Schedule line should not generate until SA release

Dear All,
We want when we run MRP against schedule agreement then "Schedule line should not generate until SA release"
Abhinay

HI Abhinay Sachan ,
Bascially when we run the MRP the system generate the Schedule Lines for that  schedule line we are doing release .....
If you have SA for a particular materail system gives the Error or warrning message based on the setting what we made...if it is error sysetm won't allow other wise it is warrning meaasge means we can cretae the PR for the particular materail i hope i wll help you
Regards
Murugan J

Similar Messages

  • Schedule lines should not be maintained with out release

    schedule lines should not be maintained with out release of schedule agreement......but system accepting to maintain the schedule lines.Please say how.
    regards,
    Sridhar kumar.a

    Hello,
    I have the same problem as you. Someone know something about it?
    kanyadhara, did yo solve this problem?
    Thanks a lot

  • Without release schedule agreement schedule lines should not be maintain

    Hi experts,
           i made a schedule agreement and i have given 2 level of releases for it.. so with out releasing i maintained schedule lines in me38, then i made migo then system says the document has not been released yet. but what my query is schedule lines should not be happened with out release means it should stop here only. So how to give check for it.i have searched in system messages but nothing is there in that. So please solve this problem its urgent.

    Hello,
    I have the same problem as you. Someone know something about it?
    kanyadhara, did yo solve this problem?
    Thanks a lot

  • Billing Doc should NOT generate until you do PGI.....

    Hi,
    Please help me for the below Scenario:
    I have an Issue which is, Billing document should not generate until and unless you do PGI in Delivery.
    Can anyone tell me CONTROL PARAMETERS for this issue.
    Thanks in Advance.
    Raj

    Hi there,
    Standard SAP willnot allow invoice unless delivery is PGI'ed.
    Check the copy control routines in VTFL at header level. Check if the requirement assigned in copy control from LF to F2 is 011 Head.dlv-rel.w/o GI. If yes, change it. 011 will allow F2 to be created without PGI. Change it to 3 which is Header/dlv.-related & try it.
    Regards,
    Sivanand

  • Schedule lines are not generating properly in MD04

    Hello All,
    I have a issue in MD04, in which schedule line for Schedule agreement is not getting generated on the same day as sales order is created (09.05.2014). But Schedule line is getting created in different date. Because of which i am creating schedule lines manually at required dates. 
    Note: I have attached screen shot of MD04
    Kindly help me to overcome this issue.
    Regards,
    Manoj  

    Hello Manoj
    Please observe that there are rescheduling exception messages and rescheduling dates for your scheduling agreements. It generally happens when you have sales orders in the past and you don't allow "start in the past" for replenishment proposals generated by MRP.
    Go to the customizing transaction OPPQ and change the customizing "start in the past". After that, run MRP again for your material and the schedule line dates should match the sales order. Please observe that firmed schedule lines wont't be changed.
    BR
    Caetano

  • Schedule lines should not change 3 weeks time from MRP date

    Hi
    Is there any specific customisation required to get following results in case of schedule lines.
    1) MRP should not change/adjust the already send delivery schedule lines  which are lying within 3 weeks time from MRP date
    2) System should not allow to book the GRN unless the messages / print out has been generated from the system in case of scheduling agreement.
    Thanking you
    Shantakumar
    09944009752

    Hi,
    There are 2 possibilities:
         1. use MRP fixing using planning time fences, this is done by putting the relevant settings in the MRP1 view of the material master
         2. use the firming options of the scheduling agreement, these are set per material number that is entered in the scheduling agreement.
    The GR can only be posted for schedule lines that have been processed aka output generated.
    Regards,

  • Scheduling Agreement -Schedule line should not pass the requirement to MRP

    Hi Friends!
    As we all know the scheduling agreements is outline agreement with future schedule lines, with this system will  pass the requirements to MRP for the schedule line which is even after 5 years, so my requirement is  if the schedule line date is above 15 days from the current date then requirement should not pass to MRP. 
    solution which we gave is, SA initially will determine the schedule line category as  CN (which will not transfer the requirement) and  a batch job program will run daily and it will check for each schedule line if any of the schedule is with in the 15 days from the current date then it will change the schedule line category from CN to CP. 
    Now the problem is , by using Batch Job which program I have to call to change the schedule line category?????
    1. we tried BAPI_SALESORDER_CHANGE but when we are changing the CN to CP it is not performing ATP where as if we do manually it is performing.
    2. we tried BDC but here also we facing some strange problem i.e. while recording the ATP screen is not populating where it is coming while doing manual.
    Can someone let me know which one program we should call in Batch job to do this change.
    Regards
    Nath

