Scenario related to Assembly Process in Depot

I have the assembly process in Depot, so I configured Depot as manufacturing plant in SAP.
1. Question is some product I will get through STO and same product will be sold to customer. How do i need to handle this scenario? Because while receiving I will update in RG23A, what is the process of selling? Please explain me the steps.
2. If the depot is doing assembly, whether we need to consider it as manufacturing plant or Depot? in SAP
Thanks,
Venkat
Edited by: venkat venkat on Oct 6, 2008 9:04 PM

not received any response

Similar Messages

  • Assembly Process related configs..

    Hi,
    At Present I am working on " Assembly Processing" (i.e), A project(Project System) has to create, once I create the SO. I have done the config settings in Ps & MM. I want to know the Configs settings in SD for assembly process. ( Already I have defined the Org. Structure for SD)
    If anyone know, Pls. share your ideas.
    Regards
    Prabu

    Closed

  • Reg Assembly Process

    Hi Guru,
    i would like to know the assembly Process with CIN details.
    please give the details regarding the above.
    Thanks
    BR
    siva

    Hi Guru,
    we are using the following process.
    Direct Material
    Prcourement from the supplier who are coming under VAT taxation
    Procurement from supplier who are coming under CST taxataion
    Procurement from the supplier where C form need to be given
    Procurement from the Subcontracting Suppliers
    Indirect material:
    Service Procurement and relevant taxation
    Consignement Procurement
    Procurement from the supplier with account assignement purchase
    Capital Goods
    Capital Goods Procurement for Machineries
    Capital Procurement for Machine accessories - Grinding wheel
    Import
    Procurement from other  Plants
    Procurement of Steel from Suppliers
    Procurement of Capital Goods
    Service Procurement for Tool Calibration
    Pricing
    Domestic pricing with Tax calculation
    Option to edit the Tax condition type value in the PO
    Option to enter the tax condition value or % in PO
    Import Pricing to include the required condition of Excise and Govt requirement
    Incoming Excise Invoice
    Capture Excise Invoice During GR
    Option to Edit the value after Excise Invoice Capture
    Returnable Excise Invoice Form
    Import Duty Capture and Excise Invoice posting
    Registers
    RG23A  - Part I and Part 2 update
    RG23C  - Part I and Part 2 update
    Cenvat Regeister
    Sales Tax Regeister
    Payment of tax to central and State - Separate GR posting
    CIN Configuration Check list - PTP
    Excise Registration
    Check Excise Registration is updated for all plants
    Check Excise Reg  is updated with the Excise Range Information
    Check Excise reg is updated with the ECC NO for all the plants
    Check Excise Reg, Division and Range is maintained in Excise Reg
    Plant Settings:
    Check whether Excise Registration is assigned to plant or not
    Check the manufactruing plant is unchecked with Depot Indicator
    Check Multiple goods receipt/Multiple Credit option is set for Manufcaturing plants
    Check the Depot plant has been flagged with Depot Indicator
    Check Multiple goods receipt/Multiple Credit option is set for Depot plants
    Excise Group
    Check Excise Groups is created for manufacturing plant
    Check the outgoing Excise Invoice settings
    Check Default Challan Qty from GR is flagged in Excise group
    Check Depot setting are deflagged for manufacturing plant Excise Group
    Check in MIGO setting of Excise group all the below
    EI Create/23D deflagged for manufacturing plant
    EI Capture, Post, Duty different at GR, update RG1 at MIGO are flagged.
    Check Depot settings are flagged for Excise groups for Depot
    Check EI Create/23D is updated with flag mark for all Depot Excise Groups
    Check the assignement of Plant, Excise Registration and Excise Group
    Subcontracting
    Check the sub contracting attribute is maintained as per plant requirement
    Check the maintain movement type group is maitained with correct movement types
    Incoming Excise Invoice
    Check the assigned movement type for EI and Register Updates
    Maintain Rejection code to cancel the Excise Invoice
    Excise Regesiters
    Check SAP Script is assigned
    Number Ranges
    Incoming Excise Invoice
    Subcontracting Challan
    Thanks
    siva

