SAP MIGO Partial Goods Receipt of a PO then after close PO

Kindly help.
If partial GRN made and we want close PO line item so that futher GRN not possible against that PO line item.
we tried as per our knowledge like delivery complete tick mark but its not help us. and we do not want to delete or block that line item of PO.
thanks in advance.
Edited by: Priyam Choksi on Jan 27, 2009 2:16 PM

Amend the Purchase order quantity to received qty and Set Delivery completed indicator.
Setting Delivery completed indicator will not stop further processings. This is a Standard SAP behaviour.
What can be done
You can block the Po line items for further processings.
you can put Latest gr date as qty received gr date (past) in Purchase order item detail delivery tab. This will stop further goods receipts.

Similar Messages

  • Partial Goods Receipt for Inbound Delivery

    Hello Frends,
    We have a requirement to generate partial goods receipt against Inbound delivery created in Intercompany scenarios, however when we analzed there two alternative ways possible -
    1.  Goods Receipt in Inbound Delivery - Transaction VL32N : In this transaction,ssytem allows goods receipt for complete quantity but not for partial quantity
    2.  Goods Receipt reference to Inbound Delivery - Transaction MIGO : In thsi transaction, there is a provision to generate partial goods receipt however system not updating the status in inbound delivery document.
    In this regard, requesting your support on what is possibility to fulfill our requirement, is there any standard SAP approach for this.
    Appreciate your support.  Thanks
    Best Regards,
    Goutham

    Hi,
    Thanks for your quick reply..
    I have a outbound delivery with 100 EA, now system automaticallly generates a Inbound delivery for 100EA using output message.  Now we need to generate partial goods receipt for the inbound delivery, mean first 20, then 40 and the remaing.
    What are the best practices available since when I check from the Inbound delivery,we cannot make partial goods receipt.
    Best Regards,
    Goutham

  • Partial goods receipt for PO with multiple line items

    Hello All,
    While doing MIGO, for a PO with multiple line items, if one line item is having error, will we be able to go ahead with goods receipt? Or entire material document is blocked for doing MIGO?
    We will be doing a development - in case if there is problem in goods receipt (checking of any parameter, and if it is missing - we will be posting error message)...is it possible to ahead with next line item and still post the material document?
    If partial goods receipt if possible for PO with multiple line items, how do we do it?
    Regards,
    RJS

    Hi
    While doing MIGO, for a PO with multiple line items, if one line item is having error, will we be able to go ahead with goods receipt? Or entire material document is blocked for doing MIGO?
    No. You cannot post the MIGO, if even one of the PO line item is having problem or giving error.
    We will be doing a development - in case if there is problem in goods receipt (checking of any parameter, and if it is missing - we will be posting error message)...is it possible to ahead with next line item and still post the material document?
    If you skip a line irem and do GR with next line item, how will you match quantity & value with the vendor Invoice at LIV ?
    If partial goods receipt if possible for PO with multiple line items, how do we do it?
    Partial goods receipt is possible for PO line items. That means, if PO has 100 qty for line item 1 then you can do GR for 50 now and 50 later depending on the vendors delivery.
    Hope this is what you mean by "Partial Goods Receipt".
    Edited by: Arun R on May 10, 2010 2:03 PM

  • Partial Goods Receipt

    Hi,
    Is it possible in SAP Business One to create a partial Goods Receipt of a service from a purchase order?
    Thank you.
    Nadia.

    Hi Nadia.....
    In case of Service Document there is no meaning of Quantity if I'm not wrong.
    So
    you can make a partial GRN with respect to Document Value based on Purchese Order.
    But if you have Item GRPO with Service Item then it may be possible to tak Partial GRN based on PO Qty wise.
    As SAP asks you to put the Qty mandatorily.....
    Regards,
    Rahul

  • EKET-FIXKZ set after partial goods receipt of subcontract delivery schedule

    Dear all,
    when booking a partial goods receipt (via MIGO) of the finished product of a subcontract delivery schedule the schedule line becomes fixed (EKET-FIXKZ = 'X'), which hinders the next MRP run to modify the delivery schedule according to the new requirements.
    I have tested to change the fixing indicator via SE16 and the next MRP run will then replan the sub contract delivery schedule correctly. But this is no solution.
    Is there a way to modify this setting via an EXIT or BADI in MIGO ?
    Many thanky for your help
    Rabanus Diehl

    Dear all,
    when booking a partial goods receipt (via MIGO) of the finished product of a subcontract delivery schedule the schedule line becomes fixed (EKET-FIXKZ = 'X'), which hinders the next MRP run to modify the delivery schedule according to the new requirements.
    I have tested to change the fixing indicator via SE16 and the next MRP run will then replan the sub contract delivery schedule correctly. But this is no solution.
    Is there a way to modify this setting via an EXIT or BADI in MIGO ?
    Many thanky for your help
    Rabanus Diehl

  • VL32N Change inbound delivery quantity after a partial goods receipt

    Dear.
    I have created an inbound delivery using VL31N from a purchase scheduling agreement.
    I have executed a partial goods receipts using MIGO for the inbound delivery.
    I need to reduce the delivery quantity for the inbound delivery using VL32N but the system donu2019t allow to change the delivery after a goods receipt.
    How can I proceed ?
    Thanks for your help.

