Schedule line error ,urgent,urgent

dea sap expert:
I have schedule line error , please help
I have part 9173191-04.
There is schedule line as below
10th Feb 72
10th Feb 72
17th Feb 172
On 23th Feb , the stock is zero.
Due to our factory want to GR early than 17th Feb.
Material planner change lastest schedule date from 17th to 10th .
After she change ,  schedule line as below
10th Feb 72
10th Feb 72
10th Feb 172
17th Feb 12
On 23th Feb , the stock is 12 PC.
Could you help to explain , why it generate another 12 PC .
And make there are 12PC we will never be used it.
Please help me on it .
Thanks so much.
Below is the material master information .
MRP Type             P1     
Reorder Point        0                    Planning time fence  10
Planning cycle       Z05 (Friday )
Lot size             SB
Rounding value       72
Procurement type     F                    Batch entry
Special procurement                       Prod. stor. location AS03
Quota arr. usage     3                    Default supply area
Backflush            1                    Storage loc. for EP  XT06
JIT delivery sched.                       Stock det. grp       REM
In-house production  0   days             Planned Deliv. Time  0   days
GR Processing Time   0   days             Planning calendar    Z05(Friday )
SchedMargin key      LOC
Safety Stock         0                    Service level (%)    97.0
Min safety stock     0                    Coverage profile
Safety time ind.     2                    Safety time/act.cov. 7  days
STime period profile

Hi,
>Wish to know when & why does the schedule line Exist tab in sales order trigger.
Schedule line is a place where you can define different delivery dates for a single line item.
Let's say, you have one line item for quantity 1000. Now if your production department and planning department saying they can deliver it in a weekly basis.(Say 250 for each week)
In that case you have 2 options.
One is to create 4 separate line items instead of original line item with different delivery dates and relevant quantities.
You can create delivery from VL01N or VL10C here for relevant line item.
Else
have 4 different schedule lines with delivery dates and relevant quantities
You can do delivery from VL10E for this case for relevant schedule line.
Same is happening when ATP is triggered, where system suggest different delivery dates as different schedule lines.
So it's based on ATP or it can be your decision as well.
>when I try to do the delivery I get an error u201CNo schedule lines due for delivery up to the selected date u201D.
This can happen for many reasons.
1 - Because the "Selection Date" you have given in the VL01N screen is not equal or greater than the "delivery date" you have maintained in the schedule lines.
Always make sure below rule.
"Selection Date" of the VL01N > "delivery date" you have maintained in the schedule lines
Therefore change the date in the "Selection Date"  of the VL01N to "delivery date" you have maintained in the schedule line or forward date and try.
2 - You don't have confirmed stock.
Check your schedule line tab for "Confirmed quantity" column, if you don't have a value there, this error comes. This happens when you haven't done ATP.
Best regards,
Anupa

Similar Messages

  • Schedule line error

    Hello sir
    i am facing the error in schedule line agreements
    As discussed with you we are maintaining the schedules in JIT for the making the ASN delivery. But today we are not able to make delivery, but the schedule has been maintained .  Pl let me know how to resolve this issue.
    date also available , material also available
    message no VL248
    Regard ,
    Bhaskar.k
    Edited by: Lakshmipathi on Feb 10, 2012 6:38 PM
    Thread Locked - Reason Duplicate Post

    Hi,
    >Wish to know when & why does the schedule line Exist tab in sales order trigger.
    Schedule line is a place where you can define different delivery dates for a single line item.
    Let's say, you have one line item for quantity 1000. Now if your production department and planning department saying they can deliver it in a weekly basis.(Say 250 for each week)
    In that case you have 2 options.
    One is to create 4 separate line items instead of original line item with different delivery dates and relevant quantities.
    You can create delivery from VL01N or VL10C here for relevant line item.
    Else
    have 4 different schedule lines with delivery dates and relevant quantities
    You can do delivery from VL10E for this case for relevant schedule line.
    Same is happening when ATP is triggered, where system suggest different delivery dates as different schedule lines.
    So it's based on ATP or it can be your decision as well.
    >when I try to do the delivery I get an error u201CNo schedule lines due for delivery up to the selected date u201D.
    This can happen for many reasons.
    1 - Because the "Selection Date" you have given in the VL01N screen is not equal or greater than the "delivery date" you have maintained in the schedule lines.
    Always make sure below rule.
    "Selection Date" of the VL01N > "delivery date" you have maintained in the schedule lines
    Therefore change the date in the "Selection Date"  of the VL01N to "delivery date" you have maintained in the schedule line or forward date and try.
    2 - You don't have confirmed stock.
    Check your schedule line tab for "Confirmed quantity" column, if you don't have a value there, this error comes. This happens when you haven't done ATP.
    Best regards,
    Anupa