  • Problem in Assembly Processing in Project System

    Hello All,
    My Client want to implement Assembly Processing. We have configured the system as per SAP Standard. we are testing this in Quality System along with SD & PP Modules. we have template which contain Material WBS Process WBS & Other Cost WBS But we are getting all cost of material and process cost on one Material WBS after Production order confirmation. How can we divide this cost separately for Material & Process WBS.
    As SAP Standard Process we maintained activities for different process also but when we tested this we are not clear about the use of these activities. We are not getting any cost or don't have any relation in any way for these activities.
    Please Help me about this Assembly Process.
    Thanks
    Warm Regards
    Sunil

    1. Create a Inquiry in VA11 --OK
    *2. Create Quaotation in VA21 wrf to Inquiry*--OK
    3. Create a Sales order in VA01, while creating sales order, as soon as we assign the material component in SD line item a pop will come for entering std wbs, std ntw, network profile. once we enter this at bottom we can see that scheduling is carried out. Note: if we define material/std wbs/std ntw in CN08 then pop will not come. Now check for errors and save the sales order, at bottom we can see that project order is created. Note: Project number is same as sales order no:---OK
    4. in Billing plan tab at item level we can see the milestones for new project.--In sales order i don't see any milestone or any type of setting. can you please tell me about this we are not able to execute milestone billing in our case.
    Ans to Query: For Milestone billing to work you need to do the following settings in SAPSD
    1.     Create Billing Plan in SD and assign the Billing Plan to Sales Document type you are using. Path: IMGSDBillingBilling Plan
    2.     In the above node , do settings for Define Billing Plan Types, Define And Assign Date Categories, Maintain Date Proposals For Billing Plan Types, Assign Billing Plan Types To Sales Document Types, Assign Billing Plan Types To Item Categories.
    By doing above settings you will get an additional tab u201CBilling Planu201D in Sales order where you can get the milestones generated for new project. For exiting project you can copy milestones to SD from project.
    If you want Billing Plan at sales document item level, assign the billing plan type in Item category.
    5. In Sales order we can see that billing lock is set against the milestones.---Not Found
    Ans to Query: By doing the above settings as in slno 4, you can see the billing block against the milestone*6.Now open the project in Cj20n and go to network we can see sales order no with line item no.*---OK
    7. Now verify the mile stones in the project.--Adding milestone but no effect in billing
    *Ans to Query : you can see that milestone no in Sales order and Project will be same. Note: Subject to in your standard network you should have milestones, so that we you create a sales order new milestones will get generated wrt to milestones in Std network. So when project is created you can see mile stones are also created.*8 .check the requirement list in MD04 against the Finished product we can see that requirement is generated againt project wrt to sales order.---No requirement is displayed .
    To generate the requirements. Check the settings in requirement class.
    9. Run MRP in MDBT/MD02/MD01, based on procurement type in MM , PR's and Pld order will generated. Note: ALL PR's and PLD Orders are account assigned to WBS.---When we execute this MRP this is not picking requirement from project. BOM created by CS01. if we assign material to activity than this MRP is picking requirement from project.
    10. Now do Pr>PO>GR>(ALL all accounted against project.--OK
    11. Convert Pld order to Production order> release the order> Goods issues against production order.--OK
    12. Confirm the Procution order wrt routing operation one by one in CO11N.--OK but we want sageregated cost for material cost and process cost to different WBS as we have material WBS and Process WBS.
    Ans to Query: This is not possible because in Assembly order processing single account assignment is only possible for the finished products, and for that finished product routing is also account assigned to the WBS assigned to Production order. So operation cost comes and sits in same WBS. If at all you want to track separately you can  transfer the actual cost for process to process WBS in tcode:KB11N
    Using KB11N tcode we can manual transfer cost from one WBS to another WBS.13. in cost element reports at projects we can see the cost breakup for all production activities as well as for material.--you mean CJI3 report 
    *Ans to query: Yes you can see in CJI3 report or in SALR_870135452 report also_*14. settle the production order.----where to settle this production order? and how?
    *Ans to Query: For assembly processing account assignment is u201CQu201D so automatically in production order we can see the settlement rule is set against the WBS. So the cost from production order is settled to WBS and subsequently from project to the respective receiver as per settlement rule in project.*
    15. conform all activities in Project.----OK CN25 or CJ20N
    In any of the above tcodes
    16. Do billing in SD as when when mile stone reaches to post actual revenues.----OK
    17. run RA in KKA2 and save the RA results--OK
    18. Run settlement in CJ88 ---Not using any settlement
    19. set the status of Project as Teco and Clsd.---OK
    Please let me know if you need more clarifications
    Regards
    kishore
    Edited by: Virendra Pal on Jun 1, 2011 11:53 AM
    Please do not use bold and underline text message short cuts etc - in future your posts will be removed
    Secondly all that you are mentioning is available in SAP Help or in the wiki

