SAP Solution for Mini steel plant with DRI Process

Dear all,
I am a metallurgist who spent couple of years in steel and process Industry and then moved to IT Consulting as SAP consultant / business analyst mainly working in the area of solution designing.
Here i will like to describe SAP solution for Mini steel plant with DRI proces.
u201CManufacture Productsu201D Description
The series of operations performed upon material to convert it from the raw material or a semifinished state to a state of further completion. This includes the establishment and maintenance of a CAPEX plan, the planning, scheduling and execution of production activities, the dispositioning of produced goods, the maintenance of production data, the monitoring of production performance and the implementation of engineering changes.
u201CManufacture Productsu201D Objectives
M-010
Compile 3-year CAPEX Budget     Establish the overall manufacturing goals and metrics that the organization will use to measure performance and progress towards objectives. These goals should be consistent with overall organizational strategy/value propositions. Develop long-term goals for production capabilities and manufacturing. These goals should align with the overall goals and objectives of the organization.
M-050
Perform Long Range Production Planning     u201CBudgetingu201D. Long range planning of production quantities based on planned available capacities and known or estimated customer demands. This process may include planning for different capacity and/or demand scenarios. Approved capital expenditures from the 3-year CAPEX budget may influence the budget. Range and frequency for budgeting is yearly.
M-060
Perform Medium Range Production Planning     Medium range planning of production quantities based on planned available capacities and known or estimated customer demands. This process may include planning for different capacity and/or demand scenarios.  Range and frequency for planning is quarterly.
M-070
Perform Short Range Production Planning     Short term planning of production quantities based on capacities and demands as previously planned in the longer terms, actual customer demand and actual capacities. The result from short range production planning will run into the operational plan for the current and following days.  Range and frequency for planning is monthly.
M-080
Schedule Production     This sub-process enables detailed scheduling by resources over the planning horizon. Planned orders that fulfill demands (Stock Transfer Requisitions, Sales Forecasts and Customer Orders defined by due-dates and due-quantities) come from the short range plan. This results in a feasible schedule, optimizing utilization of the production resources. It is based on production process constraints as well as labor resources in order to minimize production costs and also taking into account constraining raw materials availability.
M-090
Execute MRP     The purpose of this sub-process is to generate a Materials Requirements Plan (MRP) for all materials, which are produced or purchased. The MRP process involves looking at current material inventory, planned inbound material deliveries, requirements, lead times and stock levels to generate a detailed plan for future material requirements. The materials requirements will be generated with respect to the three planning horizons, short-term, medium-term, and long term. If an over stock of raw materials occurs as a result of a planning change production and marketing personnel will be informed. This would allow for the cancellations of any unneeded shipments.
M-100
Perform Setup / Changeover     Perform set-up and changeover activities on production equipment as necessary, to prepare for the production of specific materials/grades. Set-up and changeover activities will enable the production equipment to perform operations on materials, as per the specifications called out on the production order. Ensure time is allocated for first off inspection requirements after changeover.
M-110
Execute Production     Insure that the production plan is met by converting raw materials and component supplies into finished and semi-finished products. Batch/lot documentation will be created for individual production orders to provide traceability throughout the process. Each step of the production process is continuously monitored to identify mechanical, quality, and productivity issues and suggest solutions when problems arise. Data collection for performance and financial reporting enables management to take immediate action on manufacturing processes as well as conduct historical analysis.
M-120
Perform Quality Management     Quality management refers to the entire supply chain process. Process activities are related to the evaluation and inspection of key characteristics of semi-finished and finished materials. These evaluations are recorded and acted on based on the results. Report/manage internal quality problems or issues. Install and manage quality control systems to insure product quality. For supplier or subcontractor based issues this data should be used as a performance measure during the vendor evaluation process.
M-130
Manage Product Disposition     This process ensures those semi-finished and finished products that do not meet quality requirements, are prevented from being used and distributed in good finished product to customer, or released for the next step of the production process. A semi finished product is any material that needs to have another operation on line before being shipped to the customer. Finished goods are defined as any material that can be shipped to a customer; in house produced finished goods, subcontracted materials and trading goods. The information required to make decisions regarding disposition comes from the Quality Management system of each production facility. The first step ensures that raw material and returnable goods are dealt with in another subprocess. The reason for the goods not meeting quality standards is recorded along with the results of any investigation to find the cause of the fault. Information is sent to all other parties who need to know: order fulfillment, inventory management and shipping. The process ensures that the most appropriate action is taken to either dispose of, or rework the goods. Disposal or rework may be either through the original materials supplier or subcontractor, or Mittal Steel Point Lisas.
M-140
Maintain Product Related Data     u201CMaterial Master Maintenanceu201D. The Sub-Process 'Maintain Product Related Data' is the list of activities that identify the steps and decision points related to the request for and performance of additions, changes, and deletions to the Material Master file or files. This sub-process begins when a need to create, change or delete a material is identified and ends when the request is either actioned or refused. The sub-process is intended to cover all material types, including finished goods, raw materials, bills of materials, equipment and service, POS, Sundry Items etc. In fact, any product which the company wishes to inventory or purchase. A number of key strategic decisions, including a clear definition of when we issue a new material, will affect this sub-process.
M-150
Maintain Production Related Data     u201CMaster Data Maintenanceu201D. This subprocess identifies the activities related to requesting changes or additions to production related master data. Once a need for master data maintenance is identified, a request is submitted for approval. Data defining production capacities and performance standards (e.g. line efficiencies, material yields, etc.) require Corporate level approval prior to maintenance. Other data that is more specific to internal planning functions are maintained at the plant level. Maintenance requests are returned to the originator whether the request is approved or not to improve communication throughout the system. This subprocess may be triggered by: annual operations budgeting process process/production equipment upgrade or replacement change in facility work schedule (i.e. planned hours or days) change in personnel required to operate process/production equipment new products, formulations, or packaging.
M-160
Operations Execution Reporting     Gather manufacturing information at various points in the production process. Prepare management reports both at the detailed level for plant management and summary level for senior operations management. Reports will be available on-demand and will include - volume, efficiencies (mechanical, line, and labor), yields, downtime, asset utilization, environmental, safety, quality, and financial data. A major goal of this sub-process is to define a consistent method of calculating operations metrics. Some plants will use line information systems and PCSs to collect information. Not all plants are equipped with these systems and the where they do exist, the level of sophistication varies.
M-170
Manage Process Reliability     Optimize capacity by reducing process downtime and ensuring compliance to quality expectations by the reduction of rejects. Install tracking systems to measure line time utilization, quality results, process settings. Conduct root cause analysis, and use the data to develop and implement improved operating procedures.