  • Schedule Line Error in MD04

    Hi All,
    I am having the following scenario in my SAP system.  We have 2 Sales Orders ( Requested Delivery Date ) in the past where we would like to cancel ( in agreement with the Customer ).  We then went to VA02 to change the Scheduline Category from CP to CN.  However, when we run MD04, we still see the requirement for that particular schedule line.  I have tried to deleted it or change the requested delivery date of this line item, but the requirement still exist in MD04.  Does anybody know other places where I have to set in the Sales Order in order to make it go away in MD04.
    Thanks in advance.

    Hi,
    You might need to use program: SDRQCR21 to delete those faulty SO which appear in MD04. You may go to tcode:SA38 to run the program.
    You may refer to my printscreen below for better understanding if you wish to.
    Thanks.
    Edited by: Lakshmipathi on Oct 26, 2010 8:57 AM
    You have already been warned in the past not to paste your blogs in this forum and still you ignored our requests.  Your name has been referred to the concerned forum panel for their action
    Edited by: Lakshmipathi on Oct 26, 2010 3:45 PM

  • Erroneous link between R/3 Schedule Lines and CRM Schedule Line

    Hi everybody,
    I am analyzing the best approach to fix a duplicate schedule line issue in CRM. The documents are modified from R/3 by means of an IDOC (ORDERS05).
    First of all, let me explain the process.
    1.- Document is first created in CRM
    2.- Document is updated from CRM in R/3 (Using middleware)
    3.- In R/3, a customer program (Z), does a lot of calculations to the order (rejection, item splitting, Qty changes, creation of new Items, etc) and once its done, it populates the IDOC and sends the information to CRM (ORDERS05).
    4.- CRM receives the IDOC, modifies the order.
    5.- Document is update from CRM in R/3 9Using middleware)
    The Z program, DOES NOT modify the database in R/3, it lets the process to be executed and also lets CRM to do this job.
    I had to make several modifications to the XIF module, in order to allow many of those changes to be valid in CRM (i.e., A rejected ITEM is changed to be valid and it's Qty changed. CRM does not allow this to be done in one step, since the qty is "greyed" for no changes).
    Edited by: Rob Burbank on Feb 17, 2010 5:34 PM

    My issue is this.
    The worst thing that happened, is the fact there is key fields in R/3 -> CRM, to link the schedule lines, since R/3 Uses the regular key fields in the T. table, CRM uses the GUID for the sched. lines.
    After a OSS msg and many goes and comes, I had the suggestion from SAP to change from ORDERS05 Idoc into CRMXIF_ORDER_SAVE_M01 idoc, since ORDERS05 is not supported by CRM (however the Idoc is in the system).
    I am not sure that is the best solution, in fact I do not believe that is a solution at all. CRMXIF_ORDER_SAVE_M01 does not exist in R/3 and even if somehow I do all the effort to create it in R/3, R/3 still does not have the schedule line GUID to properly point to the right record.
    What I did to override this error, was to include inside the XIF module the CRM_APO_SALES_SELECT_GUIDS, CRM_ORDER_READ and CRM_ORDER_CONVERT_DOCNUMBER Functions to get all the sched lines for the specific orders in the guid form. However this solution does not work OK, since sometimes the CRM system is not able to properly return the correct GUID values and this leads to the duplicate schedule lines error.
    If somebody has ever deal with a situation like this, I will appreciate if could share its point of view or even better, share the solution used.
    As an extra comment, modifying the Z program to update the database and let middleware to do the job for us, is ou of the qustion at this momento.
    Thank you for your time and help.
    Sincerely
    Meuli
    Moderator message - Welcome to SCN.
    There is a 2,500 character posting limit, but in this case I split it in two.