  • Implementation scenarios relating to SD

    Hi ,
    Can some one pl let me know the implementation scenarios relating to SD module..
    I am new to SD field...Could u please suggest me some important areas i should concentrate ..
    Thanks in anticipation.
    Regards
    Atahar

    Link: http://help.sap.com/bp_blv1500/BL_India/index.htm
    Preconfigured Scenario's for: Sales
    Here as you select the scenario & further go into it, you will ger the Business Process as well as configuration guide. These are very helpful & knowledgable information.
    Regards,
    Rajesh Banka
    Reward points if helpful.

  • Querries about Assembly Processing

    Hi,
    In our scenario we planned to trigger Project thru sales order.We did the necessary setting. In standard WBS I defined one header level WBS & below it four 2nd level WBS.but the Project which generated the SD document contains only one Header level WBS n Network Header only. Can I trigger the entire project hierarchy say of @ 100 WBS & 150 networks with material thru SD document by definining a single sales material ? if yes How ? Wht should be the process flow in scenarios of Assembly processing where i hv to generate project thru Sales document. also I want to run MRP for production ?
    Pl suggest.
    Rgds

    Hi,
    It seems that you have assigned only top level WBS to standard network. Goto CN02 enter your standard neywork and click on Total tab and assign other WBS to activities.
    You can create only 1 network for 1 line item, number of WBS can be more than 1 provided they are defined as standard WBS and assigned to standard network.
    Refer this link thouroghly:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/ab/5d4868733311d2b6600000e82d8bd1/frameset.htm
    Regards

  • Assembly processing-85

    Dear all,
    I am working on assembly processing . wht i have done i will tell you first.
    1) strategy 85 in material master
    2) Created sale order , automatic  generate project .
    Now could you plz tell me for further step like  In this scenario where the  stock and cost  will update ? In slae order or project? and how?
    plz gude me

    Hi ,
    In project u can hv option of No stock/non valuated stock /valuated stock.
    refer
    http://help.sap.com/saphelp_di46c2/helpdata/EN/d7/b8853488601e33e10000009b38f83b/frameset.htm
    cost booking is either thru GR/GI for material or service against WBS or activity or production order confirmations or direct finanacial postings for project.
    Assy processing has its advantage for auto generation of projects in line with the sales process due to this the further cost booking or stock update processes didnt affect.
    Rgds

  • Invoking ODI Scenario from a BPEL process - Resolved

    I new to Oracle products.
    I am exploring Oracle Data Integrator tool.
    I would like to call ODI scenario from a BPEL process.
    I created a scenario in ODI, I have SOA suite10.1.3.3 installed in my machine.
    In some portal I have read that, we need to deploy apache axis to Oracle App server and then deploy the ODI public web service to axis. This public web service facilitates us to call scenario from partner link.
    Following are my questions:
    1) I guess Oracle App server acts as webservice container too. Why should I use apache axis here?
    2)If axis must be used, please let me know how to deploy it to OAS.
    If axis is not required, please guide me how to deploy public web service to OAS.
    Thanks!!

