv_tstfr.
      ls_prod-catgr         = 'PP1'.
      ls_prod-categ         = 'EE'.
      ls_prod-categ_prku    = 'EE'.
      ls_prod-categ_prse    = 'EL'.
      ls_prod-kz_prod       = '9APPROD'.
      ls_prod-kz_prku       = '9APPROD'.
      ls_prod-kz_prse       = '9ADMDSE'.
      ls_prod-produ         = '1000'.
      ls_prod-proid         = ls_sources-trpid.
      ls_prod-mosta         = gc_new.
      ls_prod-order_type    = lc_order_type_1f.
      ls_prod-is_fixed      = 'X'.
      ls_prod-snp_is_header = 'X'.
      APPEND ls_prod TO lt_prod.
      CALL FUNCTION '/SAPAPO/DM_PROD_ORDER_CHANGE'
        EXPORTING
          ic_database           = 'LC'
          ic_application        = '4'
          iv_simsession         = lv_simsession
          it_prod               = lt_prod
          iv_netch              = 'X'
        EXCEPTIONS
          material_not_supplied = 1
          location_not_supplied = 2
          OTHERS                = 3.
    * Merge simulation version (to commit order changes)
      CALL FUNCTION '/SAPAPO/TSIM_SIMULATION_CONTRL'
        EXPORTING
          iv_simversion                = lv_vrsioid
          iv_simsession                = lv_simsession
          iv_simsession_method         = 'M'
        EXCEPTIONS
          lc_connect_failed            = 1
          lc_com_error                 = 2
          lc_appl_error                = 3
          multi_tasim_registration     = 4
          target_deleted_saveas_failed = 5
          OTHERS                       = 6.
      IF sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.

  • Bapi for sfg dependent dem,snp planned order qty, and ppds planned orde qty

    Hi Gurus,
    I am not much familiar with APO, so please help me,
    Input details:
    Field                         Value     
    Planning Version     000     
    Source Location *     1001     Single/Multi Value
    Product *                          1000061     Single/Multi Value
    Production Planner *     PRC     Single/Multi Value
    Start Date *          
    End Date *          
    o/p:
    Source Location     Date     Semi-Finished Material     Material Description     SFG Dependent Demand     SNP Planned Orders qty     PPDS Planned order Qty     Total SFG Variance due to Lot size     Total SFG Variance reference to dependent demand
    1001     15-Jul-10     1000041PP     PRIMARY FF MILK  3% FAT     340     412     420     8     80
    1001     15-Jul-10     1000041PP     PRIMARY FF MILK  3% FAT                         
    1001     15-Jul-10     1000041PP     PRIMARY FF MILK  3% FAT                         
    Is there any bapi to fetch the data as shown in o/p.
    Thanks

    Hi Phani,
    Tryout the below BAPIs
    IF10503 (object)
    BUS10503
    Regards
    R. Senthil Mareeswaran.

  • Issue in Deployment of SNP Planned orders

    Hi Experts,
    I am trying to deploy SNP Planned orders and I have made relevant settings in SNP2 i.e. ATP category in ATD Receipt.
    When I run deployment, it creats deployment stock transfer (DEP: PReq / DEP:ConRl) based on available stock first. When I run deployment second time, then it creats deployment stock transfer( DEP: PReq / DEP:ConRl)  for SNP Planned order with the same quantity of stock & not for entire quantity of SNP Planned order. Please refer below example to make it clear
    Total Demand at destination location = 600
    Stock at supply location = 100
    After planning run, Purchase requsition of 600 is generated at destination location.
    At supply location, SNP Planned order of 500 is generated considering 100 stock is available against PReqRel of 600.
    When I run Deployment first time, it forms DEP: PReq / DEP:ConRl  of 100 based on available quantity of 100.
    After running Deployment second time it forms again DEP: PReq / DEP:ConRl  of 100 and it continues to create deployment stock transfer till it completes the quantity of SNP planned order.
    So all together it creates 6 deployment stock transfers instead of forming one deployment stock transfer (stock+ SNP Planned order).
    There is no lot size setting for product master.
    Can anyone suggest whether I need to do some settings to get one deployment order instead of 6.
    Thanks & Regards,
    Chetan
    Edited by: Chetan Patil on Nov 10, 2010 4:45 PM