    Hi nath,
    i also failed in changing shedule line category in userexit and in BAPI.
    in one case, i succeded in doing it with a bdc after MV45AFZZ / userexit_save just bevore the datas are reset but after the commit-work is processed.
    the other possibility is, to change the accepted amount in userexit RV03VFZZ / USEREXIT_AVAILABILITY_OUT.
    3. possibility is, to block the order with a delivery - block , same as the credit-control-block. This block can be set in MV45AFZZ or perhaps in BAPI too.
    hans

  • In ME38 If (EKET-MENGE) (EKPO-KTMNG)Schedule lines should not be created

    Hi,
    Our Requirement is in ME38 which is for creting Schdule line Agrement the system should not allow to create schedule lines
    if the Total of Schedule Line Quantity > Total Scheduled Quantity
              (Sum of all EKET-MENGE) > (EKPO-KTMNG)
    Can anybody give me the right User Exit,BADI for this Requirement and Coding for this

    Hello,
    I have the same problem as you. Someone know something about it?
    kanyadhara, did yo solve this problem?
    Thanks a lot

  • When we run the MRP schedule lines are not generated automatically.

    Hi,
    In MD04 requirement date is on 5.12.2009.My source list validity starts from 1.12.2008 onwards.When i run the MRP for the material system generates the Purchase requisition instead of the schedlue lines.When i change the source list validity as 25.11.2008 now i run the MRP system generates the schedule lines.
    My question is why the system couldn't able to generate the schedule lines when the validity starts on 1.12.2008.In the source list we maintained the scheduling agreement and maintaine the MRP setting as 2.

    hi,
    Let me know your purchasing processing time defined in the SPRO settings for CBP?? It may be due to this also...
    Regards
    Priyanka.P

  • Schedule lines are not getting generated during MRP Run

    Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
    Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
    Can any one help me and suggest me what to be done in this case .
    Thanks & Regards ,
    Nirmalya

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Schedule Lines are not getting generated after MRP run.

    Hi,
    I have an issue where a SA exists for the parent material with item category L (subcontracting). The parent material has a valid BOM and some sub components as well. I see in CS03 that BOM is fine with validity dates for the parent material. A valid source list also exists for the parent material where SA is present as the source of supply with MRP indicator as 2. Now when i run MRP for the parent material using MD02 (NETCH), with indicators as below:
    Create pur.req.  2
    Schedule lines   3
    Create MRP list  1
    Planning mode   1
    i don't see any schedule lines in MD04. Instead it creates a PR that too without any source of supply.
    In master data for the parent material MRP type is PD with Procurement type F and special procurement key 30. I have checked and every thing seems to be fine still MRP run doesn't create schedule lines.
    Any help is appreciated. I can give more info if required.
    Thanks.

    Dear Rakesh,
    Scheduling agreement:An outline agreement against which materials are procured at a series of
    predefined points in time over a certain period.
    1.For this you have to first use ME31L for creating scheduling agreement and then ME38 for maintaining scheduling agreemnet
    schedule.
    2.Ensure in the source list after maintaining the material,vendor combination the setting for MRP relevancy is set to 2 - Record
    relevant to MRP,Schedule line generated automatically.
    Moreover you have to use value 3 for delivery schedule line which is one of the MRP control parameter while taking MRP run.
    So for the materials for which scheduling agreement exists,schedule lines will be generated.
    Check and revert back.
    Regards
    Mangalraj.S

  • Line item not relevant for payment release

    Dear Expert,
    When I select payment block : 'Payment Request' in FB60. Error Message appear "Line item not relevant for payment release".
    I also have set payment block in master vendor and  OBB8.
    Can you tell me why the error message still appear?
    Kindly need your help
    Thanks and Regards,
    YL

