Scedule lines data change after MRP run
I generates a schedule lines when I run the MRP for certains articles. When I run again MRP, It modifies the data's of schedule line (quantity per ex) even thoough I have already transmetted the request (schedule lines) to the vendor.
How to prevent to make changes in the schedule line once I sent the info to the vendor. Instead I would like that the MRP creates new schedule line.
Than you for any help.
Ahmed.
Hi Ahmed,
In MRP-4 view have you maintained 1 or 2 for Indv. / Coll indicator?
Regards,
Vivek
Similar Messages
-
How system will generate schedule line for PO after MRP run.
Dear Experts,
i have updated MPS in MD61, the period indicator was M (monthly), after MRP run, system generating schedule lines on daily basis for Scheduling Agreement(ME38), i want schedule lines on mpnthly basis, how to achive this,
thanks in advance.
regards
rajakarthikHi
1. Are you maintaining any Planning time fence period for MPS- No
2. What is the PIR qty you maintained in MD61:
i.) FG01 is having BOM child part RM01.
To produce 1 nos of FG01 , I need 1 nos of RM01
ii.) i maintained FG01 in MD61 with PIR Qty 5000. in MD61,Planning period is M and planning hirizon1- jan10To 31-Jan10
ii.) i maintained lot size:Monthly lot size for RM01.
iii.) there is no stock available for both RM01 and FG01.
3. After MRP how much qty is get planned on what date-
i) planned order created for FG01 in co41 with qty-5000 nos.
ii) in ME38, schedule line created for RM01, on 01-01-2010, with 5000 nos, currently Category of Delivery Date
field is D and delivery date is 01-01-2010, but i want Category of Delivery Date should be M and delivery date should be 01.2010.
thanks
raja -
Schedule line date changes after each MRP run
Dear Experts,
Clarification needed on how the system plans the MM schedule lines.
Setting: Start in the past not allowed.
3 days for processing of order
The issue is after each MRP run the system is moving the schedule line to the current date + 3 days for processing + the planned delivery time.
If the schedule line is not firmed, after each MRP run ( which happens everyday) the system is moving the schedule line and then giving an alert saying the " order has to be rescheduled to the previous day"
on the second day after the mrp run the system moves the schedule line again by one more day and gives the rescheduling date as " -2 days from today"
this change is happening every day after the planning run. - because of this there are really no backorders ( schedule line in the past ) in the system. we were not able to know if the vendor is actually delayed in this case.
can you kindly suggest what went wrong here ??
we are using strategy 10 for the planning of procured parts. Let me know if more info is needed.
Note: we are also using stock transfer process for some procured parts. there too the PR date gets changed after each MRP run. There there is no lead time in this case. the order is placed on the same day as the requirement as both plants are nearby. There the PR date is changing everyday to the current date.
your advice would be of great help
thanks
Nagendra KumarHi Caetano,
thanks for your suggestion
Yes, we use firm zone for few of the vendors. there the system don't change the schedule lines.
Also for the stock transfer PR's there is no firm zone and the lead time is one day. in this case it changes everyday after the MRP run.
the stock transfer PR's leads to the creation of Schedule lines from the source plant. Since this PR gets changed everyday. the alerts coming out of MD07 gets changed and we really did not know if this order is delayed or not. In the source plant we use the firm zone to avoid moving the schedule line. But then the alerts are always not correct.
is there any setting which helps in not moving the PR everyday without using " start in the past"
thanks
Nagendra Kumar -
Schedule lines not generated after MRP run
Dear All,
I am trying to create Schedule lines through MRP run , but instead system creates MRP element PRqRel and its PurRqs when i check in MD04 , the following are the prerequisite i done before MRP run , but still Schedule lines are not generating.
1.activated checkbox source list in material master.,Procurement type is F, MRP type PD , lot size MB , marked JIT Scheduling indicator as 1 in Pur view of material master , no MRP group is used in our process.
2.Maintained Inforecord.
3.Maintained source list for the material and marked MRP relevant as 2. Validity also checked.
4. Quota arrangement for this vendor only.
5. Created New scheduling agreement.
6. Material is not sent for subcontracting.
7. Ran MD02 with following parameters ,
Processing key NETCH Net Change in Total Horizon
Create purchase req. 1 Purchase requisitions in opening period
Delivery schedules 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 3 Adapt planning data (normal mode)
Please let me know if i am missing something
Thanks in Advance
BennyHi,
Please check the below links...
Schedule Lines not getting created in MRP
Schedule Lines not generated for MRP Type PD
Kuber -
HCM Master Data Loan repayments date change after payroll run
I am facing a challenge in a case in which the car loan has been posted in the month of Dec’13 and payroll have been executed till Feb’14.
Now, the employee has taken relevant approvals for getting the car loan moved from Dec’13 to Nov’13 loan payment and this will also result in change in the end date of the loan.
