Schedule line quantity changed by MRP with in firm zone

Hi,
We have a schedule agreement with firm zone maintained and MRP binding indicator blank is maitained in additional data at item level. But we have seen schedule line quantity has been changed after MRP run. I dont understand how its possible....please help
Regrds,
Raghu

If the qty is not transmitted to the vendor using message transmission, system does not firm the qty with in planning time fence.
So pls chk your planning time fence as well.
Also pls chk the below link
http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2a5b44af11d182b40000e829fbfe/content.htm
BR,
Krishna

Similar Messages

  • Schedule line category CN is inconsistent with the MRP type

    Guys,
    I am running into an issue here..
    I have change the MRP type of articles from ND (no planning) to PD (MRP)
    Now when I try to change sales oders on this articles (VA02), I get error message saying that the Schedule line category CN is inconsistent with the MRP type
    Does that make sense to any of you and what is/are the remedies
    KR - Loï

    Dear
    When you have created SO at that time the MRP type was ND so based on that System has picked the Schedule line category CN which is No mat.planning. Create new SO this problem will not come. Based on Strategy & PD schedule line category will come as mat. planning.
    Regards
    ABhijit Gautam

  • How to Change Schedule line Quantity in BADI 'ORDER_SAVE'

    Hi,
    I need to change the Schedule line quantity While Order saving. I am writing the code in ORDER_SAVE BADI. Using the Header guid i am reading the details and changing the quantity in Schedule line structure. How can i pass those values in to Memory so that order quantity will change. I try to Use CRM_ORDER_MAINTAIN but not able to change the quantity. Can an

    Hi,
    You need the One Order Function Module - CRM_ORDER_MAINTAIN to update the Schedule line value. So, you need to have a look at all the fields that are necessary to fill using the Tables and Structures. If you have the header guid, then you can probably pass the guid to CRM_ORDER_READ to read the values and then fill in the entries necessary to make the changes.
    You can also debug the order code to get a feel of the necessary changes.
    Hope this helps.
    Thanks,
    Samantak.

  • MD04 firm schedule line - ME38 schedule line manualy changed

    Hello Gurus,
    many users change manually quantity in schedule lines but then the schedule is locked and becomes firm in MD04 ( * ) so that MRP does not take this quantity into account.
    How to change this behaviour as I want the MRP to take this modification into account ?
    Thanks a lot.

    Hi,
    When your users change a schedule line they are automatically firmed as the system can only assume that they know more about the supply position than it does.
    MRP does take the quantity into account, however, it is not allowed to change the date nor the quantity, so any increase or decrease in demand is reflected in the first unfirmed schedule line.
    This behaviour is not configurable.
    If the firmed schedule line is not correct because the user has made a change in error then you need to set the quantity to zero so that the schedule line is deleted. MRP will then create a new schedule line in line with the planning parameters and current stocks / demand.
    Hope that has answered your question
    Alex Dixon

  • Schedule lines not generated after MRP run

    Dear All,
    I am trying to create Schedule lines through MRP run , but instead system creates MRP element PRqRel  and its PurRqs when i check in MD04 ,  the following are the prerequisite i done before MRP run , but still Schedule lines are not generating.
    1.activated checkbox source list in material master.,Procurement type is F, MRP type PD , lot size MB , marked JIT  Scheduling indicator as 1 in Pur view of material master , no MRP group is used in our process.
    2.Maintained Inforecord.
    3.Maintained source list for the material and marked MRP relevant as 2. Validity also checked.
    4. Quota arrangement for this vendor only.
    5. Created New scheduling agreement.
    6. Material is not sent for subcontracting.
    7. Ran  MD02 with following parameters ,
    Processing key NETCH Net Change in Total Horizon
    Create purchase req. 1 Purchase requisitions in opening period
    Delivery schedules 3 Schedule lines
    Create MRP list 1 MRP list
    Planning mode 3 Adapt planning data (normal mode)
    Please let me know if i am missing something
    Thanks in Advance
    Benny

    Hi,
    Please check the below links...
    Schedule Lines not getting created in MRP
    Schedule Lines not generated for MRP Type PD
    Kuber

  • Scedule lines data change after MRP run

    I generates a schedule lines when I run the MRP for certains articles. When I run again MRP, It modifies the data's of schedule line (quantity per ex) even thoough I have already transmetted the request (schedule lines) to the vendor.
    How to prevent to make changes in the schedule line once I sent the info to the vendor. Instead I would like that the MRP creates new schedule line.
    Than you for any help.
    Ahmed.