    Hi:
    I have similar problem, when invoke ODI Scenario from a BPEL Process, the error in ODI Designer is:
    java.lang.NullPointerException
         at com.sunopsis.dwg.dbobj.SnpSession.a(SnpSession.java)
         at com.sunopsis.dwg.dbobj.SnpSession.y(SnpSession.java)
         at com.sunopsis.dwg.dbobj.SnpSession.treatSessionPreTrt(SnpSession.java)
         at com.sunopsis.dwg.dbobj.SnpSession.treatSession(SnpSession.java)
         at com.sunopsis.dwg.cmd.DwgCommandScenario.treatCommand(DwgCommandScenario.java)
         at com.sunopsis.dwg.cmd.DwgCommandBase.execute(DwgCommandBase.java)
         at com.sunopsis.dwg.cmd.e.i(e.java)
         at com.sunopsis.dwg.cmd.h.y(h.java)
         at com.sunopsis.dwg.cmd.e.run(e.java)
         at java.lang.Thread.run(Thread.java:595)
    In the BPEL Console the result is OK and process complete, but in the INVOKE scenario send message:
    <messages><ODI_REQUEST><part xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" name="part1"><invokeScenarioRequest xmlns="xmlns.oracle.com/odi/OdiInvoke/">
    *<RepositoryConnection xmlns=""*
    <JdbcDriver>oracle.jdbc.driver.OracleDriver</JdbcDriver>
    <JdbcUrl>jdbc:oracle:thin:@192.168.1.109:1521:ORCL</JdbcUrl>
    <JdbcUser>dimaster</JdbcUser>
    <JdbcPassword>sabr0sa</JdbcPassword>
    <OdiUser>SUPERVISOR</OdiUser>
    <OdiPassword>SUNOPSIS</OdiPassword>
    <WorkRepository>TESTWORKREP1</WorkRepository>
    </RepositoryConnection>
    *<Command xmlns="">*
    <ScenName>P_TRASPASOSOP09</ScenName>
    <ScenVersion>2</ScenVersion>
    <Context>Global</Context>
    <LogLevel>5</LogLevel>
    <SyncMode>0</SyncMode>
    <SessionName/>
    <Keywords/>
    <Variables>
    <Name/>
    <Value xmlns:ns1="http://xmlns.oracle.com/Recepcion">
    <ns1:Escenario>P_TRASPASOSOP09</ns1:Escenario>
    <ns1:Version>2</ns1:Version>
    <ns1:Contexto>Global</ns1:Contexto>
    <ns1:ID>1</ns1:ID>
    <ns1:NivelLogeo>5</ns1:NivelLogeo>
    </Value>
    </Variables>
    </Command>
    *<Agent xmlns="">*
    <Host>192.168.1.109</Host>
    <Port>20910</Port>
    </Agent>
    </invokeScenarioRequest>
    </part></ODI_REQUEST><ODI_RESPONSE><part xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" name="part1"><odi:invokeScenarioResponse xmlns:odi="xmlns.oracle.com/odi/OdiInvoke/">
    <odi:CommandResultType>
    <odi:Ok>true</odi:Ok>
    <odi:SessionNumber>445000</odi:SessionNumber>
    </odi:CommandResultType>
    </odi:invokeScenarioResponse>
    </part></ODI_RESPONSE></messages>

  • Error coming while creating sales order Thru' Assembly processing.u00A0

    Hi,
    I am working on assembly processing. when i am creating sales order if order qty when i am giving more then 999 means if i given 1000 kg it giving an error like the exection factor in the network is reduced to 1000 to 1 kg and confimed as 1 kg only and system is giving msg *Change not accepted (execution factor in network too large)* where i have tomodify this .
    In above context i would like to brief you that i can't extend quantity more then 999(Three alfabet).
    All suggestions will be apreciated with good points.
    Regards,
    Vishal Kr. Sharma

    Hi vishal
    Check in MMR the  following settings  :
    1) Base unit of measure
    2) sales unit
    3) Strategy group maintained  in MMR ->MRP 3 view
    4) Availability check(sales/general plant view in MMR ) and MRP type (MRP1 view in MMR)  has been maintained or not.
    5) Check the fields maintained in the MRP 3 view.
    Regards
    Srinath