    Hi Chetan,
    It looks the SNP planned order is not being considered in the receipts quantities  to be available for deploying against requirements.
    Please check SNP order  ATP type( it  is normally EE)  is included in the appropriate Categroy group
    IMG >> APO > Supply Chain Planning  > SNP > Basic Settings > Maintain Category Groups
    Example :  ATD Receipts:   ATR
    Typical values :    AI, AJ, BF, CC,EE,EF, EI
    Secondly, in the transaction /SAPAPO/MSDP_ADMIN, in the Key Figure detailed  tab, ATD Receipts should have assigned the Category Group(say  ATR).
    Regards
    Datta

  • SNP Planned order not following resource bucket capacity/factory calendar

    Hi gurus,
    SCM 5.0
    I am running SNP heuristics for a product and expecting planned orders for it.  It has corresponding production data structure and multimixed resource.  The resource has an assignd factory calendar and SNP bucket capacity.  The bucket capactiy availablity dates of the resouce is consistent with the factory calendar workdays/holidays.  Using simple lot for lot strategy, I am expecting heuristics to schedule the planned orders on the dates of the demand in compliance with teh SNP bucket capacity availability of the resource.  APO does not schedule on holidays consistent with bucket capactiy.  This is true until...
    We have a public holiday in factory calendar that needs to become a workday. To remedy this, we put a special rule for the factory calendar and explicitly made that holiday into a workday.  The changes were synchronized with APO, and this is also reflected in the bucket capacity of the resourc: former holiday now has bucket capacity after the calendar change.  However, when running heuristics, it still does not create SNP planned order on that former holiday that has been changed into workday.  Even if it is a public holiday, there is already a special rule for the factory calendar and the resource bucket capacity reflects this correctly. But SNP heuristics seems not to follow this change.
    Any ideas on this? looks like a bug.

    Hi Edgar,
    Yes, when your resource reflects the addional capacity of the holiday turned working day, then it is expected to be considered for the SNP planned order.
    Instead of SNP heuristics, you may try to check interactively in SNP planning book, if manual order creation in the bucket works out.
    Since this is a mutlimix  resource , it can also be checked if in PPDS planned order can be created on the day.
    The above checking may not solve your problem , but will get to know if at least manully the bucket is being considered or not.
    regards
    Datta

  • Pegging relation for stock got lost once we do changes to the SNP planned order.

    Hello Experts,
    Pegging relation for stock got lost once we do changes to the SNP planned order.
    We are using a BAPI  "BAPI_MOSRVAPS_CREATESNPORDER" to make changes to the planned order as per our business requirement.
    However after changes the pegging relation got lost.
    Please help, why and how to solve this.

    Dear Krish,
    While creating orders using BAPI pegging relationship will be lost.
    Could you be more clear which orders you are creating?
    Some times dynamic pegging is possible.
    Regarding pegging relationship please check the link, it may help you.
    Pegging - SAP Library

  • How we can define User Constraints in SAP APO SNP?

    Hi
    How we can  define flexible User Constraints in SAP APO SNP ? Meaning standard constraints can be configured in SAP APO SNP but how we can configured real time  customer constraints?
    Thanks
    Poorna

    Hi,
    You can use CIF user exit CIFMAT01 for this purpose. You can follow below path in SAP for more details
    SPRO---SAP refrenceIMG----Integration with other SAP components---Advanced Planning and Optimization---Application specific settingsand enhancements---Enhancement for materials---Influence data before transfer to APO on user specific basis.
    YOu can read help in above path about exit.
    YOu need ABAP person who need to code this. What you need is read custom field from table from MARC  and Populate in procurement cose field in this exit.
    Regards,
    Santosh,

Maybe you are looking for

  • Upgrading CPU

    Hi everyone!Before 6 months I bought HP Pavillion 15-p000su. I just wanted to ask (because my knowledge about laptops is too **bleep** low..) if it's possible to change the laptop processor which now is AMD Quad-Core A8-6410M 2.00 GHz, 2 MB cache wit

  • Vendor hierarchy full process

    i would love to know all about vendor hierarchy,including customizations please help.

  • V11.1.2.3 Rapid Deployment Issues

    In spite of a reportedly successful install I am having issues. Java was not installed as a part of the Deployment - I have installed it now after the rapid deployment. When trying to open Workspace I am getting a hang on a "Bindows" screen saying th

  • Not working lenovo photo master

    i like the photo master app but it got corrupt (very soon after purchasing the laptop) and so I had to delete it. Now I want to install it again but there is now possible way I can get a download link. Anyone has a clue to how I can get a fresh copy?

  • Message types related to MM module

    hi friends, I want to know the standard masters for MM modules. according to the masters i want to know the Message types. can anyone give the t code for searching the message types. i am searching by using WE81, i got the no of message types but i c