Sap construction project cost escalation

Hi Experts,
My current client asking to implement the  Project Cost Escalation . Please brief me how to proceed.
Thanks in Advance
Rakesh Ranjan

Please guide in the following scenario.
my client is getting project with escalation clause applicable. In this clause the variation in the rates of material or services gets the impact on cost of project . The variation in cost due to change in rate impacts the escalation. The escalation has some short of formullas mutually understood with client, which also includes RBI index and all.
Eg. Estemation has been done for 1000 Ltrs petrol at 50 Rs/ltr in the project. Project will be executed for 5 years. In first year 200 ltrs has been consumed with a rate of 53 Rs/Ltr. Then the extra amount 200 X 3 (this is not the formulla, it is being desided with customer and their client) = 600 will be claimed to client.For this system should record the  year wise consumed/work done qty and the variation of rate to generate the claim amount.
The extra amount generated should have to be claimed as escalation value.

Similar Messages

  • How to settle project costs to AUC

    Dear Experts,
    Please teach us how to settle project costs to AUC.
    Your response is very much appreciated.

    Refer below link
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/2a/f9f56e493111d182b70000e829fbfe/frameset.htm
    Venkat

  • What is project cost analysis

    hi sap gurus
    can anybody clear about the project cost analysis
    thank you
    venkatareddy

    Hi Venkat
    Please go through the following link which is useful
    http://en.wikipedia.org/wiki/Project_management#Cost
    best regards
    assign points if helpful

  • Managing SAP Portal Projects

    Dear All,
    Based on your experience in managing SAP Portals projects can you please share with me some high-level
    guess etimates (based on some clearly stated ssumptions) on the following data points -
    Typical Total Implementation cost (design,deploy,install & configure, develop)
    Typical Annual Application Support Costs.
    Kindly share me or suggest me on this.
    Rgds
    PRadeep
    Message was edited by: Pradeep Reddy

    For what its worth what I do is to split a long movie project into sub-projects each not longer than 5 - 10 minutes.  I export (=share in the new terminology) each one separately.  When (and only when) I am happy with all the (shared) pieces I join them together using Quicktime 7 Pro. 
    You cannot "render as you go along" in iMovie.  You could  join the subprojects in iMovie and re-share the combined project but this takes much longer than the few minutes it takes to stitch together in Quicktime 7.  
    There are a number of advantages to this approach:
    1:  Sharing takes a long time.  As soon as I share a projects and view them (in high definition) I find things that need correcting/improving  - but at least one only has to re-share the affected sub-project(s) at not the whole lot.
    2: iMovie 9 seemed to get more sluggish if there was a lot in the timeline - I don't know yet whether this is also the case with iMovie 10
    3: If something goes seriously wrong you have only lost part of your work.
    4: I find it easier to keep track of what I am doing on a timeline which is not too long.
    You are going to need a lot of GB storage on iCloud!
    Best of luck with the project!

  • Engineering & Construction Project

    Hi,
    I need to give a presentation to my mangement for SAP Implementation for Engineering and Construction Firm.
    kindly provide me with a template for the same if it is available with anyone plz forwrd me to mail address [email protected]
    Thanks in advance,
    Atul R. Rajmane

    Refer media library in the below link
    https://websmp104.sap-ag.de/eco
    You'll find presenttation on below topics:
    Claim and Change Order Management
    PLM for Contractors / Construction
    Project Development with c-Project
    Shipbuiding Positioning (pdf)
    Shipbuilding Positioning
    Solution Positioning - Construction
    Solution Positioning - Contractors
    Solution Positioning: SAP for EC&O - Homebuilding
    Strategic Project Management with SAP SEM
    Utilizing SAP for EC&O for Engineering and Detail Design
    mySAP PLM Project Management for EC&O - Business View
    Regards
    Sreenivas
    Pls close the post if satisfied.

  • Project cost monitoring..?

