Can anyone please point me to SAP-XI transport strategy document. e.g what would you transport, what tool would you use etc.
Thanks.

Hi,
We have two options
-- one is File transfer method through which we can export the objects into a file and that can be imported in another.
here we can export individual obeject and SWCv wise,namespace wise also.
-- Another one is CMS
through this option tracks are to be defined from DEV-QA-PROD
see the below links
https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/f85ff411-0d01-0010-0096-ba14e5db6306
Also...
How to configuring the CMS for XI?
Please see the below links
https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/b8d8f7b2-0701-0010-b09a-cda4cca2c98e
Where can I get installation files of DTR, CBS, and CMS?
https://websmp201.sap-ag.de/~form/sapnet?_SHORTKEY=01200252310000071155&_SCENARIO=01100035870000000202 -> How to Guide on
'How ToTransport XI Content Using CMS'.
/people/sap.india5/blog/2005/11/28/xi-software-logistics-solution-iii-cms
Regards
Chilla
<i>reward points if it is helpful..</i>

Similar Messages

  • Multiple SAP component transport strategy

    Hi all,
    I have a SAP landscape with ERP, BW, F&R and DM. Each of these components has 2 instances (dev and quality/test). The transports between these instances are managed with the TMS, aren't they??
    But my real problem is that I don't know how to define the transports between components. I have read something about RFCs between ERP and BW instances. <u>Is the same with F&R and DM??</u>
    Thank you.

    Hi,
    Rarely, a customization done for ECC appy to BW or any other system...
    Anyhow if you found a case where you need to apply the same changes to all the systems you can release the transport and copy the cofile and data file to the target systems...
    1. release the transport (with the customization or whatever changes you want to export)
    2. go to \usr\sap\trans\<sid>\cofile and \usr\sap\trans\<sid>\data of the source system and look for the transport... cofile <sid>K<transport number>, data file <sid>R<transport number>.
    3. copy the cofile and datafile to the \usr\sap\trans\<sid>\cofile and \usr\sap\trans\<sid>\data of the target system.
    4. Then just go to STMS -> Extras -> Other requests ->Add
    5. Transport and distribute.
    Regards
    Juan
    Please reward with points if helpful

  • Transport strategy for BOE landscape

    I am looking for a transport strategy for BOE landscape from security viewpoint. Basically we want to transport crystal reports, webi reports and folders along with security principles (BW roles/users included). Can anybody provide more info on this?
    Regards,
    Prasad

    Yeah...we have LCM (XI 3.1 onwards) and Import Wizard for BOE tranports. But if we use BW roles as principles, transporting reports/folders with Security doesn't give desired results.
    For example, if I am transporting a webi report with principle DEV001@RoleA from Dev to QA/PRD, I would get a new group in QA with name DEV001@RoleA instead of QAS001@RoleA. *I am looking for a pointer change here from DEV001 to QAS~001*. I think we have this feature of changing system pointers for Connections/Universes/Crystal Reports in LCM.
    I know we need to move crystal reports and publish them again in QAS/PRD but this way we need to assign security for folders. I want to avoid these efforts by doing one time configuration in DEV and moving it to QAS/PRD through LCM. This is more consistent with current SAP Netweaver transport strategy.
    Regards,
    Prasad

  • SAP Query Use and Transport Strategy

    Anyone wish to share their experience in the use of SAP Query?  We generally have an understanding that we don't want to be giving out this tool to end-users in Production.  We would like to create queries, and when we wish to give them out we'll attach t-codes to them and roll them out.
    However in practice, this is becoming difficult.  An example is where in our gold client we create queries and then we would typically transport to our unit test client.  But whenever we do an export, it generates a transport request.  Before we are done testing we may end up with 10's of transports for a single query?
    Anyone have some ideas on a transport strategy for SAP Query?  How about it's use in Production?  Our landscape for changes are typically DEV Gold -> DEV Test -> QAS -> PRD.  We would ideally like our transport strategy for queries to match what we do for everything else.