    Do you have any workflow variant in place?
    Moreover, when you have already set the Payment block at Master level, you need not to fix it in transaction level.
    Vendor itself will not get paid until unless you remove the block option
    Thanks

  • Schedule lines should be in gray mode

    Hi Gurus,
    Any idea how to make the schedule lines in gray mode.
    My client demand is when we save the sales order and
    we go to va02 schedule lines should show in gray mode to avoid
    the changes  quantity.
    Thanks in advance

    Dear Protan,
    the solution suggested above with the help of user-exit USER_EXIT_FIELD_MODIFICATION (Include MV45AFZZ) is the correct way to make the schedule lines unchangable. But please take into consideration that in the "normal" sales orders you do not need to go to the schedule line screen to change date or quantity. It is sufficient that you change the date or quantity on the item level. Then the schedule lines will be changed (created/deleted) in the background automatically.
    So, if you really want to grey out the quantity and date fields, you have to do this on all screens (Sales Overview, Procurement, Shipment etc.) also on  the item level. Then the item will be unchangable at all. Please be careful with this.
    So, you have to grey out all item date and quantity fields in all screens of the order. To do unchangable only schedule line screen is then not sufficient.
    As Manam said above, the USER_EXIT_FIELD_MODIFICATION is the only correct place to make the fields unchangable. I can only confirm this.
    I hope, this additional info was also helpful for you.
    Kind regards,
    Akmal Vakhidov
    Development Support SD, SAP, Walldorf/Germany

  • Schedule lines are not getting confirmed even though stock is there

    HI,
    i want to discuiss one sensitive issues which is a simple one.
    my schedule lines is not getting confirmed even stock is there at sales order.
    there is no delivery block.
    there is no minimum stock level.
    there is no credit check for that.
    there is stock of 2 EA in that plant and storage location, but stock is not getting confirmed at sales order level or transaction level.
    even stock is there it is going to avaliability check overview screen and giving stock confirmation after 12 days.
    even i checked all the dates.............but its of no use.
    what to do ?
    after testing all the possible options i am taking help from
    please help me in this regard,
    regards,
    balajit

    Hi
    you need to check the following.....
    First check the Factory calander of your plant whethear some holidays or not
    Second most importantly you have to check which stretagy group is assigned  in the material . whethear it is make to order or make to stock. change it as make to stock.
    "What happened if material stretagy group is make to order then from sales order system generate requirement of that material against that particular stock, that time system do not consider the unrestricted stock and not confirm schedule line."
    Regards
    Shambhu Sarkar

  • Lines are not generated for holidays and sundays

    Hi
    creating a sale order shcedule lines are not generated for sunday for a particular plant .
    Schedule lines are generated for subsequent monday only.
    the plant calander  is also  correct
    with regards
    partha

    Hi
    I would really double check the factory calendar ans the  of the plant and sales organisation
    regards,
    Sidi

Maybe you are looking for

  • Difference between business service and business system in SLD

    hi all, i m very new to XI. can anybody tell me that what is the basic difference between Business Service and Business Systems? Is it necessary to use them? and if yes then when to use what? Thanx. Regards, Kunjal......

  • Disc Drive Problem

    Hi guys, I got a problem with my macbook pro disc drive. I accidentally changed the Dvd Region Code five times and now I only can play American Dvd's anymore and no European ones. And I was told that the only way to correct this problem would be by r

  • O man, it won't work for nothing!

    Ok hello everyone, I'm new to this whole router stuff. I have a WRT54G v.6 wireless-g broadband router that i just bought. I have a PC running Windows Me(I know, it sucks but luckily my laptop has WinXP) ISP: Verizon DSL Now the first thing i did was

  • I get alerts to update Firefox. Updates won't load. I have Mac OS X 10.7

    Occasionally I get alerts from Firefox to install updates. When I click to install, it never installs itself. I eventually close the window. What is the problem and how do I fix it?

  • Transfer all mail accounts from iphone to mac os x mail

    Hey, Is there any way i can transfer all my mail accounts from my iphone to mac os x mail directly rather than going it one by one i mean is there any setting in itunes which will copy my mail accounts from iphone to mac os x mail ? thanks