Hi,
On APO 3.0 in the past we created cross-system transports from our 4.6c R/3 system in SCAL to keep APO and R/3 calendars in synch.
Since upgrading to APO 4.1 which is on Basis 6.40 we are not sure if its safe to transport SCAL from R/3 4.6C to APO 4.1 which is on 6.40.
Is anyone doing this or do you manually maintain SCAL in both SCM 4.1 and R/3 4.6c?
Thanks in advance.
Sean

We have tried to configure this in our SCM development systems for both F&R and EWM but have hit a couple of snags...
We have the following system/client structures for the F&R SCM system:
Development                    Quality Assur.                  Production
DF0 260 (Golden)                 QF0 360                              PF0 960
DF0 261 (Unit Test)
DF0 262 (Perf. Test)
And for BI we have:
DB0 120                                QB0 220                             PB0 920
For the QA and Production instances, we do not have an issue, since the limitation of having only one BI client per system doesn't matter as we only have one client to connect.
But for the Development systems, currently it is the DF0 261 client that is connected to the DB0 120 BI client. We want to be able to pull the data from our ECC golden client (DE2 700) into each of the DF0 clients. But when we try and run RSA1 in any other client than 261, we get an error telling us that only one client can connect to BI and we must work in that client.
I thought we could maybe get around it by simply running RSIMPCUST in a batch job, but cannot see how to save a variant with the source client name in it since this is always greyed out when you run it online. I guess if I maintain the BI system as the default client for each of these F&R systems in SCC4 it might work, but I don't know what else uses this default client value?
Does anyone know of any workarounds for this? It would be really nice to be able to synchronize all systems (especially as the link is between two non-BI systems, so the BI restriction should not even apply). If we have to go back to the current approach of manually updating the development systems for any changes in ECC then we may as well use that for all clients and just transport the changes. It is not a good solution though...
Thanks,
Luke

Similar Messages

  • Using table rate with scale in transportation zone

    Hi Experts,
    I have a question with using a rate table and scale in transportation zone.
    I need a scenario of calculation sheet with rate table using a transportation zone scale. In my freight order, i have many freight unit of different destinations (many locations).
    I configure this scenario, but the system does not use the transportation zone with select price on table rate.
    Help me.

    Hi Tarun Kumar,
    well, go to more details.
    I have a freight order with two stages.
    My calculation costs is based on stage condition (FRT_PEDIDO).
    My configuration for this scenario is:
    )    Calculation Sheet
    )    Rate Table
    )    Config to condition
    )    Master data to Transportation Zone
    )    Locations included in transportation Zones
    )    transportation Lane
    location “PLC_SBC_014” is my plant and “Z_SP_SUL” is my transportation zone.
    “Z_SP_SUL” is the transportation zone and “0……021” is customer location 1.
    “Z_SP_SUL” is the transportation zone and “0……063” is customer location 2.

  • Collaboration:Issue with Exchange Calendar Transport & Edit Local Features

    I have installed the Exchange Transport to interface the Outlook calendar with our portal calendar. When I attempt to access the Calendar, I receive a blank calendar section (no errors). I have checked permissions and SAP notes, but I can't figure out where the issue is. I have the same problem with the "Edit Local" feature. When I attempt to edit a document, nothing happens (no errors). I even tried installing the Java RTE 1.4, but I do not receive any indicatation that the RTE or ActiveX component is even being used.
    Thanks

    Hi Vick,
    Based on my research, I suggest you should upgrade the AD first.
    1. Exchange 2013 CU5 contains schema changes. To upgrade the Schema to CU5 you can execute the following command:
    Setup.exe /PrepareSchema /IAcceptExchangeServerLicenseTerms
    2. And you also should upgrade the
    Configuration Partition and the Domain Partition with the following command:
    Setup.exe /PrepareAD /IAcceptExchangeServerLicenseTerms
    Setup.exe /PrepareDomain /IAcceptExchangeServerLicenseTerms
    3. After finished above two steps, now you can start to upgrade an Exchange 2013 server to CU5. Open a command prompt and enter the following command:
    Setup.exe /Mode:Upgrade /IAcceptExchangeServerLicenseTerms

  • Calendar transport

    Hi friends,
    Here is our issue,
    we are not able to delivery today( no availability check for all materials even though MD04 shows material available)
    after checking, I found today (01/20) was set as Christmas eve. After fixing, delivery wroks on DEV. After transport to QAS, it shows the correct calendar info. But still delivery won't work with the availability check. I believe it's something realted to transport. Please advise if you had the experience.
    Thanks,
    Linda

