Schedule line date in Sale order for backward sched.

Dear Experts,
In my MTO Scenario, I want to Use Backward Scheduling, so as any change in Schedule line dates in Sale order shall take effect at least in planned order Stage, i.e in output of MRP,
But not happening so..
I  have customized OPU5 and checked OPU3 as well,
Please suggest...
Regards
Raghu

HI Mario,
Thanks for reply,
I have not worked in this strategy but will try,
What i found was, in Planned orders detailed scheduling tab, the Scheduling type appeares to be Forward, but when i convert it to Production order it shows backward scheduling.
This duel behavior is difficult to understand.
Regards
Raghu

Similar Messages

  • Problem in Schedule line data in sales order creation

    Hi,
    I am using the BAPI_SALESORDER_CREATEFROMDAT2 to transfer the sales order from one system to other. My problem is that the Schedule line data is not created in the new system and because of that order quantity is not appearing in the item level data.
    I have populated both order_schedules_in and order_schedules_inx... 
    but still its not getting transfered.
    Somebody help me..
    Thanks & Regards,
    Martin

    HI Martin
    Please check that you are using the right Delivery Date. Am not sure, but might be problem if we try to pass the delivery date in past... Please check on the same.
    Also, if you can post your code that can help for better advices.
    <u><b>Additional Info:</b></u>
    Below are the parameters that you have to pass to change the schedule lines:
    SALESDOCUMENT - Sales Document Number
    ORDER_HEADER_INX
    -- UPDATEFLAG = 'U'
    SCHEDULE_LINES
    --ITM_NUMBER
      SCHED_LINE
      REQ_DATE
      REQ_QTY
    SCHEDULE_LINESX
    --ITM_NUMBER
      SCHED_LINE
      UPDATEFLAG = 'U'
      REQ_DATE = 'X'
      REQ_QTY = 'X'
    Kind Regards
    Eswar

  • Want to automate process of adding schedule lines to a sales order

    Hi Experts,
    I want to change the schedule line data in sales order.So I Found a BAPI_SALESORDER_CHANGE.Is it ok if I go with this BAPI or is there some other way?
    Thanks in advance!!!!!!!!!!

    HI
    Yes it's ok, another solution can be to create a BDC program, but it's better and easier to use that BAPI
    Max

  • Adding Schedule lines to a sales order

    Friends,
      We have a requirement to clear the old un-delivered scheduled lines from a sales order and then add new schedule lines from a EXCEL file.  We were able to clear the old by putting in a new location.  Then, when we go to enter the new schedule lines, it clears the location, marks the Fixed date and Qty, and enters the delivery dates and confirmed quantities.  We tried using BAPI_SALESORDER_CHANGE, but the schedule_lines table only has the required quantity so when used it increases the order quantity, which is not good.  Is there any Function module that we can call to insert new schedule lines without increasing the order quantity other than using a BDC?  Thanks!

    Pasted below is the BAPI documentation for this parameter.
    "Check Table for Schedule Lines
    Description
    This parameter completes the following two tasks:
    Controls processing functions with the value in the UPDATEFLAG field (change indicator).
    The following entries are available:
    ' ':   Create new schedule lines
    I:     Create new schedule lines
    U:     Change existing schedule lines
    D:     Delete existing schedule lines
    Controls the field entry with check fields
    If the UPDATEFLAG field has been activated, the system only copies those fields to the data parameter that have been filled with 'X'."
    Nabheet

  • Schedule Delivery Date in Sale Order

    Dear All,
    I have an order on 03.11.2009 (today) and its last delivery date is 15.11.2009. It means that I have to deliver the complete order on or before 15.11.2009.
    So where can I put this date in Sales Order?
    Regards,
    Vishal