    Hi Ahmed,
    In MRP-4 view have you maintained 1 or 2 for Indv. / Coll indicator?
    Regards,
    Vivek

  • Schedule line quantity

    Hi All,
    A sales order is created with 0 confirmed schedule line quantity.
    At the time of creating delivery if stock is available system creates delivery else doesn't create delivery.
    Now for some materials system is not creating delivery eventhough stock is available. Availability check configurations at SO and DO are same.
    If i go to va02 and redo avaliability check system is allowing me to create delivery.
    Please let me know any clues on this....did any of you faced this problem....
    Thanks
    Venkat

    Dear Venkat,
    Welcome to the Forum!!!
    Normally, if the stock is not available on the requested Delivery Date (While creating the Sales Order) then the schedule line level data shows that there are Zero Confirmed Quantity as a first line item. Then, once the material is available then the system shows the confirmed quantity on the particular date when material can be delivery considering all the possible loading, transporation planning times etc.... as a second line item....
    So, system will allow you to create delivery only on the date on which the quantities are confirmed.....
    For some materials where you are not able to create delivery that could be because of some other reason like Item not relevant for Delivery etc....
    In Va02, if you run the availabilty check system is allowing the delivery creation because may be some new quantities could have comne to stock...
    Regards

  • Schedule lines should not be maintained with out release

    schedule lines should not be maintained with out release of schedule agreement......but system accepting to maintain the schedule lines.Please say how.
    regards,
    Sridhar kumar.a

    Hello,
    I have the same problem as you. Someone know something about it?
    kanyadhara, did yo solve this problem?
    Thanks a lot

  • Intercompany STO's delivery quantity schedule line quantity

    Folks,
    I have the following issue:
    STO / PO for 01.01.2010 for 2 PCE's
    1 schedule line for 1 PCE for 01.01.2010 -> delivered and receipted;
    1 schedule line for 1 PCE for 01.02.2010 -> cannot yet be delivered.
    Total of schedule lines = 2, so schedule line quantity equals PO quantity.
    Stock comes in and VL10g runs in background and generates 2 deliveries for 1 PCE each, whereas there was an open quantity for only 1 PCE!
    So in fact total delivery quantity is 3 whereas the PO quantity is 2.
    Anyone seen this?
    MZ

    Hi
    Hi can you check the following
    1. In  delivery item category  t code  OVLP availability check should be on
    2. use the t code to generate the delivery for the purchase order  t code VL10d  (In this system will show the open quantity how much is going to deliver)
    Delivery is happening more than STO quantity
    Regards
    Damu

  • Schedule line date changes after each MRP run

    Dear Experts,
    Clarification needed on how the system plans the MM schedule lines.
    Setting: Start in the past not allowed.
                  3 days for processing of order
    The issue is after each MRP run the system is moving the schedule line to the current date + 3 days for processing + the planned delivery time.
    If the schedule line is not firmed, after each MRP run ( which happens everyday) the system is moving the schedule line and then giving an alert saying the " order has to be rescheduled to the previous day"
    on the second day after the mrp run the system moves the schedule line again by one more day and gives the rescheduling date as " -2 days from today"
    this change is happening every day after the planning run. - because of this there are really no backorders ( schedule line in the past ) in the system. we were not able to know if the vendor is actually delayed in this case.
    can you kindly suggest what went wrong here ??
    we are using strategy 10 for the planning of procured parts. Let me know if more info is needed.
    Note: we are also using stock transfer process for some procured parts. there too the PR date gets changed after each MRP run. There there is no lead time in this case. the order is placed on the same day as the requirement as both plants are nearby. There the PR date is changing everyday to the current date.
    your advice would be of great help
    thanks
    Nagendra Kumar

    Hi Caetano,
    thanks for your suggestion
    Yes, we use firm zone for few of the vendors. there the system don't change the schedule lines.
    Also for the stock transfer PR's there is no firm zone and the lead time is one day. in this case it changes everyday after the MRP run.
    the stock transfer PR's leads to the creation of Schedule lines from the source plant. Since this PR gets changed everyday. the alerts coming out of MD07 gets changed and we really did not know if this order is delayed or not.  In the source plant we use the firm zone to avoid moving the schedule line. But then the alerts are always not correct.
    is there any setting which helps in not moving the PR everyday without using " start in the past"
    thanks
    Nagendra Kumar