    HI,
    Query objects are transported in different ways according to the query area in which they were created.
    In order to know which transport options are available, you must first understand how query objects are created.
    <b>Standard Area</b>
    Query objects are stored in the client-specific table AQLDB. They are not connected to the Change and Transport Organizer.
    <b>Global Area</b>
    Query objects are stored in the cross-client table AQGDB. They are connected to the Change and Transport Organizer.
    http://help.sap.com/saphelp_47x200/helpdata/en/d2/cb467f455611d189710000e8322d00/content.htm
    Global area objects can be transported into other systems. Standard area query objects can not only be transported to other clients within their own system, but into all clients of other systems as well. In addition, query objects can be transported from the global query area to the standard query area and back within the same system.Transports are normally performed by the system administrator, not by end-users. For this reason, you need the appropriate authorizations
    Check the below links for detailed explanation
    <b>Transporting Global Area Objects</b>
    http://help.sap.com/saphelp_47x200/helpdata/en/ec/052786a30411d1950a0000e82de14a/content.htm
    <b>Transporting Standard Area Objects</b>
    http://help.sap.com/saphelp_47x200/helpdata/en/ec/052789a30411d1950a0000e82de14a/content.htm
    <b>General Transport Description</b>
    http://help.sap.com/saphelp_47x200/helpdata/en/d2/cb4699455611d189710000e8322d00/content.htm
    <b>Generating Transporting Datasets</b>
    http://help.sap.com/saphelp_47x200/helpdata/en/d2/cb46a6455611d189710000e8322d00/content.htm
    <b>Reading Transport Datasets</b>
    http://help.sap.com/saphelp_47x200/helpdata/en/d2/cb46e7455611d189710000e8322d00/content.htm
    <b>Managing Transport Datasets</b>
    http://help.sap.com/saphelp_47x200/helpdata/en/d2/cb46f4455611d189710000e8322d00/content.htm
    <b>Transporting Objects between Query Areas</b>
    http://help.sap.com/saphelp_47x200/helpdata/en/ec/05278ca30411d1950a0000e82de14a/content.htm
    I hope this solves your purpose.
    Regards,
    Vara
    Message was edited by:
            varaprasad bhagavatula

  • Transport strategy of BI-BO Objects

    How to transport the BI-BO objects across the landscapes? I mean WEBI, DEKI, XCELCIUS, Crystal and all other BO reports
    created on BI Queries/Infoproviders.
    Can we have BO reports saved along with our regular BEX Queries in BEX folders?
    Can we publish BO reports in BI portal?
    Plz help in understanding the transport strategy of BI-BO objects!!

    If you're using XIR2 you have only one option - Import Wizard tool. If you are on Xi3.1 you have 2 options Import Wizard or LCM (Life Cycle Manager).
    Documentation for both available at http://help.sap.com/businessobjects.
    Can we have BO reports saved along with our regular BEX Queries in BEX folders?
    No
    Can we publish BO reports in BI portal?
    Yes, if you're using CR reports.

  • Transport strategy for your transport landscape is inconsistent

    Hello everybody,
    we had 4 system landscape.
    DEV>QAS>TST-->PRD.
    we move the request from DDEV >QAS>TST and then forward request from TST to PRD system.
    Now, we have delete the system TST from TMS, after deletion it give the warning.
    Transport strategy for your transport landscape is inconsistent.
    Message No. XT481
    Please suggest, what is meaning of this warning and how to correct.
    Thanks
    Ganesh

    You need to do following
    1. Logon to domain controller client 000 -->STMS --> Overview System --> Select TST --> SAP System --> Delete
    2. Reconfigure STMS  DEV>QAS>PRD
    3.STMS --> Overview Transport Routes  --> Configuration --> Distribute and Activate (To All System)
    Note : You should do this from Domain Controller client 000
    I assumed you know Step 2. If you dont please let me know i can guide you on that as well
    Cheers !
    Manish

  • ChaRM: usage of ChaRM and none-Charm transport strategy

    Hi ChaRM-TMS Gurus!
    We have the following [SAP system landscape |http://www.file-upload.net/view-1086963/SDN_TMS_Ist_Soll.jpg.html] and would like to use ChaRM approach simultaneously.
    What are the minimal requirements concerning transport layers/routes, which settings should be changed?
    How much and which transport layer/routes does ChaRM need?
    a) 1 any new transport layer/route
    b) standard transport layer, transport layer "SAP" and others
    Should all the standard transport layer/routes from virtual systems to real QAS and PRD systems or can I start as follows:
    1) Leave the current TMS settings unchanged
    2) Activate the extended transport control
    Result: the current setting will be client specific and all the old transport requests will be moved to client specific transport routes
    3) change the transport strategy (from mass transport to single transport)
    3) Define new transport layer
    4) Define  new transport route for SAP objects from DEV to QAS
    and assign the transport layer from 3) (client specific)
    5) Define  new transport route ZXXX from DEV to QAS
    and assign the transport layer from 3) (client specific)
    6) Define the delivery transport route from QAS to PRD (client specific)
    7) activate and distribute the settings
    Thank you very much indeed!
    Thom