  • Delivery deleted but schedule line status shows as fully delivered - Urgent

    Hi,
    I deleted the delivery related to the order but teh schedule line status says its fully delivered....
    Is thr a way to refresh the schedule line so it shows the correct status? Urgent PLs.,
    Thanks
    Keshi

    Thanks fro the reply.. But i tried this but the inconsistency is still there? any other report i cn try
    Thanks
    Keshi

  • Bursting Scheduling Error - Urgent

    Hi,
    Can anyone help? I have scheduled a report for bursting and see the following errors in schedule history:
    Error!! Can not find the delivery details for the delivery Id :Commercial Data Ltd
    When I check the bursting query this delivery id(Commercial Data Ltd) does exist and there is an email address.
    Can anyone help understanding why this error appears, is the email address invalid?
    Also where can I locate the log file on the server containing the details of the delivery:
    Error!! Could not deliver the output for Delivery channel:EMAIL . Please check the Log for error details..
    Thanks
    Edited by: sliderrules on 07-Oct-2010 02:03

    Hi,
    Can anyone confirm if the email address needs to be valid for the bursting schedule to process successfully, I see these errors in the schedule history:
    Delivery Key ASSET LTD
    Delivery Type
    Status Failed
    System Message Error!! Can not find the delivery details for the delivery Id :ASSET LTD
    The delivery key does exist and there is an email address?

  • Double shedule lines confirmed-Urgent

    Hi
    Today for one of the order two shedule lines are confirmed.
    Like below in SO-Item-Shedule lines
    Delivery date    ord qty  rounded qty confirmed qty
    03/19/2007       50        50                50
    03/19/2007       0        0                   50
    Any idea for why duplicate shedule lines are confirmed here any OSS notes for this?
    Urgent help needed.
    Cio
    Shankar124

    Hi,
    I guess the only way to figure out specifically what is happening behind the scenes is debugging. ABAP team should be able to help you. Check the internal tables xvbep, yvbep for the sales order program SAPMV45A. While debugging, try to run the availability check again. Then monitor any updates to tables, xvbep and yvbep.
    The error could be due to a user exit modification or a genuine SAP issue which is caused due to conflict with SAP ATP check and APO based ATP check.
    Debugging will help you to nail down how it is happening.
    Also check database table VBEP using transaction SE16 to check whether duplicate schedule lines are really saved to database.
    Regards
    Anil

  • Scheduling Agreements Issues -Urgent!-

    Hi Experts!
    I had some questions regarding our scheduling agreements.  Questions are below:
    1)  Our Open Order Report only shows the "unconfirmed" schedule lines...Is there any way or a report that will show the "confirmed" schedule lines as well?
    2)  Our delivery schedule lines remain on the delivery schedule list item detail screen (VA32 or VA33), even though the delivery has been delivered and completed.  The only way this seems to disappear is when a new schedule line is loaded.  Why do the old delivery schedule lines remain on the list even though they have been fully delivered and completed?
    3)  What is the difference between "New Delivery Schedule <b>WITH</b> Proposal" and New Delivery Schedule <b>WITHOUT</b> Proposal"?
    4)  What is "JIT Horizon"?
    5)  What does the "Propose CRQ" button do in scheduling agreements?
    6)  What is "Go Ahead Quantity"?  What is the "Analysis" function used for in scheduling agreemtns? 
    This is an urgent matter.  Any responses will be greatly appreciated.   Thank you for your time!!
    Best Regards,
    WC

    HI,
    Pl find info on
    http://help.sap.com/saphelp_47x200/helpdata/en/93/743af7546011d1a7020000e829fd11/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/93/743b11546011d1a7020000e829fd11/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/93/743b52546011d1a7020000e829fd11/content.htm
    Vrajesh

  • BAPI Error: No schedule lines due for delivery up to the selected date

    Hi,
    I have created a program to create delivery orders with reference to sales orders using BAPI - BAPI_OUTB_DELIVERY_CREATE_SLS.
    After execution I get the error: No schedule lines due for delivery up to the selected date
    Please help.
    Thanks in advance!!!
    Regards,
    Sriram

    hi,
    this is to inform you that,
    please check the schedule line date in the sales order because the date is not matching here for the BAPI to upload.
    here,  for example the schedule line is 4 days after and you are running BAPI today. that will mismatch no.
    the same thing is happening in uploading case also.
    so please check the date.
    because in teh sales order if teh schedule line date is today it will accept the uploading with out throwing any errors.
    regards,
    balajia

  • Error in creating schedule line aggrement through BAPI

    Hi All ,
    I want to create schedule line aggrement (VA31) by using BAPI / FM .
    I am using " SD_SALESDOCUMENT_CREATE" FM  .
    Here i am getting error in output when i enter shchedle line data in input .
    Error is given below .
    E V1                   434 No schedule line category could be determined during quantity adjustment
    Error only come when i want to create new schedule line ....in Changing any schedule line aggrement there is no error .
    I am able to create schedule line aggrement manually .
    please help .