  • Schedule Lines not generated for MRP Type PD

    HI All,
    I have created Schduling Agreement, maintained Source List with MRP Relevant - 2 option and maintained Vendor as Fix, maintained info record.
    I have created a material with MRP type as PD and lot size as EX, and strategy group as MTS. Now when i enter requirement through MD61 and do MRP Run through MD02, system is generating PR instead of Del Schdule line inspite of schduling agreement. 
    But If i change MRP type to VB and maintain reorder point and maintain min lot size, then system generates Del Schdule lines for the same material.
    What could be the reason. I want delivery schedules based on MRP Type PD.
    Where I am wrong in MRP Views or in any cutomization. It seems that purchasing part is fine since it creats scudles line so no problem in SA or in Source List.
    Please help
    Regards,
    Vikas

    I have created Schduling Agreement, maintained Source List with MRP Relevant - 2 option and maintained Vendor as Fix, maintained info record.
    I have created a material with MRP type as PD and lot size as EX, and strategy group as MTS. Now when i enter requirement through MD61 and do MRP Run through MD02, system is generating PR instead of Del Schdule line inspite of schduling agreement.
    But If i change MRP type to VB and maintain reorder point and maintain min lot size, then system generates Del Schdule lines for the same material.
    What could be the reason. I want delivery schedules based on MRP Type PD.
    Where I am wrong in MRP Views or in any cutomization. It seems that purchasing part is fine since it creats scudles line so no problem in SA or in Source List.
    Hi Vikas,
                      After being thru with your query,i would like to reply your ultimate question"I want delivery schedules based on MRP Type PD"
    Simple answer:put parameter 'delivery schedule line' as '3'(schedule lines in opening period) without simulation mode.
    Please make sure you  don't make any change with previous settings(custom)
    please get it done and revert.
    Regards
    Chandra

  • ME38 Schedule Line Mass Change

    Hi Experts,
    I have a requirement to change Schedule lines(Line wise) quantity from excel sheet by delivery date.
    I tried  BAPI_SCHEDULE_MAINTAIN  but I am getting below error due to my system setup.
    Scheduling agreements with time-independent conditions are not supported So i couldn't change any schedule line.
    Because  time-independent conditions  is deactivated in my SAP system.
    Is there any other solution like BDC or LSMW ?.
    If through BDC is possible how can i go particular item wise?.
    Experts please give me solution <removed by moderator>.
    If you want further details I can ready to give.
    Edited by: Thomas Zloch on Feb 24, 2012

    I tried with userexit_move_field_vbep but no luck.
    Bala: i can use the save_document user exit but if i go and see the schedule line it will show the old date and time. I think that is usefull when saving the application.
    Sorry, i forgot to mention one more thing.. i.e., user can change the date and time using 'fast change of' option in menu bar.
    Please let me know which field do i need to change to change the date. I tried VBEP-EDATU and VBEP-EZEIT.
    Thanks in advance
    Sam

  • Schedule Line Date Changed By Standard Code After User Exit

    We've implemented USEREXIT_MOVE_FIELD_TO_VBEP to conditionally change the schedule line date (it changes VBEP-EDATU) when sales orders are being created.  This functions correctly when VA01 or EDI is used.  However, when the order is created using BAPI_SALESORDER_CREATEFROMDAT2, standard code executing after the user exit changes the schedule line date to an incorrect value. 
    The user exit correctly changes the schedule line date; then later on in the execution subroutine VBEP_FUELLEN_VBEPKOM in include FV45EFEP_VBEP_FUELLEN_VBEPKOM is executed which changes the date on line 37 using the value in US_VBEPKOM-EDATU.  US_VBEPKOM-EDATU is in scope in the user exit, but earlier in subroutine VBEP_FUELLEN_VBEPKOM (line 12 to be exact) this variable is updated with the value in US_VBEPKOM1-EDATU, which is not in scope during the user exit.  So, USEREXIT_MOVE_FIELD_TO_VBEP doesn't have access to US_VBEPKOM1-EDATU and can not ensure that the correct value is used later on in subroutine VBEP_FUELLEN_VBEPKOM.
    I noticed at the end of subroutine VBEP_FUELLEN_VBEPKOM it calls USEREXIT_MOVE_FIELD_TO_VBEPKOM.  I could update VBEP-EDATU here to correct the error whenever the order is created using the BAPI, but it would be nice to have a solution that could be implemented only in USEREXIT_MOVE_FIELD_TO_VBEP without also having to implement USEREXIT_MOVE_FIELD_TO_VBEPKOM.
    So my question: is there a way to update the schedule line date in USEREXIT_MOVE_FIELD_TO_VBEP where it won't be changed later in subroutine VBEP_FUELLEN_VBEPKOM when the order is created using the BAPI?

