SAP BW project brief

Hi gurus
would anybody please advise me the structure of BW project team and the steps the team needs to go thro while implementing the BW in the organisation already having SAP installed?
Also advise the relation between technical and functional document and how the documentation can be done during BW implementation?
Thanks in advance.

Hi,
In normal BW project, we will have Technical team, Functional team and Basis team
The structure of BW team is 
Project manager
Project leader,
Team leaders,
Team members.
Initially we will do business requirement analysis for business specifications or requirements by conducting seminars, workshops and meetings with Business executives and report owners.
Once we done with Business requirement analysis then we do Analysis on Business content for suitable extractors and infoproviders according to the business requirements then we will create all designing documents for each and every dataflow then
Realization, Testing,Cutover,Go live,PostGolive support.
Functional documents contain all the information about the business specifications or requirements:
Technical Documents contains all the information about the designing of BW dataflows.
Best Regards,
VK Siddu.

Similar Messages

  • SAP Enterprise Project Connection 2.0 in SAP ECC 6.0 EHP6

    Hello experts,
    Before describing any think let me tell u that i am very new to this field.
    We are configuring SAP Enterprise Project Connection 2.0 in our SAP ECC 6.0 EHP6 .I have already installed ABAP add on for EPC in ECC system.
    I have also installed trial version of primavera6 in another system.So now how can i connect my ECC system to Primavera6 through Enterprise Project Connection(EPC). I have gone through the installation guide for SAP Enterprise Project Connection 2.0 SP2.But i could not get any clear idea.
    Any reply is helpful for me..
    Thanks
    Debasis

    Hello Debasis,
    Post EPC installation,you need to perform configuration of EPC through portal.You can see it listed under configuration--> configuration scenarios-->EPC.
    During configuration you will be asked to define path of you primavera installation and a user on that system with sufficient permissions. This user is called APS user.
    Try to do a mock configuration run on sandbox/dev system and then you can follow the guide.
    Regards,
    Hetal

  • SAP Retail Project - Assembly Order configuration

    Dear all,
    We are into SAP Retail Project, as per the process we have to generate an assembly order to our internal workshop to assemble the product.
    this assembly order has to generate from sales order. Articles required to assembly will be maintained in workshop only.
    we are not implementing Production module, we are trying to create a purchase requisition from sales order. but the BOM main items purchase requisition is not getting generated and there is no communication between sales order and workshop regarding Assembly process.
    I am expecting an expert advice, with config steps to map this process into sap. Your suggestions will be highly appreciated.
    Thank you
    Raghu ram.

    Hi Mohan,
    Thanks for the useful link you shared.
    But I am looking for specific configuration and master data set up required for store order creation scenario where " Warehouse stock is created if stock exists else third party order is created"
    This option is activated in POS interface inbound profile for store order control by selecting document categorydefault as "A - Warehouse order if stock exists, otherwise third-party order"
    Just wanted to understand how this option works by requiring what kind of configuration and master data settings.
    Any further suggestions will be really helpful. 
    Regards,
    Debraj

  • SAP CRM Projects Implemented or Done in India Required Urgent and Important

    hi, friends and experts
          I wish u could send me SAP CRM Projects done in india with information including, Clients Name Operations, Duration and Location as soon as possible. Its urgent and important. Pls send the details.
                                                      thanking you
                                                             with regards
                                                       PRAVEEN

    There are several potemtial root causes.
    + NetWeaver Mobile/DOE is not setup
    + DOE -> CRM should be Trusted RFC
    + CRM application user ID should be in DOE

  • Role of a Security Consultant in an SAP implementation Project

    Hi All,
    What is the role of a Security Consultant in an SAP implementation Project and the stages in which he is involved?

    Hello Mohammed,
    The role of a Security consultant in any SAP product implementation (not just GRC) is wide enough and it's hard for anyone to sum up on a single forum post. Still I can give you some pointers.
    Security consultants come from different backgrounds, some from networking, database administration, infrastructure and even development like me. They contribute enormously to any product implementation from scratch (landscape design) to go-live (and continuous maintenance) so they are active on every phase of the implementation.
    Following are some of the activities they may perform (or participate)
    -System Landscape Design (work closely with BASIS and DBAs)
    -Check Infrastructure feasibility from security perspective (For Portals exposed to internet or extranet work closely with network providers for firewall security, VPS etc.)
    -Propose security guidelines, access policies, disaster recovery plan, business continuity roadmap (work closely with information security consultants and internal auditors or risk management teams)
    - Implement SAP solution specific Security measures (involves almost every SAP solution) for example: SAP R/3 security, GRC, BW/BI, HR, FI, Portal security etc.
    - participate in application integration for example: LDAP, IDM, SAP UME, shared directories etc (User master records security is on high priority).
    -   Check for any possible backdoor access vulnerabilities (ex: open RFCs, function modules like ping_rfc), and it involves almost all SAP solutions and there are special procedures to analyze such vulnerabilities.
    there are many such activities that a security consultant perform on day to day basis. Please do not interprete the above mentioned activities (entirely) as a criteria for any security consultant profile. There are many many possibilities for a security consultants to work from pen testing to SoD violation remediation. That's why I said it's not easy to sum up security.
    Always remember, Security and GRC are two sides of a coin they work together. however GRC is more of a combination of policy, regulation, events and involves management participation whereas security is a purely technical practice.
    You may also be interested to know what it takes to become a forensic security specialist.  Take a quick look at [http://amudee.com/?p=378|http://amudee.com/?p=378]
    Best Regards,
    Amol Bharti