    Hi,
    When a (partial) goods receipt has been posted to an inbound delivery item, the possibilities to change this item are restricted.
    If the delivery quantity is the same as the goods receipt quantity, then the item is fully posted goods receipt. No change of quantity is possible.
    If the delivery quantity is still higher than the goods receipt quantity, you can create one or several new TO's for the rest and
    confirm, if needed, with differences.
    You have also the chance to adjust the delivery quantity to the picked (and already posted) quantity with VL32N and menu:
    Edit => Copy Putaway Quantities as Delivery Quantities
    Please also have a look at note 796053.
    Hope this can help
    Regards
    Mauro

  • Partial goods receipt & invoice settlement

    Hi All,
    I  want to know the process of partial goods receipt. I want to know how the PO is created for this purpose and GR is done for partail goods receipt. Also how the invoice is settled for only quantity received??

    hi buddy
    no need to make any special po
    make the normal po
    then do gr with the partial quantity  , at time of migo ie  gr u will find quantities change that with ur partial quantity
    then do the miro ie invoice verification ,system will take automatically the gr quantity ie partial and show price accordingly
    this way u can do the partial gr and settlement
    but now if u dont want to do the gr of remaining quantity then just in me22n ie change po in delevery tab in item level give indecator of delevery completed and also lock the item from item overview
    this might helpful
    reward if useful

  • Split/change line in Purchase Order after partial goods receipt

    Hi
    I have a PO with multiple lines/items. For one line there has been a partial goods receipt and for the open qty there will be a delay. Do I have any chance to either:
    - Change the delivery date for this row to match the ETD of the open qty
    - Change the initial qty of the line to the one received (that the line closes) and open a new line with the correct date for the open qty
    I just cant change anything in a line for which a partial goods receipt has been posted.
    Thanks
    Franz

    Hi Gordon,
    Thanks for the info. Another idea: How about ..
    - adding the item on a new line with the open qty and the correct date
    - simply closing the partially posted line with the open qty (is that ok from the DB view?)
    Any doubt that this could work as intended?
    Thanks
    Franz

  • Need rounding off value for partial Goods receipt

    Hi,
    My requirement is that the PO value,PO tax value ,GR value and Invoice value(IR) should get rounded off.
    When I am using the PO value which is rounded off in PO, but at the time of posting partial goods receipt the value for the GR/IR clearing or the stock value is not getting rounded off for these G/ls.
    What should I do for this to get the rounded off values in GR.
    Regards,
    Goraksh

    Hi Goraksh,
    The problem is that the pricing (incl. the rule 17) is not normally called at the time of GR. As Jürgen wrote, the system just uses the "net value" field of the PO.
    I have however a "wild" idea. If the price in the PO comes from the info record or from a contract (and not changed manually there), then you can set the "pricing date category" = 5 there, meaning "GR date". This causes the pricing to be called again at the time of GR and your formula 17 will fire.
    The side effect of course is that the price that you had in the PO, printed and sent to the vendor will not be binding: if you change the PIR price before the GR, the GR will be posted to the new PIR price, despite the fact that the PO printout showed something else. So the question is if the price printed on the PO is indeed binding in your business case - in many business cases it is the current vendor price that matters for the billing by the vendor, not the one that you prined on the PO. For such business cases you should have had pricing date category 5 anyway...
    BR
    Raf

  • Delivery complete indicator set by partial goods receipt in kanban orders

    HI Experts,
    we recently upgraded to ECC 6 DIMP EP 6. Now for kanban production orders delivery complete indicator is set for partial goods receipt. Under delivery tolerance is zero. Is there any notes available for this issue. Manual production order goods receipt is fine.
    THanks
    RIjil

    Hi,
    Let me try and understand your scenario better. You have a production order triggered by KANBAN. You then do a GR via inventory management of a partial quantity. Would you then GR the remaining quantity?
    The reason I ask is because this is KANBAN production, the bin being filled multiple times for the same trigger does not sound right. The system behavior of not expecting further deliveries (by setting delivery complete) seems appropriate.

  • MIGO. Goods receipt. Default posting date ??

    Hi All!
    My user wants to put restrictions on <b>posting date for goods receipt</b>. It should depend on fiscal year (FY) of document delivery date. There are 2 rules for this. One should works only if the current month is September.
    If FY of delivery date  < current FY then posting date = 8/31/prior FY.
    Else. Posting date = current date.
    The second rule should work only if current month is August.
    If FY of delivery date >  current FY then Error message “Cannot post…”
    During the rest of the year they want to have standard MIGO.
    Is it possible to realize it in SAP without modifications? If yes, what is the best way to do it?
    Thanks a lot.
    Lena

    Hi,
      You can use this exit,
    MBCF0005
    Function module is,
    EXIT_SAPM07DR_001
    In the Changing part the structure ( AM07M ) is accessed as C_AM07M which has the posting date.
    <b>Reward points</b>
    Regards