    Hi Caetano,
    thanks for your suggestion
    Yes, we use firm zone for few of the vendors. there the system don't change the schedule lines.
    Also for the stock transfer PR's there is no firm zone and the lead time is one day. in this case it changes everyday after the MRP run.
    the stock transfer PR's leads to the creation of Schedule lines from the source plant. Since this PR gets changed everyday. the alerts coming out of MD07 gets changed and we really did not know if this order is delayed or not.  In the source plant we use the firm zone to avoid moving the schedule line. But then the alerts are always not correct.
    is there any setting which helps in not moving the PR everyday without using " start in the past"
    thanks
    Nagendra Kumar

  • Dropship PO schedule line date changes and impact in SO

    Hi,
    Please suggest where senario; Drop ship PO created and Changed Schedule delivery date on Purchase order and automaticaly changes in Sales order schedule line level.
    SO- PR - PO
    Senario1;
    When Vendor not confirms requested delivery quantity on date, he confirms partially qty and later confirmes remaining quanity. When we split in Purchase order delivery schedule directly it will not update at sales order it confirms and changes initially qty only on SO schedule line level. how can i copy back to sales order schedule qty partial split done on PO.
    Senario2;
    When SO created and PR - PO generated later when we Add new line item in SO or Directly add PO line item how can i make sync between the two documents automatically.
    SO Schedule delivery date and PO schedule delivery date how can i see the link b/w to document back to back updates automatically when we change any one doc.
    Thanks in advance
    JACK

    Hi Caetano,
    thanks for your suggestion
    Yes, we use firm zone for few of the vendors. there the system don't change the schedule lines.
    Also for the stock transfer PR's there is no firm zone and the lead time is one day. in this case it changes everyday after the MRP run.
    the stock transfer PR's leads to the creation of Schedule lines from the source plant. Since this PR gets changed everyday. the alerts coming out of MD07 gets changed and we really did not know if this order is delayed or not.  In the source plant we use the firm zone to avoid moving the schedule line. But then the alerts are always not correct.
    is there any setting which helps in not moving the PR everyday without using " start in the past"
    thanks
    Nagendra Kumar

  • Schedule Lines not created from MRP

    Hi !!
    I have a finished product ""111-2523-64"" and in its BOM i have a semifinished product ""111-2523-64-010"" produced(Inhouse)& three raw materials .
    For the Raw Materials I have made the scheduling agreement & source list with indicator ("2"" create schedule lines automatically""
    Problem -: Now when I run the MRP using T-Code MD02 the system is planning the finished & semifinished product 
    *but no schedule lines are created for the raw materials.*
    Please Guide , Itz very urgent.
    Regards
    Rahul Bhardwaj
    9909986406

    Dear Rahul,
    When u r running MRP maintain '3' for Delivery Schedules Field under MRP Control Parameters ( T Code MD02). Sheduling Agreement should be valid. If there is sufficient stock on hand compared with the requirement then system will not create any Schedule Lines. In material master of raw Materials on MRP2 view Procurement Type should be Maintained as 'F'. If u have maintained 'E' or 'X' then MRP run will not create schedule lines.
    Regards
    Sunil Kumar

Maybe you are looking for

  • Multiple GWIAs : multiple domains too or not?

    First off, let me confess that this is near the end for our GW system. The reason for creating GWIAs in this manner is to migrate our users' email to another system via IMAP. We have ~6000 users and > 500GB of messages to move. With that being said..

  • User dimension in a frame

    Hi, I'm a verry newby to graphics programming (i'm more a techie), but what i want is a dimension, or (even better) the width and dimension of the user field in a frame. When i make a frame of 800x600, the user field is reduced, in height because of

  • TIFF files not placing/placing as blank images in InDesign CC

    I'm working on a large catalog and am having issues with just one of the TIFF files I'm trying to place out of 300+ that have all been saved the same way in Photoshop. When I try to replace the image within it's original bounding box, it erases anyth

  • Rem Lot Creation

    hi guys, We have reporting points 10,20,30 and 40. I am doing Backflushing by using reporting point my is problem Is there any way automatic generation of qm lot for reporting point 30 only, where I have assign certain chrac for that operation??????

  • Free Flex 3 Posters

    Has anybody been able to order the free posters you get with Flex 3? I have been trying to explain to support that the page below does not take my REGISTERED VALID serial number. https://www.adobe.com/cfusion/entitlement/index.cfm?e=posters I have be