    Dear Friends,
    My client is having Power ericssons through out the India, and they want to see the report Project wise profit and cost
    so please suggest me which way is sufficient for us...and which module very helpful to reach the project cost monitoring...
    Thanks & Regards
    Sunil kumar.K

    Hi Sunil
    kindly read the below link that will help to understand the concept of project system
    SAP Library - Project System (PS)
    Thanks
    Trinath

  • Project cost controlling

    Hi guru
    What is project cost controlling & what are its step by step customisation settings.
    Thanks
    shivaji

    Hi,
    You can refer to this link:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/bf/5ffd166d4311d1ad5e0000e8a6353a/frameset.htm
    Regards,
    Eli

  • Without IM how can i settle construction project to AUC and asset

    Dear all
    without IM, how can i settle construction project to AUC and asset.
    can someone explain it in details?
    thanks a lot.
    Judy

    thanks for all of your answers.
    i create the investment profile and assgin it to the project profile.
    when i release the project, i see the system status changed from crtd to release and AUC.
    when i do cj88, the costs are settled to the AUC No. automatically.
    could you tell me how the AUC No. is created? where does it configure?
    when AUC is settled to FXA, what are the procedures?
    first TECO the project and then do CJ88, am I correct?
    thanks a lot
    Judy

  • Construction  Project

    Dear All.
    In Construction Process our client is building 4 floor in that the main
    Project is L1 WBS and in the
    2nd level WBS will be  Basement , Floor1  Floor 2 Floor 3 and in
    Each Flat will will be separate WBS 
    My question is How to map Activity carried out in Floor level  EG in Basement, Floor 1 2,3.
    Re grads
    raj

    Hi Raj,
    Ref. below blog to create construction project in ps.
    SAP Project System - A ready Reference ( Part 1 )
    Hope this will be useful to you.
    Regards,
    Sandeep

  • Regarding SAP Enterprise Project Connection

    Hi Experts,
    I understand there is a connector available in the name of SAP Enterprise Project Connection to interface SAP PS/PM with Primavera. We are planning to use this. Have anyone came across this product ? How is the performance of this product and how much it costs ?
    Thanks in advance.
    Regards.
    Bala

    Hi,
    We are getting below error when we are providing "Oracle Primavera 6 Client API JAR File" location..
    Validation error:Invalid jar file pathThe user name or password is incorrect
    Regards,
    Sudarshan

  • Webservices for 11i Project Costing

    Hi,
    Does anyone know if there are webservices interfaces for the Oracle Application (Project costing module in specific)?
    We would like to integrate this into the weblogic J2EE server.
    Thanks.

    Hi,
    1. Costing for the Quotation: For you I recommend to go for the Easy cost planning option.
    Please go through the following link:
    http://help.sap.com/saphelp_47x200/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm
    2. For the workforce planning: you can carry out in SAP via capacity planning and if you wish to do it outside SAP then only the cost can be captured for the labour cost via activities in Project System.
    Please see the link below:
    http://help.sap.com/saphelp_47x200/helpdata/en/ed/b7853488601e33e10000009b38f83b/frameset.htm
    For the configuration purpose:
    http://help.sap.com/saphelp_46c/helpdata/en/3d/72369adc56d11195100060b03c6b76/frameset.htm
    Reward points if found useful.
    Revert back for any other questions.
    Thanks!

  • Opening Balances for Project Costing in R12

    Hi All,
    What are the Open transactions should be migrated as Opening Balance in Project Costing (R12) for Projects and Tasks. Here at client place cost will come from Inv, PO, AP and OTL to Project costing (R12). Can you please explain in detail (Opening Balances & Historical Cost - How to Migrate)?
    Waiting for replies...

    Hi
    Usually on implementation of Projects, people are migrating total historical costs per project.
    Depend on your current system, you may convert the historical data summarized by project, task, expenditure organization and expenditure type. There is an option to summarize costs into the latest period, just before starting the future transactions import into Projects. Otherwise, consider summarizing cost data per period, per quarter or per year.
    The summarized data may be loaded as miscellaneous expenditures into Projects.
    Be aware that for converted expenditures you should setup a Transaction Source which is costed and accounted.
    Dina