    Hi Martin,
    Solmaniacs' assumptions are correct. You can have as many source clients as you want.
    As long as
    - STMS configuration (transport routes, and domain links) are consistent
    - SMSY configuration (logical components are declared properly with assigning the right role types to systems/clients)
    - Project declaration are done correctly (so that from Solman solar_project_admin you can read the STMS as confiured in the distant STMS domain)
    - IMPORTANT: those configuration GO ALONG with each other !! (SMSY should nt contradict STMS for example...)
    The tasklist that is generated for each Solman project will be as follow
    - Node 1: Header Tasks (commun to all systems)
    - Node x: Corresponding to track x declared in Project (each Source System will have his own node with the corresponding track under)
    - Node x+1
    - Node ...
    - Last Node : Tasks for Tasklist closure - checks on scma consistancy and CTS projects closure
    So you'll always have n+2 nodes in your tasklist; n beeing the number of declared source (=dev) systems in project
    For each action launched from change docuemnts like creation of TR, release of TR or Retrofit (as Solmaniac said) you'll have an additional pop-up that will appears letting you choose the system you want to use for the action
    Hope its helpful
    Regards
    Khalil

  • Re: Workflow controlled Transport Strategy

    Hi friends,
            we are using workflow controlled transport strategy in our landscape. So far we are using existing help help.sap.com to configure the same. But we found that it is not enough for completing configuration in perspective of out client requirement. Can anybody help to get the more help on this?
    Any help would be highly appreciated.
    thanks,
    krishna

    SAP Note : 313991
    Due to the approval of a request in the QAS system, this becomes
    active in the import queue of system VDE (status: Request is ready
    for import). Refused requests receive the following status:
    Request was refused.
    o The RSTMS_DIST_APPROVED_REQUESTS program is used to transfer the
    requests with the status "Request is ready for import" from the VDE
    import queue to the supply system of VDE (that is, the PRD
    production system or, if necessary, several production systems and
    clients) and then to delete them from the import queue of VDE.
    Refused requests (status: Request was refused) are also deleted
    from the VDE queue.
    You can choose between the following options:
    - Transfer all approved requests:
    All approved requests from the VDE queue which are before the
    end are transfermark (stop mark) red. All requests that have
    not yet been processed with the QA procedure remain in the VDE
    queue until a decision (approval or refusal) has been made.
    cheers
    dEE

  • Transport strategy for BPC

    Hi all,
    Is there a transport strategy for BPC.  How do we move changes made in the development to the testing to the production environment?  How do we transport the changes?  Is it done manually or does BPC have a feature that automatically transport the changes?  Does BPC keep automatically track of the changes?
    Thanks.

    I think this OP's message was posted in the wrong forum.  In any case, there's a whitepaper on the transports for BPC 7.0NW.
    https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/b048ecf4-9414-2c10-ceac-fb2492a8016c
    Hope this helps.
    -Ken

  • SAP Query: Transport tool(program: RSAQR3TR)

    Does the SAP Query: Transport tool(program: RSAQR3TR) transport addtional fields and code in Extras of an InfoSet from one system to another?
    TKS in advance.

    Hello,
    Yes the ABAP query transports the whole Infoset.
    Goto Transaction SQ02
    Goto Environment -> Query areas -> Select teh Standard area.
    Select Environment -> Transports -> Import radio Button
    Check the Overwriting allowedand teh remove the check for Test Run
    Select the Transport Infosets and queries radiobutton
    Fill in the Infoset and teh Query with the corresponding names and the Import option with Transport Request Number
    Execute
    Regards

  • Does SAP supports transport of TPZ  files from PI7.11 to XI3.0 ???

    Hi,
    Does SAP supports transport of TPZ  files from PI7.11 to XI3.0 ???
    because after Pasting PI7.11 .tpz files into import directory of Development XI3.0 .. I am not able to find these files into ID/IR -Tools - Import ?
    What could be reason ??
    Regards
    PS

    Have check this note :Note 1247043 - Release Restrictions for EHP 1 for SAP NetWeaver PI 7.1
    BC-XI-CON-SOP
    No release
    XI 3.0 message protocol in the SOAP adapter
    Supported with EHP 1 for SAP NetWeaver Process Integration 7.1 (version abbreviated with 7.11 from now on) is the XI 3.0 message protocol in the SOAP adapter for the communication between an Advanced Adapter Engine version 7.11 and ABAP proxies generated in the SAP NetWeaver Process Integration versions 3.0, 7.0, 7.10, 7.11; Advanced Adapter Engine version 7.11 and 7.10; SAP Partner Connectivity Kit version 7.11 and below, Java SE Adapter Engine 7.11 and below, Integration Server 7.11. However for all above listed scenarios the following functions are currently not supported: Acknowledgements, Transport & message level security, Principal propagation, Bulk support on sender-side, HTTP destinations support. Not supported with EHP 1 for SAP NetWeaver Process Integration 7.1 is the XI 3.0 message protocol in the SOAP adapter for the communication between an Advanced Adapter Engine version 7.11 and Java proxies, Integration Server 7. 10 and below.
    ( Changed at 18.12.2009 )
    Regards
    Pothana