  • In sap plm projects

    hi guru.
    in sap plm projects is this necessary , to generate the reports,scripts.
    what is exactly sap plm projects,give some idea briefly.because just recently
    i got offer for working in sap plm development projects.
    help me.
    thanks& regards
    subhasis

    Hi Subhasis,
    Are you a Technical/Functional i.e. ABAP/Functional please let me know?
    If you are a Technical (ABAP) then you no need to worry about your work in PLM
    your work remains same as of ABAP. i.e. you will be working on Function Modules, User Exits, Field Exits, Report Design, Scripts & enhancements etc.
    The Objects/Area which you will be dealing are : Document Managment System (DMS), Engineering Change Management (ECM), & CAD Integration yes i forget to mentioned you will be working on "Interfaces" too. and rest in PS or CProjects & CFolders based on the Scenarios/Requirements of your Project.
    If you are a Functional:
    Then working in PLM is still easy if you have a experience of working in SAP,
    First part of your PLM is PDM (Product Data Managment) which deals with
    DMS, ECM, CAD Integration, Material Master, BOM etc
    Basically you have to integrate all these objects or business objects precicely speaking to all the modules of the SAP R/3.
    Welcome to the board.
    If you have any specific questions, you can write at SDN, SDN team will help you at maximum, no need to worry.
    Best Regards
    Rehman
    <b>Mark Useful Answers</b>

  • Function Point Analysis for SAP BW Projects

    Hello All,
    Have been assigned a task to come up with Function Point
    analysis for SAP BW projects.
    Any help will be appreciated.
    Thanks,
    Mainak

    Hi Mainak,
      Function Point Analysis is independent of technology, methodology or platform, so there is no function point analysis specific for sap bw, rather you should familiarize with the fundamentals of FPA.
      And as you might know, FAP is used to determine whether a given a tool, an environment or a language is more productive when compared to others.
      I can send you good links if you can give me your email-id.
    Hope this helps...
    Thanks,
    Raj

  • QA job for sap bw project

    Hello Gurus,
            will you please tell how to do QA job for sap bw project?
    Many thanks,
    Frank Zhang

    hi chakri,
    i sent some docs to your mail i.d
    also refer to these links
    http://help.sap.com/bp_biv235/bi_en/html/BWspecific_Info.htm
    http://help.sap.com/bp_biv235/bi_en/documentation/Multi-dimensional_modeling_EN.doc
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/2b50ac90-0201-0010-d597-8d833833f9e0
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/828d9590-0201-0010-95a7-ea8cf8814b94
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/1b439590-0201-0010-ea8e-cba686f21f06
    Also for Bw case studies u can refer to these links
    http://help.sap.com/bp_biv135/index.htm
    http://service.sap.com/bi .
    regards
    ravi
    <b> Assigning pts is the way of saying thanks in sdn</b>

  • Cutover checklist for SAP BI project

    Hi All,
    Please share the cutover checklist for SAP BI project.
    Thanks
    Sandeep

    sandeep,
    please give us details of ...
    where you are on the upgrade
    landscape you are trying to upgrade
    nature of systems ....
    cutover depends on :
    1. criticality of systems and their availability
    2. Nature of upgrade - if you are upgrading your sandbox - then cutover is just a formality
    3. Ensuring that no data loss happens...
    Please be more specific - also search the forums on the same ..... this has been discussed a lot many times...
    since you have not given details - I expect that you will be adding more details to your post and am not locking your post....
    Arun

  • SAP XI project - proof of concept

    What will be tasks of an XI consultant for a SAP XI project - proof of concept stage.
    Thanks,
    -Naveen.

    Hi Naveen,
    As an SAP XI proof of concept...
    First you need to understand what what Business System your are integarting or migrating any existing Interfaces in that case...you need to analysis how the interface is developed in that particular Tool..you need to analys the code if and business functionality with the Buiness Analyst and with the endusers..
    This will be done usually for set of interfaces but not a single interface as an when the requirements,Business Process list,architecture,Communication plan,logic data model,usecase ...
    you need to do design documents  in which you need to explain you interace design and flow of it and design mapping documents for partiuclar inteface...
    accoding to the time factor the initial face takes some time but designing document and mapping spec takes around 2 to 4 days
    Amaresh