Is there any option/possibility in SAP that we can change the start and end date of an employee who has taken Loan keeping in mind that the payrolls have been executed.
Hope it clarifies my problem if this still need to be explain further, please let me know.Hi Sonu16,
The Query is not very clear to me.
I think u want to change the date of joining after the payroll run along with position. If that is the case then u can do it.
Please followw the given steps :-
1) Go to PU03 for Payroll Status and delete all the dates, before doing it take a snapshot of the PU03. So that after changing it u can revert back to what it was.
2) Go to PA41, move to HIRING action and u'll get BEGDA in modifiable mode, then change it. Save it. But the noticeable thing is that ur present Position shud have a creation date well before ur new HIRING date otherwise u won't be allowed to change.
3) Thinking u have changed the date in Step #2, then go to SE16 and select PA0001, go to debugger mode and change the POSITION id. save it and come out and refresh it. Changes will be updated.
Hope this solves the purpose.
Regards,
ARNAV... -
Schedule line quantity changed by MRP with in firm zone
Hi,
We have a schedule agreement with firm zone maintained and MRP binding indicator blank is maitained in additional data at item level. But we have seen schedule line quantity has been changed after MRP run. I dont understand how its possible....please help
Regrds,
RaghuIf the qty is not transmitted to the vendor using message transmission, system does not firm the qty with in planning time fence.
So pls chk your planning time fence as well.
Also pls chk the below link
http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2a5b44af11d182b40000e829fbfe/content.htm
BR,
Krishna -
Automatic creation of Schedule line after MRP RUN
Hi,
Till now we are using only PO for placing orders to vendor, now we want to use the functionality of scheduling agrement, so that after MRP run, we can get automatic schedule line creation, for this , what are settings required, how system create the automatic schedule lines based on which criteria, second thing while creating on eschedule agrement i found that the conditon which i can add for a vednor in ME21N that all condition are not coming while creating schedule agrement even my vendor is same for PO and Schedule agrement, so what are the setting required for this.
regards,
zafarHi
1.In material master purchasing view data auto PO is to be flagged.If scheduling agreemet with release documentation.
Then flag JIT indicator 1.
2.maintain MRP views in material master
3.In source list for fix vendor,source list usage 2 is to be maintained.
4.Vendor master purchasing data auto PO indicator is to be flagged.
5.Then when you run MRP automatically schedule lines are generated.
For JIT and forecasting maintain creaton profile in OMUP transction.
Assign the creation profile in scheduling agreement. -
PR created after MRP run, instead of schedule line
Dear all,
I want to create schedule lines automatically from the planning run, for raw material. I have maintained info record, scheduling agreement, quota arrangements and also the source list.
For the raw material, safety stock of 1000 nos. has been maintained. The current stock of the material is 0.
After MRP run, based on the upper level PIRs, schedule lines are generated properly. But, against the safety stock of 1000, a PR is generated.
I donot want a PR to be generated.
Please suggest a solution.
Thanks in advance,
Shrenik
Edited by: Shrenik on Mar 8, 2008 4:17 PMDear all,
I checked an found that the schedule agreement date does not have any effect. Even if the requirement date falls outside the date range, i am able to create schedule lines.
I also found that if i maintained GR processing time, then always a PR is created. If GR processing time is 0, then only schedule line is created. Moreover, planned delivery time does not have any effect on the calculations, even if it is 10 days, 20 days or 900 days.
Can someone please clarify all these? How are these times taken into account?
Thanks in advance,
Shrenik
Edited by: Shrenik on Mar 9, 2008 3:04 PM -
Availability/GR Date after MRP Run
Hi All,
After MRP Run for perticular period, system plan the material at the start date of the period. Is there any ways where we can set it to last date of the period.
Like if I will put the PIR for Month of March and April, system will create the PIR on 01/03/07 and 01/04/07. so is there any ways where it can be change to 31/03/07 and 30/04/07 for march and April.
Regards
PavanHi Pravan,
you can configure lot size key in SPRO accordingly
lot size procedure-p
lo size ind-M
Scheduling-2
no of period 1
assign it o material in MRP 1 view.
Regards
Hemant Gadhari -
Hi Experts,
On the MM side creating scheduling agreements for week. When i run the MRP with parameter "Schedule lines in the opening period" i want to scheduling lines for monday, wednesday and friday in weekdays and weekly quantity of scheduling agrements will be seperated 3 equal quantity for monday, wednesday and friday.
For example;
Scheduling agreements
Date: 09.02.2012(Thursday)
Quantity: 600 ST
After MRP run;
Scheduling agreements in MD04
06.02.2012(Monday) - 200 ST
08.02.2012(Wednesday) - 200 ST
10.02.2012(Friday) - 200 ST
In this scenario which badi, user exit can i use or is there any standard solving. Can you help me. This is really urgent subject.
Thank you very much.