Thank you for your prompt response. I'm assuming you are still proposing to use Sales order -> purchase order -> invoice verification -> Customer billing process flow. Is that correct?

Similar Messages

  • An SAP Solution for capital planning and Budgeting of Capital Assets?

    Is there an SAP Solution for the Planning and Budgeting of Capital Assets?
    A solution that provides planning, budgeting, and tracking for capital assets through the entire life cycle of each asset, from the initial request through the final disposal.
    The solution needs to be able to run “scenarios.” A scenario contains equipment that may potentially be purchased. Scenario items are used to help determine cost, capacity, and cash flow feasibility.

    Hi
    What you suggested is the ideal approach...
    However, if they say that the budget allocated to capital purposes (70%) applies to both capital projects and expenses and they would like to control it together, but have reports separately, it is not possible with standard SAP...
    If they want to have just one IO for both cap and exp, You can suggest them a work around to capture CAPITAL or EXPENSE in a ref field (XREF1 in BSEG) and you can run KOB1 with XREF1 displayed in it....
    In standard KOB1, XREF1 is not displayed, you have to use Exit COOMEP01 to include the fields you want... Add XREF1 to the Structure CI_RKPOS and write your code in the include ZXKAEPU01 of EXIT_SAPLKAEP_001
    Without an identifier @ the time of booking the transaction in the system (Either by way of IO or a ref field), you wont be able to generate reports later on
    Regards
    Ajay M

  • Regarding SAP solutions for mobile business

    Hi,
    Please let me know of any document summarizing all the SAP solutions for mobile business.
    Regards
    Raja Sekhar

    Hi Rahul,
    Thanks for the reply.
    I cudnt find the drop box 'Related Technology topis...'.
    I got the doc thru some other means.
    Thanks anyway
    Raja Sekhar

  • Tyre Manufacturing SAP Solution for production Planning PP-PI OR PP-Rep???