  • Settlement of Project Cost and revenue to GL

    I am trying to Settle the project Cost and Revenue to GL account. For the same I have defined settlement profile maintaining GL as optional receiver and then I have maintained Source structure for cost and revenue as to separate them at the time of defining settlement rule, defined Allocation structure where in receiver against source, I have assigned GL as by cost element receiver. After that I have maintained settlement rule for WBS element, but when I am running a settlement is done to either of the GL for cost or Revenue which ever is defined first in settlement rule. It is not creating any settlement for second line item of the settlement rule and system is not giving any error message as well.
    Where as if I am trying individually only for cost or revenue , settlement is completed with all the values but with any accounting document generated, but if I see the entries to that GL, a settlement entry is created for that transaction.
    Can anyone please help in solving this issue ASAP.
    Thanks and Regards

    Hi,
        If it is posting to the first line means....
    Follow the steps below:
    First try to create a project and post the actuals and revenues.
    Go to cost element report pick up those cost elements both for costs and revenues.
    Go to Soruce Structure in the config, define the structure with name for Ex: 'Z1' and define two assignments, one is Costs and other Revenue, by selecting the costs go to Source mention the cost element where the actual costs are posted on (Mention only that cost element no other cost elements), next select the Revenue assignment and click on Source and mention the only cost element where the revenue wsa posted (Mention only that revenue cost element no other cost elements) and save the transaction.
    Come back to project builder, select the wbs and click on settlement rule, in the menu goto-->settlement parameters and check whether the source and settlement profiles are correct or not, incase source structure is not available mention the same.
    come back to settlement Rule overview and fill the fields as mentioned below:
    1st line:   Category: GL
                  GL Account: GL Account Number
                  Source Structure: COSTS
    2nd Line: Category: GL
                  GL Account: GL Account Number (Revenue Account)
                  Source Structure: REVENUE.
    Now Run the Settlement for the specific period costs posted, the costs will be posted seperately to the two different GL Accounts.
    I think this will resolve your problem.
    Rgds
    Sudhir Reddy

  • Project cost plan Header Data table ( PS module - T.code CJR2)

    Hi,
    I am working on PS module where we have to build a integration between PS Cost plan (At WBS Element level) to SD Quotation. I have to use transaction CJR2 for this. we will add the custom field 'Indicator' on the initial screen of transaction CJR2 for this. I want to know what is the HEADER DATA table for Project Cost Plan, so i can add this custom field in that table and letter on use in CJR2.
    If someone have done any kind of modification for work on CJR2 transaction, please provide me some information on this since i am first time working on PS module. I need some information on modifying the initial screen on transaction CJR2.
    Any inputs will be appreciated.
    Thanks,

    Hi,
    you'll find Project cost plan  in tables RPSCO / COSP
    regards Andreas

  • A Standard RRB report that shows actual project cost line items .... ?

    A Standard RRB report that shows actual project cost line items but that also shows amount/qty by rejected, billed, to be billed, postponed?
    I'm looking for something that will allow project managers to reconciile with the RRB totals and be able to dril in a see a level detail not available in RRB to decide what should be billed, what should should be deferred (postponed) and what should be rejected out of hand.
    Thanks.

    Thanks Virendra Pal but the VAx5 reports are not really the answer - maybe a custom report will be required right enough.

Maybe you are looking for

  • How to Hide a column in a report @run time

    Hello Can you help me please I need to hide some columns in a report when you run it , I dont want it to be displayed. Here is the scenerio. I have a column called (QTY) and the other (Price). Now I have a new one where I take (Qty*Price) and the res

  • How to move iPad from old XP to new Windows 8?

    I get how to move the music. I get how to transfer the store purchases. My fear is that I will somehow lose my Contacts and Calendar information, and my game progress. Luckily, my old XP is still working. I have an external drive. I've downloaded and

  • RAC issues and mostly asked Interview questions

    Hi Gurus, It would be great if someone shares some RAC issues and mostly asked questions. Thanks in advance.

  • GR For Subcontracting PO using BAPI

    Dear Experts, I m using BAPI_GOODSMVT_CREATE this BAPI to create GR for Subcontracting PO , Here i want to give my own values in BOM component with 543 mov.type but its not working. And GR for normal PO is working fine.But for Subcontracting its not

  • Since upgrade my ringtones don't work

    ringtones don't work on my iPhone since upgrade.  It shows them on my contacts, but I get normal ring when I get a call.