    Hi Vishal,
    Your Last Delivery Date can be entered in the "Requested Delivery Date" field in the sales order.
    By doing so, the system will give us a confirmation that whether the delivery can be made possible on the Requested Delivery Date or NOT (The status can be seen by going in to the Schedule Line Level of your line item).
    The system also gives us the NEXT POSSIBLE DELIVERY DATE with the confirmed  Quantity as a Second Line item in the Schedule line level.
    The System considers mainly the Material Available Date to come to a conclusion on the Delivery Date of the goods. Also, there are other activities (Loading Time, Transporation Planning Time etc) for which some time will take and that also need to be considered (The same can be seen by going in to the Schedule Line Level of your line item and then click the Shipping button).
    Your Scenario: In your case, the delivery can happen ON OR BEFORE the Last Delivery Date.
    So for that follow the steps:
    Step 1: Put the Last Deliv Date in to the "Requested Deliv Date" field in Sales Order.
    Step 2: After enetering the other necessary details in the sales order then Save it. Now go the Schedule Line level of your line item and look for the Confirmation of the Delivery Quantity on the Requested Delivery Date.
    If Yes: Then its your wish that you can Prepond the Delivery Date by giving the required Delivery date during your delivery document creation.
    If No:
    Then you have look for the Next Possible date. OR Make sure that you can manage all your other activities like Loading, Transporation Planning etc. in 10 - 12 days time and make your material Availabilty today and do the delivery.
    Reagrds

  • Changing proposed delivery date in sales order for one specific sales org

    Hi All,
    I want to change proposed delivery date in sales order automatically for one specific sales org only without changing lead time in VOV8.
    For that can I use MV45AFZZ. But it is asking access key to make changes. Is there any other user exit for the same. And how does exactly change it.
    Thanks in advanced.
    Points will be awarded.
    Regards,

    EXIT_SAPFV45E_001 has nothing to do with this - it is meant to update the purchase order from a sales order. It might not even be triggered if the sales order has no link to a purchase order.
    USEREXIT_SAVE_DOCUMENT is not really good for this either, because the delivery date has to be changed before that. If memory serves, it also influences the schedule lines and probably the ATP check and such. I would strongly advise against it. One of the other routines in MV45AFZZ should do just fine, USEREXIT_MOVE_FIELD_TO_VBAK for example.

  • Delivery date in Sales Order for Make to Order Scenario

    Hello,
    We are creating Sales order for MTO ... In that our requirement is to get the delivery date based on Production planning and not from RLT. ie we have configured RLT as 36 days, system calculates delivery date as 36 days from the date of order what ever be the order quantity but considering our plant capacity  this is not possible. In our Production planning we allocate certain numbers per week. so when we give 100 nos order it plans as per the allocation if we see through MD73 it will give clear picture but in our sales order it shows delivery possible date as 36 days from date of PO. How to correct this.. it should calculate from the date of beginning of the production process.
    Can any one help in finding solution for this
    Thanks in Advance

    Hello,
    We are creating Sales order for MTO ... In that our requirement is to get the delivery date based on Production planning and not from RLT. ie we have configured RLT as 36 days, system calculates delivery date as 36 days from the date of order what ever be the order quantity but considering our plant capacity  this is not possible. In our Production planning we allocate certain numbers per week. so when we give 100 nos order it plans as per the allocation if we see through MD73 it will give clear picture but in our sales order it shows delivery possible date as 36 days from date of PO. How to correct this.. it should calculate from the date of beginning of the production process.
    Can any one help in finding solution for this
    Thanks in Advance

  • Requested delivery date in Sales order for internally produced products

    Dear All,
    I'm searching for a solution for the following case:
    Customer places a sales order for inhouse produced material, there is no stock for that product and no planned receipts, so ATP check does not confirm anything.
    A sales person does not know when product can be produced since thats depended on components availability on stock or confirmed dates of future receipts of needed components.
    So at the stage when a sales person inputs a sales order he should somehow calculate the requested delivery date.
    He can create a production order (without saving it) for requested good and check components availability inside production order, and based on that figure out a valid date, but thats of course is not convenient at all.
    He will need to go through all confirmed dates in ATP (in production order) and figure out the latest date when the latest component is available. Then he will get a start date for production order and as a result a date when requested product will be on stock.
    All these activities which could be a workaround are not so convenient for sales persons.
    I'm curious, is there any official SAP way how to calculate a day for above described case when product will be produced (like simulation of overall chain) and of course much better to have it in background...
    Your ideas and suggestions are very much appreciated.
    Best Regards,
    Andrey