    Tyre manufacturing in SAP solution does it require to use PP-PI and/or PP-Repititive or PP-Descrete.Pl share if any one implemented SAP for tyre manufacturing with Process flow and which are the PP Components needs to be used.
    Thanks
    Ram

    Dear Girish,
    Thanks for the info and I think you are right,but some times if customer wants the answer from Consultant,what is best suggested or recomended ?? ,then it requires some expert judgement or based on previous experience,if you have any case study to share with me would be greatly appreciated.means which company uses what process ,are they benifitted from the solution if not what are the pain points and how are they managing it etc...
    Thanks
    Ram

  • SAP Solution for customer crosscheck

    Hi.
    For security reasons one of our customers wants to crosscheck customers with an external database located in Switzerland.  Does someone have an idea whether or not SAP has a standard solution for this?
    Basically it entails reading the customer details from sales order/inquiry, blocking the order/inquiry while sending the details to an external database, receiving the reply and whether good or bad then releasing/discarding aforementioned order/inquiry.
    Sincerely
    Ryan

    NA

  • Full mesh VPN solution for on MPLS network with PE and CPEs

    Hi,
    We are trying to evaluate some best solution for Hub-Spoke mesh vpn solution in a MPLS network. The VPN hub router will be in PE router and all the VPN spoke will be in CPE.
    Can someone please let us know what will be the best vpn solution, we understands that there will be some technical limitations going with GETVPN but still we did counld find any documenation for possiblity of using DMVPN.
    How about the recent flexvpn, can fex-vpn work on this requirement, where can i get a design/configuration document.?
    thanks in advance.

    Hello,
    GetVPN is intended for (ANY-to-ANY) type of VPN communication, over an MPLS network with Hub and Spoke Topology, your best Option is to look for Cisco (DMVPN) implementation where this type of VPN is primarily designed for Hub & Spoke.
    Regards,
    Mohamed

  • SAP solution for patent management

    Is there a SAP solution which helps manage patents including patent filing, alerts on due dates, costs etc?

    Dear Anand,
    www.sap.com/solutions/solutionextensions/businessprofit/index.epx
    www.sap.com/industries/lifesciences/midsize/solutions/index.epx
    Do let me know in case of any queries.
    Hope this helps you.
    Regards,
    Rakesh

  • Need solution for using Symbol LRT3840 with Apps 10.7 and/or 11i?

    Any suggestions for using Symbol's scanner/terminal with Oracle 10.7 and/or 11i? The symbol unit runs a telnet session (with a 1/4 viewable area). I'm looking for some alternate screen templates and/or a software solution that will allow me to remap the existing full screen forms so all critical information is displayed on the symbol unit in the allowable viewing area. I understand that version 11i of Oracle Apps does not support character-based telnet sessions, so I'm also interested in a fix that will be transparent to my material handlers when we upgrade from 10.7 to 11i. Any help would be greatly appreciated.

    Hi
    We are developing solutions in that area.
    If we can know more of the exisitng solution you have implemented or PDA and how it is integrated with Oracle Application(whether it is a third party tool?)
    then we can discuss about arriving at a solution.
    My mail-id is [email protected]
    Thanks and Regards,
    Bibs

  • SAp Solution for revised IAS 23 - Borrowing Costs

    Does SAP has any solution to adopt/adhere to the revised IAS 23 which requries to capitalize the borrowing costs.This is effective from 01.01.2009.
    I can devide the required activities into below.
    1.
    Determine borrowing cost u2013
    Specific borrowings (we can capitalize interest on borrowings specific to asset)
    General borrowings u2013 calculate capitalization rate based on weighted average of borrowing costs except the specific borrowings as mentioned above.
    Borrowing costs - interest, finance charges on leases, exchange differences etc.
    Classifying borrowings into specific / general needs to be done by management.
    2.
    Identifying qualifying assets u2013
    Though we can use asset class as definition, there are various exceptions set by the standard.
    The standard allows management to exercise  judgement.
    3.
    The standard also defines when to start capitalizing the B costs and when to seize.
    What is the best way/approach for this?
    Does SAP has any solution to capitalise the borrowing costs?
    Please give your pointers/suggestions.
    thanks,
    ganesh

    Hi Ganesh,
    To my knowledge there is not SAP standard functionality to capture borrowing costs.
    But you may be able to create a workaround by making the account assignment to the borrowing specific asset at the time of accounting in SAP.
    This procedure would be very much manual, though.
    Regards,
    ~Vishal.