  • Ps assembly processing:WBS have not be created when saving the sales order

    In the ps assembly processing, I want to generate a network when I create a sales order.  So I did the following steps:
    1-Use the TCODE cj91 to create a standard WBS "E-000007.1".
    2-Use the TCODE cn01 to create a standard network "10000000" and assign the standard WBS "E-000007.1" to it.
    3-Use the TCODE cn08 to config the Network Parameters from Sales Order like below:
    Material number : 600000-000000-0009
    Order Type      : Z301
    Std network     : 10000000
    Class Type      : 020
    Network Profile : Z0001
    MRP Controller  : 001
    Std WBS element : E-000007.1
    4-Use the TCODE va01 to create a sales order and add an item with the material "600000-000000-0009" and save.
        When the SAP R/3 System is saving the sales order, a WBS ought to be created u2013 based on the assignment of the standard network to the standard project.But I could not found the WBS.I thought I have do all of steps and could not found the reason.
       So I need the experts give me some useful advice and reference to resolve the problem.Thank you.
    Regards
    Yoda

    Hi,
    Maintain strategy group in material master MRP tab....
    If problem still persist then check is there any credit block to that customer...if it is release it in VKM3....
    Once you release it will create automatically.
    Regards

  • Workflow tasks related to error processing when u201Cinvoices received via EDI"

    Hi all,
    Please tell me the process like how an workflow tasks related to error processing when u201Cinvoices received via EDI".
    Give me in details the inform.
    Thanks in advance
    Chakri

    Hi Sven,
    Please implement SAP Note: 1321676 in your backend system to solve the current issue.
    But later you will have to implement SAP Note: 1380788 also in your backend system to solve some other issues.
    Regards,
    Binson

  • Error in Assembly processing

    In assembly processing, while i creating a sales order the following error is occur.
    *Error when processing network
    Message no:V1380
    Diagnosis
    A technical error has occured.On calling up the assembly interface exception 2 was triggered.The exceptions have the following meanings,
    1 = External Block
    2 = General Error
    3 = Insufficient data for the interface
    4 = Order wasnot found
    5 = Update has been rejected
    6 = Final document number for network is not issued
    Procedure:
    Inform your system administrator
    Pleas anybody give the solution.
    Thanks & Regards
    Vijay

    Hi Veera,
    did u follow these pre-requisites:
    1. Std. Network (which is assigned to Std. WBS)
    2. Network parameters from sales order (CN08)
    3. In Material Master maintain SD views and MRP Views
    bye
    raj

  • Relation between Inventory Process keys and movement types

    Dear All,
    Is there any way to find the relation between Inventory process keys (which is in SBIW-> Settings for Application specific data sources(PI) -->Logistics -->Settings for IBU Retail / CP --> Transaction key maintenance for SAP BW) and movement types .
    Thanks in advance...
    Regards,
    Raju

    Hi,
    Please read the note below.
    Note 353042 - Howto: Activate transaction key (PROCESSKEY)
    It has something for you ....
    The process key (0PROCESSKEY and 0BWAPPLNM) of the InfoSources has not been filled. As a result, no key figures are updated because of the update routine of the participating InfoCube and along with it no records are inserted into the InfoCube. In each update routine, the system checks the content of the PROCESSKEY. If this field has no contents, then no data is written into the InfoCube because of the IF condition in the update rules.
    Solution
    So that you can work in the above mentioned InfoSources, you MUST activate the determination of the process key. This is done with the help of Transaction MCB_ which you can find in the OLTP IMG for BW (Transaction SBIW) in your attached R/3 source system.
    Here you can choose your industry sector. 'Standard' and 'Consumer products' are for R/3 standard customers, whereas 'Retail' is intended for customers with R/3 Retail only.
    You can display the characteristics of the process key (R/3 field BWVORG, BW field 0PROCESSKEY) by using Transaction MCB0.
    If you have already set up historical data (for example for testing purposes) by using the setup transactions (Statistical Setup Programs) (for example: Purchasing: Tx OLI3BW, material movements: OLI1BW) into the provided setup tables (for example: MC02M_0SCLSETUP, MC03BF0SETUP), you unfortunately have to delete this data (Tx LBWG). After you have chosen the industry sector by using  MCB_, perform the setup again, so that the system fills a valid transaction key for each data record generated. Then load this data into your connected BW by using 'Full update' or 'Initialization of the delta process'. Check, whether the system updates data into the involved InfoCubes now.
    If all this is not successful, please see Note 315880, and set the application indicator 'BW' to active using Transaction 'BF11'.
    Hope this helps.
    Raj