    Use BAPI_SAG_CREATE

  • BAPI_GOODSMVT_CREATE Closing scheduling line items when errors

    Hello all,
    I have an issue when running BAPI_GOODSMVT_CREATE.  If someone for instance is in a scheduling agreement when running my code.  I get a locked by user return error from the BAPI.  This is fine but the problem is the line item is closed not allowing for reprocessing when the entry is no longer locked.  When reprocessing I will get a PU Ordered quantity exceeded by 1 EA : MS9556-08 2 error message
    Any advice? Is there a way to reopen a scheduling line item?
    Here is what Im sending the BAPI  Its looped so one Goods receipt per line in my custom z table.
      ls_header-pstng_date  = sy-datum.
       ls_code-gm_code       = c_01.
       LOOP AT i_ztab ASSIGNING <lfs_ztab>.
         IF <lfs_ztab>-zgr_status IS NOT INITIAL.
           <lfs_ztab>-zgr_status  = SPACE.
           <lfs_ztab>-zgr_error   = SPACE.
           <lfs_ztab>-return_code = SPACE.
         ENDIF.
         lv_index = sy-tabix.
         ls_header-doc_date  = <lfs_ztab>-zload_dt.
         lw_goods-material   = <lfs_tab>-ematn.
         lw_goods-plant      = <lfs_ztab>-werks.
         lw_goods-stge_loc   = s_loc-low.
         lw_goods-move_type  = c_101.
         lw_goods-mvt_ind    = c_b.
         lw_goods-vendor     = <lfs_ztab>-lifnr.
         lw_goods-entry_qnt  = <lfs_ztab>-menge.
         READ TABLE li_ekpo INTO lw_ekpo
             WITH KEY ebeln = <lfs_ztab>-ebeln
                      ebelp = <lfs_ztab>-ebelp
             BINARY SEARCH.
         IF sy-subrc = 0.
           lw_goods-po_number  = <lfs_ztab>-ebeln.
           lw_goods-po_item    = <lfs_ztab>-ebelp.
           lw_goods-entry_uom  = lw_ekpo-meins.
         ELSE.
           <lfs_ztab>-zgr_status  = c_f.
           <lfs_ztab>-zgr_error   = TEXT-003. "Contract not found error
           <lfs_ztab>-return_code = c_e.
           MOVE-CORRESPONDING <lfs_ztab> to w_ztab_up.
           APPEND w_tab_up TO i_ztab_up.
           CONTINUE.
         ENDIF.
         APPEND lw_goods TO li_goods.
         CALL FUNCTION 'BAPI_GOODSMVT_CREATE'
           EXPORTING
             GOODSMVT_HEADER               = ls_header
             GOODSMVT_CODE                 = ls_code
           IMPORTING
             MATERIALDOCUMENT              = lv_matdoc
           TABLES
             GOODSMVT_ITEM                 = li_goods
             RETURN                        = li_return.

    Hi Vinod,
            Actually there are two line items in the PO and manually when I try to create a GR for both line items,  it creates a GR but when I pass it thr' BAPI, it is generating a GR only for one Line item.
    Thanks,
    Prasad

  • Error "No schedule line due for delivery upto the selected date"

    Hi Experts,
    I am getting an error while creating outbound delivery for sales order.All items have same item cat and schedule line category,same customer.
    The sales order have three items with delivery date of 18.09.2008.the material stock is available for all three material and there is no planned issue for these material.
    In sales order schedule lines for all three items is confirmed on 18.09.2008. When I create a delivery on 04.09.2008(before the chedule line),it allows to create delivery for the two items but when I create delivery for material 3 on 04.09.2008(before the chedule line),it is giving error "No schedule line due for delivery upto the selected date" .on going to help it gives information that check whether the order item to be delivered contains confirmed schedule line.I checked the confirmed schedule line is on 18.09.2008 (though we have availbe stock on 04.09.2008).
    Kindly guide me how to resolve the issue,here I want to create delivery prior to the delivery/Schedule line date in Sles order.for 2 items it works but for third it is giving error.
    Is it something to do with Material group 5 in material master sales view for the 1 and 2nd mtrl it is 14 days for for the third it is 7 days?
    Sarvesh
    Edited by: Sarvesh Vashist on Sep 5, 2008 5:31 AM