  • SAP Certification for  *ABAP  System Interfaces with SAP NetWeaver    7.0*

    Hi Experts,
      I am appearing for SAP Certification in the stream of  *ABAP 
      System Interfaces with SAP NetWeaver    7.0* 
      so as per the syllabus i required the following material,
      BC420,BC425, BC427,BC415,BC417,BIT300,BIT350
      BC401,BC402,BC400, BC430,BC490,ADM325,BC425,NET900,
      NW001,TESA20,TZCAFG,SM001
      so if any body is having the softcopy or any related links of the   
      above  mentioned material
      please send to my following mail ID's.
      <removed by moderator>
      Points Assured.
      Regards
      Praneeth
    Edited by: Jan Stallkamp on Oct 13, 2008 3:30 PM

    Don't ask for copyrighted material!
    Don't publish your e-mail address!
    Don't assure points!
    => this thread will be locked.
    Please read the rules of engagement otherwise you will set your account on risk of being deleted.
    Best regards,
    Jan Stallkamp

  • SAP Certification for   ABAP  System Interfaces with SAP NetWeaver

    Hi Experts,
      I am appearing for SAP Certification in the stream of  *ABAP 
      System Interfaces with SAP NetWeaver    7.0* 
      so as per the syllabus i required the following material,
      BC420,BC425, BC427,BC415,BC417,BIT300,BIT350
      BC401,BC402,BC400, BC430,BC490,ADM325,BC425,NET900,
      NW001,TESA20,TZCAFG,SM001
      so if any body is having the softcopy or any related links of the   
      above  mentioned material
      please send to my following mail ID's.
      <removed by moderator>  at  yahoo dot co in
      Points Assured.
      Regards
      Praneeth
    <THREAD LOCKED. Please read the [Rules of Engagement|https://wiki.sdn.sap.com/wiki/display/HOME/RulesofEngagement] to discover why>
    Edited by: Mike Pokraka on Oct 14, 2008 1:25 PM

    Don't ask for copyrighted material!
    Don't publish your e-mail address!
    Don't assure points!
    => this thread will be locked.
    Please read the rules of engagement otherwise you will set your account on risk of being deleted.
    Best regards,
    Jan Stallkamp

  • Solution for min price on sales order

    Dear All,
    When we create a sales order, the unit price is from price list 01 and the min price is in price list 02. We can change the unit price manually. Is there anyway to give our customer an alert or error message to force them to have a prince higher than price list 02? How can we make it? Thanks.
    Regards,
    Yuka

    Dear Yuka and Gordon,
    This is somewhat similar to my case, although mine is for inventory transfer. I selected a price list (any price list) in the inventory transfer, but I can also manually change the "info price" of each item in the row in the inventory transfer document. How would I ensure that the price manually entered is greater then the purchase price divided by 0.8? The purchase price is one of the price lists I defined in SAP.
    Thank you,
    Derrick
    Edited by: ericbajo on Apr 9, 2010 11:33 AM
    Edited by: ericbajo on Apr 9, 2010 11:34 AM

  • SAP solution for Wyoming Worker Compensation code being 6 digits

    I am trying to determine what SAPs philosophy is around the state of Wyoming changing their worker compensation code to 6 digits. The standard workman compensation code on the positions and jobs is only 4 in length. I am unable to find any OSS comments around this issue.

    Dear,
    Just search with Wyoming Worker Compensation code
    Check for appropriate one ... if not relevant and not changed with customization settings by someothers - raise a note.
    Note 594574 - Wyoming Workers' Compensation Code changed for 2003
    Regards,
    Syed Hussain.
    Edited by: Syed Hussain on Dec 4, 2009 2:53 AM