  • Searching for SAP certified project manager for project

    Please post a response if you know someone who has a BS or BA degree and has:
    General SAP Functional Knowledge and Experience
    8 - 10 years of previous experience as
    an SAP Project Manager with SAP, an SAP Partner, or large companies doing SAP
    implementation projects.
    A minimum of 5 full lifecycle
    implementations of SAP in a Project Manager role.
    Would prefer a candidate that is an SAP
    Certified Associate Project Manager, or have some other type of Project
    Management certification combined with significant SAP project and implementation
    experience on a number of different SAP implementation projects at different
    customers and in different industries. 
    Candidate should be certified in the
    use of SAP Solution Manager.
    Candidate should be certified in the
    use of ASAP Methodology.
    Candidate should be willing to provide
    two professional references.
    Required SAP Functional Knowledge and
    Experience Specifically for this Project:
    SAP Solution Manager
    Solution Manager Implementation
    (SMI210)
    Implementation Projects with SAP
    Solution Manager (SMI310)
    ASAP 8.0 Methodology for Implementation
    (ASA380)

    Hi,
    this might help you
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/40fde890-0201-0010-fa86-ee9a507bc62e
    Regards
    Agasthuri Doss

  • SAP Enterprise project connection and Primavera

    Hi, has anyone worked on interfacing SAP ECC and Primavera P6 using SAP EPC Add on. Need some guide on how to!!

    Hi,
    Instguide for epc 2.0 sp 04
    https://websmp106.sap-ag.de/~form/sapnet?_SHORTKEY=01200252310000094598&_SCENARIO=01100035870000000202&
    Rin Note:
    1993495 -
    RIN für SAP Enterprise Project Connection 2.0 mit Patch 04 für SP02
    PAM:
    https://websmp102.sap-ag.de/~sapidb/011000358700000103362012E
    br
    Julius

  • SAP enhancement project (ARVL0001)

    Hi All,
    I want to know on SAP enhancement project (ARVL0001), currently i am in sap 4.7 version. In SDN i have not got any good links to find on this. Can any one help me out in getting the steps or sample scenarios where we can use this ARVL0001 enhancement. Also please give me some links where i can get more info. In which cases this ARVL0001 can be used.
    Currently i am seeing the sap help.
    http://help.sap.com/saphelp_45b/helpdata/en/4f/71dee9448011d189f00000e81ddfac/frameset.htm
    Regards
    VEnk@

    Hey Gautham,
    Actually i need to research on how to implement the project ARVL0001, as i need to implement as per the USER revaluation. And also one more query is some say's like this ARVL0001 is obsolete and instead of this BADI is used to be used from SAP4.7 system is that true?
    Regards
    VENk@

  • Question about elearning - OKP SAP Commercial Project Management

    Hi Gurus,
    i have a question about an e learning course which SAP offers-
    Course Name- OCPM10-
    OCPM10 - OKP SAP Commercial Project Management 1.0 | SAP Training and Certification Shop
    It's an e learning course for 20 hours, below are my questions-
    Since its an e-learning course, is it to be completed in a specified time (within 2-3 days) or we can have access to it throughout the year but duration of course is 20 hrs
    What kind of documentation is provided to me as part of this course.  

    1. C_TPLM22_05 - SAP Certified Solution Consultant PLM - Project Management with SAP ERP 2005   
    It includes SAP PLM 235 course material along with PLM 200, 210 220, 230,
    2. C_TPLM22_60 - SAP Certified Application Associate - Project Management with SAP ERP 6.0
    It is not including the PLM 235 course.
    This is the basic difference between  it.  IN Certification there are  6 -7 areas , in each of them you have to score more than 70 % , there many few multiple answer questions as well. Finally over score will come it should be higher than 70 %.  So, I ideally weight all the topics equally,
    With Regards
    Nitin P.

  • INFORMATION ON TOOLS USED TO TEST SAP B1 PROJECTS

    CAN ANYONE SEND METHE MATERIAL OF TOOLS USED TO TEST SAP B1 PROJECTS.

    Look at the link for the different tools available for download. 
    https://www.sdn.sap.com/irj/sdn/businessone-tools
    There is not really any specific mandate to test B1 projects.  Tests are generally done at the Module level / Process level and then one complete end to end test is done.
    Suda

Maybe you are looking for

  • How to configure Mail to send from off-site

    I am trying to configure Mail on a laptop that will send and receive email both went it is connected to the servers ISP (on site) and when the laptop is connected to a non-site ISP. In other words when I am in the office I am connected to the ISP tha

  • V7 BB Desktop deleting outlook events

    Hi there, So I have seen many discussions on this topic, but none seem to resolve/ explain how to fix the issue.. The problem is that on synchronization with outlook, my outlook calendar all my history has been deleted, and wants to continue to do th

  • XQuery not returning any results when doc contains ENTITY refs

    Dear Forum members, I am a bdbxml newbie so please be gentle. I am trying to run xqueries against a TEI P5 document on bdxml 2.4.13 using Oxygen 9 (I'm also using Python and the API - it's not working either) My XML contains transcripts of poems writ

  • Transportation Route in Contract document

    Hi all, I created sales document type- G=contract. This document includes neither Sold-to nor Ship-to, its quantity contract that the sales manager create for specific market abroad. The market or country that the goods will be send to, specify by th

  • Logical vs relational

    hi, There are two notations in logical model (Barker and Backman). The Backman notation in logical model looks like relational model in look and feel. I want to know the difference between logical and relational in oracle data modeler. How can i corr