    Check OSS 1579665 - Scheduling - Date lies on a non-working day
    Regards,

  • SCAL - Transport function only active within customizing client

    hi all,
    when executing SCAL, the system prompted this message "Transport function only active within customizing client"  at the bottom of the screen.
    in SCAL --> Calendar --> Transport (this option not allowed)
    I have checked the client details in SCC4, it is set as
    a.) Automatic recording of changes
    b.) Changes to Repository and cross-client Customizing allowed.
    pls advise what need to be done to allow this client to be able to configure calendar, to save and to create TR.
    previously it was ok.
    thanks.
    regards,
    Kent
    Environment
    NW 2004S SR2 (Kernel 7.00 for OS/400)
    ERP 2005 SR2 (ECC6)

    hi all,
    the solution for this problem is in SCC4 , change the client role to "customizing" ...
    it was set to "test" that's why doesn't allow to create transport request.
    sigh .. can't reward myself.
    regards,
    kent

  • Transport of Global Parameters from ECC to SCM

    We have tried to set up RSA1 in our SCM development systems for both F&R and EWM to allow us to transfer calendars, UOMs etc from ECC to these systems but have hit a couple of snags...
    We have the following system/client structures for the F&R SCM system:
    Development                    Quality Assur.                  Production
    DF0 260 (Golden)                 QF0 360                              PF0 960
    DF0 261 (Unit Test)
    DF0 262 (Perf. Test)
    And for BI we have:
    DB0 120                                QB0 220                             PB0 920
    For the QA and Production instances, we do not have an issue, since the limitation of having only one BI client per system doesn't matter as we only have one client to connect.
    But for the Development systems, currently it is the DF0 261 client that is connected to the DB0 120 BI client. We want to be able to pull the data from our ECC golden client (DE2 700) into each of the DF0 clients. But when we try and run RSA1 in any other client than 261, we get an error telling us that only one client can connect to BI and we must work in that client.
    I thought we could maybe get around it by simply running report RSIMPCUST in a batch job, but cannot see how to save a variant with the source client name in it since this is always greyed out when you run it online. I guess if I maintain the BI system as the default client for each of these F&R systems in SCC4 it might work, but I don't know what else uses this default client value?
    Does anyone know of any workarounds for this? It would be really nice to be able to synchronize all systems (especially as the link is between two non-BI systems, so the BI restriction should not even apply). If we have to go back to the current approach of manually updating the development systems for any changes in ECC then we may as well use that for all clients and just transport the changes. It is not a good solution though...
    Thanks,
    Luke

    there is some explanation to what you have mentioned in Re: Factory Calendar
    this talks about calendars and is relevant till SCM 4.x
    I would imagine the situation would be the same for UOM
    In SCM 5 you have the option to update the tables, Rebuild the tables and also a simulation option

  • Include changes of PH in transport request.

    Hi Experts,
    Able to create transport request which is available in TCode SCAL to transport PH/ Calendar. How can i include only my changes in the transport request.
    for eg. if i have created new holiday calendar "NI" and new holidays id's. How can i include in transport request only my calendar NI and holiday id's.
    Kindly guide.
    Regards,
    M Bharath

    As far as I know, all the tables pertaining to Statutory Holidays, Holiday Calendars and Business/Factory Calendars will be included in the Workbench Transport.
    It may be possible to delete some of the tables from your transport, but I would not recommend it.
    Don't forget that your changes will not have an impact unless you re-generate the Work Schedules using the NI Calendar, and that will be a separate Customizing Transport.

  • How to tranport the public holiday calendar?

    Hi,
    Now I have chage a public holiday calendar, but I find I can't tranport this change to another system.
    In the initial screen of the public holiday calendar, the "Calendar -> Transport" button is gray. I don't know why?  if have another place to be set?
    thanks~

    Hi,
    After creation public holidays and holiday calendar and factory calendar, a small "Truck" icon in tcode SCAL , then select publc holidays click on the truck button, again select holiday calendar click on truck button, select the factory calendar click on truck button, when you are clicking the transport it will ask the workbench request not customizing request,  create the workbench request TP.
    After creation of TP, I think you know all the procedure(release the TP) 
    Hope this helps.
    Warm Regards,
    Devi

  • Factory calender transport

    How to transport factory calender to PRD system from DEV.