  • Possible solution for white C2D iMacs with screen artifacts or lines

    I have a white 20" Core 2 Duo iMac with the famous screen artifacts issues. Screen tearing, horizontal lines, goofy pixels, you name it. From my research it seems there are countless others with these problems.
    I tried running the SMC fan control app to boost fan speeds. This helped a little, but did not completely solve the issue. A lot of people think these issues are related to heat, and I agree, but only partially. When a graphics chip overheats it is eventually damaged. I have damaged my share of graphics chips while overclocking them in my PCs. In the case of my iMac and maybe plenty of others, I still have issues if the GPU is hot or cold.
    I installed WinXP using bootcamp. I finally found an application which will change the clock speed of the GPU on the fly. The X1600 GPU in my iMac has a 475Mhz core speed and 500Mhz memory speed. I cut these down to 400Mhz on the core and 400Mhz on the memory. At these lower speeds I no longer have any issues with screen tearing, horizontal lines, or random crashing. I do still have a few wierd pixels here and there, but they are not all that noticeable and I can live with them.
    Now for the fun part. I wanted to permanently fix these speeds into my GPU so when I boot back to Mac OS X, I don't have any issues, and I no longer have to boost fan speeds or run any additional apps. I spent most of today taking apart my iMac, putting DOS on a spare SATA hard drive, and running an external monitor while booting my iMac with the spare drive hanging out the side. All this so I can run ATIflash, and use it to dump an image of the GPU BIOS ROM file.
    Well, I ended up finding out the ATI GPU has no ROM to flash. My best guess is open firmware or something like that passes this data on to the GPU when the system boots.
    So, in my case slowing the GPU down significantly reduced my problems while running within windows. I am 100% confident slowing the GPU down will also improve issues within Mac OS X, but I have no way to pull this off.
    If Apple reads this, or if anyone has any connections at Apple, can we please get an optional firmware update to reduce the speeds of the X1600 GPU? It won't fix all the iMacs with these issues, but it will fix quite a few, and for those out there who don't have any issues at all with their white C2D iMacs, lowering the GPU speeds will most likely prevent damage from inevitably occurring, keeping them a happy customer.
    Now, some of you may not like the idea of a slower GPU, but if I have to pick between a slower GPU and an $800 logic board, I will take the slower GPU any day.

    There is a little easier Way to Navigate in Doing an F.D.R. than that Method: I listed it here if you prefer going this Route..
    2. Re: FACTORY RESET FOR RAZR AN RAZR MAXX

  • Is there a solution for poor sound quality with ios7.03?

    Hi all,
    After waiting for a while and using 7.0.2 on my iPad I decided to upgrade my iPhone today. 7.0.3 was installed and while I am used to the general operation of the new iOS, I found that sound quality is terrible. The audio is extremely compressed. This was not an issue with 7.0.2. Unfortunately I also updated my 7.0.2 iPad to 7.0.3 and have confirmed that the latest iOS is at fault. Somebody really messed up.
    Is it possible that I am missing a setting somewhere that was added with the latest update?

    Never mind. After testing with my android tablet I found it was the headphones. They are Bose QC 15. The original battery was running down but work great yesterday. I suspected the battery and changed it but the problem persisted which led me to blame the upgrade. I should have known better. My apple devices have been flawless. Sorry for crying wolf...

Maybe you are looking for

  • Trying to capture in FCP 6.06 w/ Sony fx 1000

    Trying to capture footage in FCP 6.06 from an fx 1000. FCP does not seem to see the camera while it is in vcr mode and hooked up through firewire. I think I have FCP fully updated but don't see the options for hdv to capture. Need help with proper ca

  • Changing MIDI Port Order is wreaking havoc on my Environment

    Anyone seen this before? I've got a MOTU Midi Express with 4 ins and outs - it's my main interface. I've also got a Novation Remote25SL which works as a control surface/controller with 3 out ports. It requires some special Environment cabling to work

  • LCM Utility

    I am in the process of setting up a port everything from env.A to env.B and have run into two issues..... they appear to be connected., The config. and installs are all identical .... except for the server names. Here is what I have been able to do s

  • Work folders not working

    Hi everyone. I am trying to configure work folders on W2012 R2. I completed server configuration (as described in all procedures) and I have no error in server logs. Port 443 is in use by "windows sync share" service (if I stop this service the port

  • I pay my rate and I can't make phone calls

    This is a concern i can't find a option to ask WHY I CAN'T MAKE A CELL PHONE CALL IF I ALREADY PAY THE MONTHLY RATE. Please I need a Skipe customer service??????