    Hi Andrey
    I feel this is more of process issue rather than config problem. Whatever market and productline your client is operating in ,there will be some analysis available regarding the time required to replenish a material from the date requirement is generated and this is even if you don't have SAP.
    Generally companies have the approximate time entered in  material master  either in GR processing When material is procured  or in planned delivery time When  produced in house.
    So you can still maintain approximate time there and configure availability check to check cumulated confirmed quantities.
    change VOV8 to propose the delivery date. this way u get delivery proposal for availability check and then still u can block the delivery as Mr.Sai ; has suggested , OR  have your own checks incorporated in user exits in  RV03VFZZ.
    The requirement transfer can be blocked and you can use  user status  or  combination of user status and user exit to control the requirement transfer.
    For customer specific manufacturing of sales order stock also ,you need to verify strategy group and planning strategy .that should solve problems rather than changing config. into sales.
    So i would suggest that have a second look  at PP ,MRP config and material  master data and then check for changes on SD side. also try using delivery proposal.
    Regards
    Mandar

  • Schedule lines & TOR in Sales order

    Hai Experts,
    ( in Sales order - VA01 ) How Schedule lines is related with TOR.
    Kindly explain me in detail
    Regards,
    Geetha

    Hi Geetha
    To deliver an Item you need to have a schedule line.
    In the Sales order, an Item can have one or more schedule line, but to be delivered atleast one schedule line must be there.
    During Sales order processing a 'requirement transfer" is sent to the "Materials planning " department for the schedule line ,which a communication between SD and MM department (SD-MM interfac).
    From this "Transfer of Requirement", Materials Planning comes to know,How much quantity of which material SD needs to deliver and on which date.
    Accordingly, they may go for Production or Procurement as applicable to make the goods available for SD to meet the schedule line.
    Schedule line contains the information about Delivery date, delivery quantity aswell as information about requirement transfer and goods movement.Schedule line is controlled by "Schedule line category".
    So, in the Schedule line category we configure, whether Tranfer of Requirement is relevant or not, beacuse all schedule lines are not relevant for Transfer of Requirement.
    For example,
    when we create a Standard order for a normal material, it has got a schedule line and its schedule line is relevant for "Requirement Transfer".
    But, when our faulty goods comes back from the customer, we create a Return order, which also has a schedule line so that the goods will come in, but this schedule line is not relevant for "Requirement Transfer".
    So, if you will go for the "Schedule line category in Return" (DN), you will find the Requirement transfer field is blank, beacuse when my faulty goods are coming back, why should I put a requirement to Materials planning.It is not relevant.
    I hope now you are clear about the relation of Schedule line and Requirement transfer.

  • Schedule lines combined in sales order

    Dear All,
    We have a sales order item with say 2 schedule lines as below
    Date                  Order Qty      Rounded Qty     Conf. Qty     Delivered Qty
    05.10.2010        60                  60                      0                  0
    18.11.2010        0                    0                        60                10
    Now, if we want to unconfirm the undelivered quantity and to do this we make the order qty = delivered qty and then change back the order qty to original qty, all this with ATP check off.
    We expect it to be ...
    Date                  Order Qty      Rounded Qty     Conf. Qty     Delivered Qty
    05.10.2010        60                  60                      0                  0
    18.11.2010        0                    0                        10                10
    It works but in some cases Sometimes, we notice that SAP moves old delivered  lines to first schedule line. Hence, we loose the schedule line information.
    Date                  Order Qty      Rounded Qty     Conf. Qty     Delivered Qty
    05.10.2010        60                  60                      10                  10
    Does anyone have an idea why SAP does this and how can we avoid this. This is really important for us, any help will be greatly appreciated.
    If anyone could also suggest a better way to unconfirm undelivered qty from schedule lines also.
    Best Regards,

    You can try to use delivery block at header level. Copy the delivery block credit limit and create a Z-block(t.code OVLS The path is SPRO->Logistics execution->shipping->deliveries->define reasons for blocking in shipping). When this block is assigned the confirmed quantities will be removed. Once  business approves, the block can be removed so that the remaining quantity will be confirmed. Just test first using the credit limit block in test system and if the results are OK, then you can create a new block.
    PS: Please close threads once those are answered. There are old threads still with open status and you action to close those are appreciated.
    Regards,

  • Schedule lines in a sales order

    Hi All,
    Its a very rare case I hoipe.
    Some times i see the deliver date in schedule lines tab in a sales order as 08.01.0001. Iam very much surprised about year 0001.
    Have you ever faced such issue.
    kindly provide me the root cause and solution
    Thanks and regards,
    satyaprasad

    Hi Satya
    please speak to your Basis people. The date he is maintaing for the system is by mistaken something else.I hope once the SAP system date / Client date is changed to today's date it will get rectified.
    Thanks
    Sushant

  • Schedule Line Issue in Sales order...