    Hi Experts,
    I am getting an error while creating outbound delivery for sales order.All items have same item cat and schedule line category,same customer.
    The sales order have three items with delivery date of 18.09.2008.the material stock is available for all three material and there is no planned issue for these material.
    In sales order schedule lines for all three items is confirmed on 18.09.2008. When I create a delivery on 04.09.2008(before the chedule line),it allows to create delivery for the two items but when I create delivery for material 3 on 04.09.2008(before the chedule line),it is giving error "No schedule line due for delivery upto the selected date" .on going to help it gives information that check whether the order item to be delivered contains confirmed schedule line.I checked the confirmed schedule line is on 18.09.2008 (though we have availbe stock on 04.09.2008).It allows to create a OBD either I change the delivery date in sales order to 04.09.2008 or create a delivery with delivery date 18.09.208.
    Kindly guide me how to resolve the issue,here I want to create delivery prior to the delivery/Schedule line date in Sles order.for 2 items it works but for third it is giving error.
    Is it something to do with Material group 5 in material master sales view for the 1 and 2nd mtrl it is 14 days for for the third it is 7 days?
    Sarvesh
    Edited by: Sarvesh Vashist on Sep 5, 2008 5:31 AM

  • Item does not match schedule line (program error)

    Dear Experts,
    I Transaction VA02/VA03 when i put Sales order number  and try to get in to the system system through error and terminate the transaction
    ERROR is  "Item does not match schedule line (program error)" with Message no. V1427
    when i check Table level and analyse thr Debuging i found that
    Table VBAP line item 10 is missing and table VBEP line item 10 is there due to this miss match its shows above error
    Question
    Why and How it happen and how to fix this issue???
    Best Regards
    hanumant

    Check Note 442831 - V1427: Item does not match schedule line (program error)
    thanks
    G. Lakshmipathi

  • Item does not match schedule line (program error) in sap

    Dear Expert.
    Greetings!
    We are currently facing with this error (V1 427 item does not match schedule line (program error) in sap), when we open the sales order(VA02/03).
    The error  is occurring due  inconsistency on the database tables, some Item is in  table VBEP, but it is missing from table VBAP.  This is what is causing the error message.
    I checked various related notes - 442831 , 401463 , 389687  etc .  These are quite old notes and I am in release ECC 6.0 .
    Report SD_CONSISTENT_CHECK_EXT and SD_CONSISTENT_CHECK are already available.
    Bapi BAPI_SD_SALES is also active.
    Please let me know if anybody has any idea on the same.
    regards
    Praveen

    Hi,
       Refer the KBA:  1464620 - Error V1427: Item does not match schedule line   which explains the reason and the solution for the issue.
    Regards,
    AKPT

  • Error during maintaining schedule lines in ME38

    Dear All ,
               While I am trying to add schedule lines in ME38 for a schedule agreement system is giving error message
    "Message no. 06 881.   The vendor is blocked by Quality Management for this material as from the date shown."
               Plz let me know the reasons for this .
    Regards
    Abhijit Das

    hi,
    check few things:
    1. check whether you are doing the del schedule only on the given dates in the shedule agreement...
    2. check whether the material is blocked in the source list...check the validity dates also...
    Hope it helps..
    Regards
    Priyanka.P

Maybe you are looking for

  • HTTP Server is not currently supported with Solaris 10

    I am having a problem to start the HTTP Server on Solaris 10 (I am installing HTTP Server as part of HTMLDB installation on Solaris 10). I had a problem to install it at first, however I've found on 'AskTom' that unsetting ORA_NLS33 helps and it did.

  • My Brand New Refurbished Ipod Touch is not working

    I just bought a brand new refurbished Ipod touch 32GB (current generation), after a week it shows flickering white screens. I seldom used it for the whole week. When I went to apple service centre they told me that the water leak indicator turns into

  • Local Printer not working via Remote Link

    I have a problem with my remote desktop printing to my local printer.  I connect via RD on Windows 7 Home to Windows 7 Pro.  I have installed an HP Laserjet Pro CM1415fn printer.  All prints fine locally.  Also everything printed fine but have had to

  • Where is the Apple Photos library to import into LR6 - it's seemingly vanished...

    On my Mac, in import sources on LR6, there is no Photos option to select.  I had Aperture, then imported this library into Photos a few week back.  Hated Photos and now wish to use LR6.  But no Photos library to be found to import...Any ideas?

  • Why does it  show in such a way

    hi,everybody      There is a GridViewSet in my application window.For example ,the upperView and the downView. I have a parameter check in the upperView, but when I run the application, the messages are showing in the downView. But at the same time,