  • Configurable Networks in Assembly Processing

    Hi Gurus,
    I have implemented Assembly Processing with configurable networks. I am facing an issue here.
    The requirment is to capture the Delivery time ( Z field) from quotation and apply a  formula and calculate the normal duration of the activites of the network created on saving the quotation.
    I have used Varaiant configuration for the same
    I created following characterstics
    1. PS_DEL_TIME_TEST - To capture the delivery time from quotation line item
    Table Name      VBAP
    Field Name      ZZ_DELTIME
    2. PS_DURATION - To fill the normal duration of activity
    Table Name      AFVGD
    Field Name      DAUNO
    3. PS_DIST_DUR_TEST- User field of activity
    Table Name      AFVGD
    Field Name      USR04
    The Dependency that is used is
    000010     $SELF.PS_DURATION = ($PARENT.PS_DEL_TIME_Test * 30)*
    000020     (MDATA PS_DIST_DUR_TEST/100)
    Now the problem is that the Delivery time is not captured in quotation level but is not copied to the characterstic value assignment to the network.
    Can some one please help me with this?
    BR

    hi,
    refer the below wiki about assembly processing and assignment of configured network.
    http://wiki.sdn.sap.com/wiki/display/PLM/AssemblyProcessinProjectSystems
    http://wiki.sdn.sap.com/wiki/display/PLM/ADemoonConfigurableNetwork
    regards,
    Edited by: NAG on Jul 21, 2010 1:28 PM

  • Querry in Assembly Processing

    Hi,
    I have created standard WBS E-9818.Using this WBS, I have created standard Network E-9818.Then I have created material M-9818 & made assignment in CN08.
    After this when I try to create sales order using order type PS1, it is not creating sales order with no. 9818. But it is creating sales order with no. 12117.Also it creates project with no. E-2117.Ideally speaking it should create project with no.
    E-9818.
    Please let me know what could be the problem?
    Any pointers on this will be highly appreciated.Useful answers will be rewarded with good points.
    Regards
    Tushar

    Hi Tushar,
    What the System does is correct.U have created std WBS and assigned them to the activities in STD network.So when ever the Sales order is created,it can create various order types thru assembly processing, since network is an order type 20,it creates std network first thru which it picks up the std WBS to create operative WBS.
    So whatever may be your STD wbs id , as soon as a sales order is created ,a project will be created with the last four digits of the sales order as the project id and similarly for the WBS element.
    thanx,
    reward points if usefull.

Maybe you are looking for

  • How do I transfer from iphone 4 to 4s while still leaving gaming apps on the iphone 4?

    I would like to transfer all everything from my iphone 4 to a 4s while still leaving the gaming apps on the orginial iphone 4.  My plan is to tranfer my phone number to the iphone 4s so that my son can use the iphone 4 as a gaming device only.

  • How do I reducing the amount of joining when using one-to-one mappings?

    Examine the following example; class Person Address address; String firstName, lastName; class Address Long addressId; String state, city, zip; Assume that both of these classes are mapped to tables in a database. Attributes such as Staff's name and

  • Slow nfs read/write from solaris 8 to solaris 10

    there is a bug:4852269 which sums up my problem well. I have a solaris 10 sparc with a big nfs shared raid5, and most of the other suns I have run solaris 8. the access time from sol8 to sol10 is awfull. Is there some config/patch I can apply to the

  • JPG is an unrecognized file format?!?! ***?

    I tried to download pics from my Kodak Z812 IS digital camera like have done no less than thirty times without any problems, and for some reason, now iPhoto says there was an error importing the pics because they are an unrecognized file format. They

  • Property panel is grayed out

    I am in the early stages of learning DW CS5. I'm learning how to create a new CSS rule/class. But after I've set up my new rule/class in the CSS Panel, I go to the Property Panel to enable the new rule, but it is grayed out. It is inactive. I can't d