    Hello,
    While creating sales order in schedule line two schedule lines are getting created. fisrt line the date of creation of the sales order with out confirm quantity and the second line which is two days later with confirm quantity. When material is available then why schedule line is showing confirm quantity in later days. How to rectify this? please let me know the all possibilities.
    David.

    Eventhough material is available today , it doesnt means that the material can be delivered by today itself. There are other dates also which will affect the delivery date like Transportation planning, availability of truckts to send the materials, based on these transportation plannign and transportation leadtimes, the Goods Issue date and thus the final delivery date will be decided.
    If you want to finetune this functionality
    1. If your route determination is enabled, then you have to configure your transportation lead time for the relevant route.
    2. If routes are not enabled, then you have to define these things in shipping point in logistics execution
    Hope this helps you to solve the problem

  • Is there any method to stop rescheduling of the PO Need By date from ATP if there is any holiday specified in shipping calender. The requirement is to update the schedule ship date on Sales Order but the lead time of  Purchase Order should not increase

    We are currently not able to manage schedule ship date proposed by ATP when our warehouse is closed. For example , we would like that ATP doesn't propose any schedule ship date for the first of May , which is a non working day in France. The constraint is that we don't want our purchase need by date to be impacted by the process.
    I tried to closed one day in FR1 calendar and, after testing with order management, it appears that ATP didn't propose the closed day, so that's fine, but, our purchase order lead time was increased of 1 day and this is not what we expected.
    Can you help us to find the right process.
    Thanks

    Hi Sandeep,
    when we try to Rescheduled out the PO and the request is errored out the with the error:-
    Start of log messages from FND_FILE
    reschedule fails
    old date in planner workbench: 19-MAY-11
    new date: 07-JUN-11
    header: 417474
    line: 605652
    po number: 2049031859
    shipment no: 1
    The need by date/promised date in the source instance is not the same as the need by date/promised date in the destination instance.
    In the source instance,
    The need by date is 19-MAY-11, and the promised date is 19-MAY-11
    End of log messages from FND_FILE
    ---------------------------------------------------------------------------

  • Delivery schedule line number in sales order is not populated in production

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    Will reward points.
    Regards
    Kumaraguru

    Hi Kumar,
    Some changes done in your PRD server.If yes then contact abap consultant regarding the same.
    Because these type of problem comes when you do transport or changes done in the system.
    Regards,
    Anil

  • Delivery schedule line number in sales order is not populated  in productio

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    Regards
    Kumaraguru

    Hi Kumar,
    Some changes done in your PRD server.If yes then contact abap consultant regarding the same.
    Because these type of problem comes when you do transport or changes done in the system.
    Regards,
    Anil

Maybe you are looking for

  • Hard Drive Replacement

    Hard Drive Replacement: I need to replace, and hopefully, upgrade a hard drive in a HP Pavilion dv4-1318tu laptop.  Can someone suggest a larger and hopefully faster drive? Kindly tell the specifications of HDD which is suitable to my laptop. 

  • Bar code Generation in ABAP report

    Hi, Can anyone help me on how to generate bar code in ABAP report output. My exact requirement in the exisiting 'Z' report,I need to generate Bar code for Sales order which is displaying in report output.Buisness will scan and they will use for furth

  • Kindly give authorization object for mrp type in material master

    Hi friends, Kind tell me what is the authorization object for MRP type in material master. Your help is considered more important. thanks in advance willaims

  • How to get sponsorship from Apple?

    Does anyone know how to submit the sponsorship proposal to Apple?

  • .11n adapters for desktops

    Hi, Been searching but can't find any recommendations or suitable .11n NICs for Desktops. The CCX approved list does not appear to have any of these listed. Have a client that wants to go fully wireless on a group of 30+ PCs from different brands. I'