Best Regards;
baaksozHello Anup,
Thanks for your reply.
Actually i have already define Planning Calendar and i have assigned it in MM. The problem is i couldnt seperate the total quantity to 3 same quantity for 3 days. Here i think i can use a badi but i couldnt find any badi to use. Could you have any idea for that.
I think i need badi for MRP run or badi for purchasing order. If you know any, could you help me about it. Thank you very much.
Best Regards,
baaksoz -
Schedule lines are not coming for HALB after MRP run
Dear All,
I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
Pls let me know if I am missing something and guide me further on this.
Thanks & Regards
Kundan KumarHi,
In transaction OMDT you have to enable the indicator create schedule lines
In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
If u run MRP properly u will get schedule lines automatically in ME38.
Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3. -
Schedule lines are not coming after MRP run for HALB material
Dear All,
I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
Pls let me know if I am missing something and guide me further on this.
Thanks & Regards
Kundan KumarDear All,
I am closing this thread. As the vendor mentioned in scheduling agreement is not a subcontracting vendor. Its a individual vendor.
Thanks for all the reply.
Thanks & Regards'
Kundan Kumar -
Track Changes the qnantity change of PR after MRP run
Hi Experts
Please suggest as i am unable to find any solution of following problem.
My CLient wants to keep track the changes made to PR's after MRP run. When running MRP, already existing requirements (PRs) are automatically changed. These changes are not taken into account by BW extractors since no change document is generated.
for e.g ,if we check stock requirememt list (MD04), PR of qty 20 exists. Now if i create a manual reservation of qty 20 and then run MRP, the the PR qty will change to 40. But i am unable to track this in CDPOS or CDHDR tables.
Please suggest.
Pradeep BansalThere are 2 ways to track the PR changes
1.Goto PR display ME53N --> Environment ---> item changes
2.Goto CDHDR Table ,input doc object - BANF ,object value as PR no and get the docuemtn no .Pass this doc no to CDPOS and get the change details
Hope it helps -
dear gurus,
after mrp run.planning file entry should be deleteted.if not deleted what will be the reasons for that?
what is replanning of materials?
please through some light on this issues
-gideHi,
Planning mode controls how the system is to deal with proc proposalexisting
from last planning run which are not yet firmed in the next run.
When we are changing reqmts qty and dates for proc proposals the system
automatically take this into account.Where as if there is any change to
bom/material master whether these changes will have an effect on planning run
will be controlled by planning mode.
Planning mode is set automatically set in the planning file and also
we can override in md02.
Mode 1: Inthis mode system reactivates the existing planning data
ie the system adapts existing planning data.
ex changes to qty/dates
Mode 2 : In this mode the system reexplode tho bom for all existing proc
proposal which are not firmed if there is any changes to bom
ex changes to bom /sales order bom
changes to production version / bom explosion no
Mode 3 : Inthis mode the existing proc proposal are deleted and again recreated
ex changes to inhouse prodn time / planned delivery time/sch margin
key
Hope this will help
Regards,
nandha -
Creation of Purchase Order automatically via PR after mrp run.
Hi Experts,
I want to know that , after MRP run i got the no of PR'S. As i know , through MD04 i can create purchase order from particular pr but is their any option from which purchase order get generated automatically from pr's which are generated afrer MRP run.
Thanks n Regards
AnupamHi,
You can maintain source list Tcode ME-01 and make it MRP relevant by selecting Sorce list MRP relevant. In sorce list you can maintain vendor and material data valid for particular period and make it MRP relevant.
With this you can automatically generate purchase order from Purchase requisitions after MRP Run.
Regards,
Tushar Patankar
Maybe you are looking for
-
BAPI_CUSTOMERQUOTATION_CHANGE - error while changing a condition value
Hallo Gurus, I am trying to use tshi BAPI BAPI_CUSTOMERQUOTATION_CHANGE to change a condition value of a condition record of a quotation. Every time I execute the BAPI, instead of the condition tyoe being changed, a new record is added to the list of
-
How to create Rules with Flex Field mapping in the bpm worklist
I Have created a flex field label and was able to map to the flex field attributes . But when i try to create a rules , I don't see the label or the flex attributes in the task payload . Can someone please help is understanding how to create Rules wi
-
I just ordered and received a new Lenovo-branded Ultrabay slide-in battery for a T400. It fits perfectly (appears to) but shows an error in the battery display and cannot even read the part number. What came out was an FRU 42T4679 (10.8V, 2.7AH, 30
-
Maintaining SQL Queries in a separate text file
Hi, I am working on web based project using Spring MVC framework and I am maintaining all SQL queries in a separate text file so that I can change them any time when needed. I just want to know am I doing right, it this a optmistict way of coding??
-
Discoverer Viewer in mobile devices
Hi, Is is possible to be shown Oracle Discoverer Viewer contents in mobile devices like iPad or iPhone?