    Hi,
    Go to SCAL transaction
    Choose the function Calendar -> Transport, in the holiday and factory calendar initial screen to copy all the holiday and factory calendar data into a request.
    Please pay attention to the information which you get when transporting the holiday and factory calendar
    Transporting of Factory Calendar:
    u2022 Changes to calendar data are not automatically included in a correction request.
    Note: You cannot transport individual public holidays or calendars. You can only transport calendar data in its entirety. When you do this, all public holidays, public holiday and factory calendars existing in the target system are deleted.
    u2022 All changes made to the holiday or factory calendar must be transported manually. The holiday and factory calendars' own transport connection should be used.
    Hope it helps

  • Problem while transporting generic datasource to test box

    Hi Gurus,
    I am trying to transport Generic datasource from SCM Dev to SCM Test box. Datasource is created with custom table in SCM.
    It is throwing me RC8.
    Start of the after-import method RS_ISMP_AFTER_IMPORT for object type(s) ISMP (Activation Mode)
    DataSource ZGATPUPLOAD does not exist in source system TA6CLNT010 of version A
    Mapping between data source ZGATPUPLOAD and source system TA6CLNT010 is inconsistent
    DataSource ZGATPUPLOAD does not exist in source system TA6CLNT010 of version A
    Field /BIC/ZCSHIPTO will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field CALWEEK will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field FIXPEGQTY will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field LOC will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field MATNR will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field PROD_ALLOC_OBJEC will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field SALESORG will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field SALES_DIST will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field SIMID will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Field USER_MOD_QTY will not be delivered from DataSource ZGATPUPLOAD in source system TA6CLNT010
    Start of the after-import method RS_ISTS_AFTER_IMPORT for object type(s) ISTS (Activation Mode)
    Reference to transfer structure ZGATPUPLOAD_CA not available. No activation possible.
    Please give me suggestions....

    Are you still looking ans on it?

  • How can Transportation Facility for Students be captured ?

    Hi All,
    Educational institutions would usually have transport facility for students. This facility might be operated either by themselves or they might outsource the same. In either of the cases, if the data has to be captured, how would we do so?
    One solution that comes to mind is using the Transportation Management module of SCM.Is there some other way of doing it in HE-R or in HR-Training and Event Management ?

    Hi Ramesh,
    <b>Not sure, if not look relevant, it will atleast give you a chance to laugh...</b>
    Till the time SAP CM comes up with solution for Transport, if it is necessary, I hope all relevant reports can be generated in Tra&Eve Mgmt by configuring Business Event group as Transport System and Business Event type as "Bus-Route1" "Bus-Route2" "Bus-Route3" etc etc.
    Now, you can schedule as per their start and end time of destination.
    Internal/External Price can be decided.
    In Reports: you can check "Bus route 1 "demand /Attendence/Booking etc etc...
    And students can be assigned to Bus of their Route, I mean to particular Business event...
    It's simple manipulation, not the right way...but could not get the right solution.I am not sure if something is there in 3rd party solution.
    Regards,
    Dev

  • LE-TRA pricing and Rate or Scale

    HI experts,
    I need some information about the functioning RATES or scales of transport.
    How do I set up the rates for conditions calculated about a distance and a weight / distance.
    Functional dynamics of these scales is not clear, thank you to help me understand this point.
    I need some information about transport pricing.
    thank you in advance
    D.D

    hi,
    you said rate or scale ?
    you want the condition types which you are using for FRIEGHT,  in normal pricing procedure or transporation pricing procedure.
    for normal pricing procedure there is KF00 in that basing on condition classification you can have the scales basing on the weight or distance.
    in transportation pricing procedure:
    seperate condition types are available you use which ever you want like FB00/weight.
    regards,
    balajia.

  • Factory calendar change in APO

    Hi All
    There has been a change in Factory calendar (holiday changes) in R/3
    How do I make the changes for calendar in APO ? Never done this. step-by-step procedure would help.
    Looks like there is a 'holiday calender' assigned to 'factory calendar' and I have the factory-shut down dates.
    Thanks
    Pooja

    Pooja,
    You can transfer Factory Calendars from R/3 to SCM.  Here are the steps:
    in SCM
    Transaction RSA1
    Select Source systems>SAP>your R/3 client.
    Right click on the client>Select Transfer Global Settings.
    Select Factory Calendars
    Select Rebuild tables
    Unfortunately, you may not update only a single calendar, you must update all calendars in SCM.
    You can set this program up as a batch job using RSIMPCUST.  Some companies run this regularly, depending on how often the calendars change in R/3 and how the changes will impact SCM.
    If you have Timestreams that rely on your factory calendars, you will have to update these manually using /SAPAPO/CALENDAR transaction
    Regards,
    DB49

  • Factory calendor changes through transport request

    Hi,
    Is it the right way to move the factory calendor changes to golden client to quality to production clients through transaport request. Please guide me.
    Regards,
    Mastan.