  • SAP R/3 goods receipt and issue process through RF

    Dear All,
    We need the below information.
    In order to setup RF enabled goods receipt and goods issue what basic infracture we need to have.
    we are not intersted in using WM module, with out WM we can go for this ??
    Is this the right forum to post this question...
    Abdul Raheem

    Hi.
    I've just carried out this architecture. You have to check 2 things:
    1- Are your DB software levels the same? (AIX + Windows)
    2- Have you checked connectivity from client to DB server?
    Regards,
    Fatih Erten

  • Invoice block for partial goods receipt

    Hii..
    I have a requirement where i need to block the invoice its respective PO is partially receipted.
    does SAP provide any customizing settings wher if i tyr to do MIRO for PO which is partially receipted the invoice should be blocked.
    Suggestion will be worth appretiated,
    Sarfraz.....

    Hi,
    You can set the tolerance limit for   BW: Percentage OPUn variance (GR before IR) to block the invoice in transaction OMR6.
    Regards,
    Chetan.

  • Printing Goods Receipt labels from a PO after the inspection is done

    Hi Guys,
    Just wondering if you can help me...
    I am having problems to print to 2 differents printer a WEE1 output type labels from MB90, like::
    -If is ACCEPTED, it will print to PRINTER A;
    -IF is REJECTED, it will print to PRINTER B.
    What is the best way to do it?
    Thanks heaps.

    Hi
    you can use user exit QSS10001 Possibility of calling a different print report.
    You can hardcode output device & call SAPLPDE printer as per UD
    Regards
    Sujit

  • Why does it take so long for microsoft to incorporate good ideas into programs, but then after they do no one elses software will work on the system?

    Case in point: I can not use Xp any longer since it is not supported by microsoft, and latest lan driver requires xp service packs which are no longer available for XP or Vista. So my old software as of April 2014 is now worthless as internet access software(microsoft
    will not provide support or service packs for xp). So I get a new pc with WIN7 op system installed and try to do traditional backups to protect myself should my system crash in the future. (usually this means cloning a hard drive or installing Faronics Deep
    Freeze to protect my op system in case of catastrophic failure.) I try to install and use some of these utility software types including Acronis Disk Director 12, Avanquest Perfect Image, Partition Commander 10, and others True Image Hdd utility for cloning
    hdds. Most of these I try to run turn out to be useless, and I get pop-up messages saying my software is incompatible with win 7 op sys! I am wondering if it is the software or the fact the op system is 64bit (not 32 bit) which means that if you buy any other
    software to help with utilities it will be worthless because most are written for 32 bit systems not 64. No one tells you these warning signs when you buy the pc with the 64 bit software already installed. But for a Toshiba 15" computer that normally
    costs 400$ and I can get it at Goodwill used computer store(1stStreet and Fairview in Santa Ana, Ca.) for 175$ I can not complain. Being an unemployed electronic technician, I have to stretch my dollars as far as they will go...Another frustrating thing is
    I buy this device made by Apricorn Driveware that allows users to hookup a second hdd using a usb cable and a three connector module that will allow the user to connect any hard drive sata or ide or the 3rd type. I try to run it and make a backup copy of internal
    hdd but I get error messages saying it can not copy hdds when there are minor differences such as total mbs on each drive or slightly different hardware issues such as my pc has 580 gb internal drive and replacement backup drive is 380gb. Such as shame because
    hardware setup is a good idea but without compatible software it is useless! Perhaps if I was using it on my old xp op systems I would have fewer problems with software compatibility issues. I really hate the fact that MS does not provide support for known
    good op systems like xp say 20yrs? When the products and markets change so fast they run the risk of alienating customers who can not financially keep up with technology changes especially during an economic depression such as the one we are in now( they predict
    it will last 20 yrs). a curious thing about the Acronis disk director 12 software I installed. It seemed I could not get partion size on hdd to change no matter what I did. I found out that if I CHANGED THE DATA BLOCK SIZE ON THE NTFS PARTITION FROM 4 KB TO
    2 KB THAT I WAS NO LONGER LIMITED BY THE SOFTWARE FROM SHRINKING THE HDD PARTITION FROM 300GB DOWN TO 100GB. Once this item was changed on the hard drives the Disk Director 12 software (Acronis) was able to shrink the partition size to what I wanted.

    Due to phenomenal development in Windows, Microsoft released 4 generations of operating systems, succeeding Windows XP. Hence, on various aspects, Windows XP becomes too old to be used practically these days. So the support was pulled out.
    I do agree that Windows XP is the most successful operating system ever, so far. But, later versions added more features, enhanced security and compatibility. Moreover, at this point, Windows XP becomes more vulnerable, although security patches are made.
    Ultimately, we need to move to a more secure, feature-rich and highly compatible operating system.
    With improved features in newer versions of Windows, the NTFS filesystem has also been improved, adding new features. Hence, certain feaures that are not availble in Windows XP are available in Windows 7, again, in Windows 8.1. So is the disk management
    features.
    As for Acronis Disk Director, it's a third party software and hence we can't comment on the features/its working.
    Balaji Kundalam

Maybe you are looking for