  • SAP IK Transports Error

    HI Experts,
    I got error while improting SAP IK Sp3 Unicode Trasnsports in the BI SYSTEM. please find detailed error message from the log file.
    R21K900693 (Business objects personalization objects) Failed with return code:8..See below error message
    Program /CRYSTAL/SAPLPERS, Include /CRYSTAL/LPERS$01: Syntax error in line 000012
    Message no. PU163
    Diagnosis
    Program /CRYSTAL/SAPLPERS has a syntax error in line 000012 of INCLUDE program /CRYSTAL/LPERS$01. The error text is displayed in a log line.
    Need your early responses and suggestions on the error.
    Thanks,
    bharath

    Hi,
    We done direct SAP IK Sp3 Transports.Do we need to do First SAP IK transports and then SAP IK SP3 Transports?Please suggest me either i need to do first Plain SAP IK transports and then the SAP IK SP3 transports?
    Please find the Detailed Log
    Log Overview for R21K900693 (JJI)
             R21K900693              Business Objects Personalization objects
               BDA        System BDA
                          Selection for Import                     04.01.2011 07:26:16    (0) Successfully Completed
                          Import ABAP Dictionary Objects           04.01.2011 07:34:16    (0) Successfully Completed
                          ABAP Dictionary Activation               04.01.2011 07:34:17    (8) Ended with errors
                          Import                                   04.01.2011 07:34:18    (0) Successfully Completed
                          Check Versions                           04.01.2011 07:34:19    (0) Successfully Completed
                          Generation of Programs and Screens       04.01.2011 07:34:20    (8) Ended with errors
                          Import ABAP Dictionary Objects           04.01.2011 07:35:30    (0) Successfully Completed
                          ABAP Dictionary Activation               04.01.2011 07:35:30    (8) Ended with errors
                          Import                                   04.01.2011 07:35:32    (0) Successfully Completed
                          Check Versions                           04.01.2011 07:35:32    (0) Successfully Completed
                          Generation of Programs and Screens       04.01.2011 07:35:34    (8) Ended with errors
    ABAP Dictionary activation ended with RC:08
      Following objects not activated/deleted or activated/deleted w. warning:
      Table /CRYSTAL/PERS_VALUE could not be activated
      (E- Nametab for table /CRYSTAL/PERS_VALUE cannot be generated )
      Table /CRYSTAL/PERS_VAR could not be activated
      (E- Nametab for table /CRYSTAL/PERS_VAR cannot be generated )
    Generation of programs and screens:
    Generation of programs and screens for transport request R21K900693
    Only generates programs with LOAD versions
    Start on 04.01.11 at 07:34:20
    Generation of the transported programs
    Program /CRYSTAL/SAPLPERS, Include /CRYSTAL/LPERS$01: Syntax error in line 000012
    Field '/CRYSTAL/PERS_VAR' is unknown. It is neither in one of the specified tables nor defined by a
    Database COMMIT executed
    Generation of the users of the transported Includes
    Ended with RC:08

  • SAP's Maintenance Strategy

    What is SAP's Maintenance Strategy? Is it consistent across various domains (industry vertical) ?

    http://www.sap.com/solutions/business-suite/srm/newsevents/press.epx?pressid=2932
    Regards,
    Rich Heilman

  • Mass transport strategy but satellite system is configured for ChaRM

    We want that all transports are automatically transported in the development test client.
    We have calling a job with program TMS_BCI_START_SERVICE in the satellite system. But this program can only be used for mass transports and does not work when single transports strategy is activated.
    Question:
    Is there no solution to transport all this transports automatically in development test client via mass transport strategy if satellite system is configured for ChaRM scenario?
    Thanks a lot in advance.
    Regards Urs

    Hello Michele,
    Please, check the point 5 in the link below:
    /people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-questions-and-known-errors
    I think that this information can help you.
    Best Regards,
    Diego Fischer

  • SAP Enterprise Portal Strategy Documentation

    Hi,
    I would like to get a template document to design the SAP Enterprise portal strategy. Is there a document which lists the areas to be considered while designing the Enterprise portal strategy? Are there any best practices which SAP suggests in this area ?
    Regards,
    Amit

    Hi.
    You may find the following links useful for you:
    [Planning and Succeeding with Your SAP NetWeaver Portal Project|http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/903122e0-b3d4-2b10-c5b3-c19f5dd58072]
    [Best Practices - Portal|http://www.sdn.sap.com/irj/sdn/index?rid=/webcontent/uuid/e0b46f8a-8fce-2b10-95a5-b72dd53a952b]
    Best regards,
    Aliaksandr

Maybe you are looking for