    Hello
    Please take a look on the following note that describes the pre-requisites to transport a factory calendar:
    538344 - Transporting calendar dates
    Also consider the following points:
    The calendar can only be transported as a whole.
    The calendar transports work according to the motto: all or nothing.
    I.e. no keys are specified in the transport and the whole content of the tables is transported.
    It is not possible to select single calendars for transport.
    For all above reasons, when transporting the calendar, all existing entries in the target system will be overwritten.
    BR
    Caetano

  • Second working day of a month

    hello abaper,
      Cud u pls tel me how to get second working date of any month

    Function group                 Function group short text
    Function Module Name           Short text for function module
    CATSXT_UTIL
    CATSXT_GET_HOLIDAYS
    DTCO
    CHECK_HOLIDAY
    COLLECT_HOLIDAY_DT
    FB00
    BKK_CHECK_HOLIDAY
    HRFBN00GENERAL                 Function Group for FBN FMs
    HR_FBN_GET_HOLIDAY_PLAN_COST   Display FlexBen Holiday Cost in IT0377
    HRFBN00MISCEL                  Function Group for Misce. Plans FBN
    HR_FBN_UPDATE_HOLIDAY_QUOTA    Anmeldung eines Mitarbeiters für Sonstige Pläne
    HRPAYBE_SRD_UN05
    HR_BE_DAQ_UN05_NATUDAY_HOLIDAY Get nature of day
    HR_BE_UN05_PUBLIC_HOLIDAY      Get replacement day for public holiday falling on a day-
    off
    HRPAYDETM01
    HR_DE_CHECK_HOLIDAY
    HR_DE_GET_HOLIDAY
    HR_DE_REMOVE_HOLIDAY_FROM_LIST
    HRTIM00FORMS
    HR_FORMS_READ_HOLIDAYS
    RHBD
    RH_REQUEST_ON_BEFOREHOLIDAYS
    RH_REQUEST_ON_HOLIDAYS
    RPTM
    RP_GET_REMAINING_HOLIDAY
    SALP_UI                        User Interface for PerfDB
    SALP_UI_F4_HOLIDAY             f4-help for holiday & factory calendar
    SCA5                           Calendar: Additional functions
    HOLIDAY_CALENDAR_GET
    HOLIDAY_GET
    SCAL                           Calendar functions
    HOLIDAY_CHECK_AND_GET_INFO     Calendar function: Public holiday check with information
    SCTR                           Transport public holiday texts
    HOLIDAYTEXT_CORRECT_KEY
    HOLIDAYTEXT_FIND_OUT_RULES
    SFT1                           CHDO HOLIDAY => Gen. by RSSCD000
    HOLIDAY_WRITE_DOCUMENT         CHDO HOLIDAY => Gen. by RSSCD000
    SFT2                           CHDO HOLIDAYCAL => Gen. by RSSCD000
    HOLIDAYCAL_WRITE_DOCUMENT      CHDO HOLIDAYCAL => Gen. by RSSCD000
    WSAF
    WSAF_OUTBOUND_PUBHOLIDAYS
    try these...
    ALSO
    Date, Month and Popup Related Function Modules
    Date/Month Related Function Modules:
    DATE_COMPUTE_DAY u2013 Finds day of the month
    DATE_CONV_EXT_TO_INT  - user formatted date is converted to system date
    DATE_GET_WEEK  - convert date into year + week format
    DATE_TO_DAY u2013 gives weekday from date
    DATE_IN_FUTURE u2013 takes number of days and date  - gives future date in user format and system format
    MONTH_PLUS_DETERMINE u2013 add or subtract month from a date
    RH_GET_DATE_DAYNAME - return the day based on the date provied
    DATE_COMPUTE_DAY
    DATE_TO_DAY
    RP_CALC_DATE_IN_INTERVAL_SG u2013 add/subtract year/month/days from a date
    DAY_ATTRIBUTES_GET
    WEEK_GET_FIRST_DAY u2013 take input as YYYYWW and it gives first day of the week.
    MONTH_NAMES_GET u2013 language is only parameter. Returns internal table with months.
    MONTH_PLUS_DETERMINE u2013 subtract months from date