Schedule lines are not coming after MRP run for HALB material

Dear All,
I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
Pls let me know if I am missing something and guide me further on this.
Thanks & Regards
Kundan Kumar

Dear All,
I am closing this thread. As the vendor mentioned in scheduling agreement is not a subcontracting vendor. Its a individual vendor.
Thanks for all the reply.
Thanks & Regards'
Kundan Kumar

Similar Messages

  • Scheduling lines are not created in mrp running

    Line 1 & 2 are having same items with different schedule lines qty 250 & 275 nos. respectively. Stock was 250. System bokked stock 250 against line 1 & given proposed delivery date for line 2. In MM module, by running MRP system generated requirement only for 25 pcs.(may be it taken again stock 250 against line 2 in consideration while running MRP). This is happened in various cases.KINDLY HELP ME in solving this problem.
    REGARDS,
    G.V.SHIVAKKUMAR

    Hi,
    With my experience I will share something:
    1) Do you have valid Schedule Agreement?
    2) Have you entered Sch. Agreement number in source list?
    3) Have you selected MRP as " 2 " in source list?
    With your earlier checks, please chekc these also.
    Karthik Params

  • Schedule lines are not coming for HALB after MRP run

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • MRP schedule lines are not created by MRP

    Hi !!
    I have a finished product ""111-2523-64"" and in its BOM i have a semifinished product ""111-2523-64-010"" produced(Inhouse)& three raw materials .
    For the Raw Materials I have made the scheduling agreement & source list with indicator ("2"" create schedule lines automatically""
    Problem -: Now when I run the MRP using T-Code MD02 the system is planning the finished & semifinished product
    *but no schedule lines are created for the raw materials.*
    Please Guide , Itz very urgent.

    Vijay , Pleae clear
    I have a doubt
    I am having one finished product & in its BOM i have three raw materials.
    I have created the scheduling agreement for these three raw materials and source list too.
    now when i run the MRp for finished product using t-code md02 the schedule lines must be generated for these three raw materials.
    or
    i have to run the MRP (seperately using T-Code Md01 ) for these three raw materials
    Please guide , its very urgent.

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Delivery Schedules not created after MRP Run for MRP Type PD

    HI All,
    I have created Schduling Agreement, maintained Source List with MRP Relevant - 2 option and maintained Vendor as Fix, maintained info record.
    I have created a material with MRP type as PD and lot size as EX, and strategy group as MTS. Now when i enter requirement through MD61 and do MRP Run through MD02, system is generating PR instead of Del Schdule line inspite of schduling agreement.
    But If i change MRP type to VB and maintain reorder point and maintain min lot size, then system generates Del Schdule lines for the same material.
    What could be the reason. I want delivery schedules based on MRP Type PD.
    Where I am wrong in MRP Views or in any cutomization. It seems that purchasing part is fine since it creats scudles line so no problem in SA or in Source List.
    Please help
    Regards,
    Vikas

    Hi Vikas,
    Go through this link you will able to customize correctly
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/3b/66596eda7b11d1b6330000e8a738dc/frameset.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm
    Cheers
    Kris

  • Schedule lines not generated after MRP run

    Dear All,
    I am trying to create Schedule lines through MRP run , but instead system creates MRP element PRqRel  and its PurRqs when i check in MD04 ,  the following are the prerequisite i done before MRP run , but still Schedule lines are not generating.
    1.activated checkbox source list in material master.,Procurement type is F, MRP type PD , lot size MB , marked JIT  Scheduling indicator as 1 in Pur view of material master , no MRP group is used in our process.
    2.Maintained Inforecord.
    3.Maintained source list for the material and marked MRP relevant as 2. Validity also checked.
    4. Quota arrangement for this vendor only.
    5. Created New scheduling agreement.
    6. Material is not sent for subcontracting.
    7. Ran  MD02 with following parameters ,
    Processing key NETCH Net Change in Total Horizon
    Create purchase req. 1 Purchase requisitions in opening period
    Delivery schedules 3 Schedule lines
    Create MRP list 1 MRP list
    Planning mode 3 Adapt planning data (normal mode)
    Please let me know if i am missing something
    Thanks in Advance
    Benny

    Hi,
    Please check the below links...
    Schedule Lines not getting created in MRP
    Schedule Lines not generated for MRP Type PD
    Kuber

  • Schedule lines are not getting generated during MRP Run

    Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
    Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
    Can any one help me and suggest me what to be done in this case .
    Thanks & Regards ,
    Nirmalya

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Schedule lines are not in sink for PO

    Hello Everyone,
    We are using ECS.
    So we create PO in SRM with some schedule lines and transfer it to the ECC system.
    But sometimes the schedule lines are not in sink on both the sides because buyer update the schedule lines on SRM side.
    So we need to check that is schedule lines in SRM and Basic quantity in SRM are same or not?
    So is there any OSS note to check this?
    Regards,
    Khushbu.

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • In Sales Order Users are not allowed to change price for any material

    Dear all,
    Please give me the solution :
    In Sales Order va02 Users are not allowed to change price for any material .

    Hi Amit
    If you  want that in VA01 manual as well as other pricing condiion entry and cahnges to be allowed and only in va02 users should be restricted ,then  you have following alternative.
    Go to  T.Code SHD0
    Select Transaction VA02.
    Create a new variant ,give suitable name.
    select option change with processing.
    So u can run a va02 transaction and for every screen u can create screen variant and control data entry whether required  , dispaly or hide.
    in this for  LV69a pricing  screen disable update button .
    so system wont change anything updated or cahnged in pricing.
    further you can create the variant transactions  from this transaction variant and assign to different users as per control requirements.
    I think this will help you
    Regards
    mandar

  • Schedule lines are not generating properly in MD04

    Hello All,
    I have a issue in MD04, in which schedule line for Schedule agreement is not getting generated on the same day as sales order is created (09.05.2014). But Schedule line is getting created in different date. Because of which i am creating schedule lines manually at required dates. 
    Note: I have attached screen shot of MD04
    Kindly help me to overcome this issue.
    Regards,
    Manoj  

    Hello Manoj
    Please observe that there are rescheduling exception messages and rescheduling dates for your scheduling agreements. It generally happens when you have sales orders in the past and you don't allow "start in the past" for replenishment proposals generated by MRP.
    Go to the customizing transaction OPPQ and change the customizing "start in the past". After that, run MRP again for your material and the schedule line dates should match the sales order. Please observe that firmed schedule lines wont't be changed.
    BR
    Caetano

  • Schedule lines are not getting confirmed even though stock is there

    HI,
    i want to discuiss one sensitive issues which is a simple one.
    my schedule lines is not getting confirmed even stock is there at sales order.
    there is no delivery block.
    there is no minimum stock level.
    there is no credit check for that.
    there is stock of 2 EA in that plant and storage location, but stock is not getting confirmed at sales order level or transaction level.
    even stock is there it is going to avaliability check overview screen and giving stock confirmation after 12 days.
    even i checked all the dates.............but its of no use.
    what to do ?
    after testing all the possible options i am taking help from
    please help me in this regard,
    regards,
    balajit

    Hi
    you need to check the following.....
    First check the Factory calander of your plant whethear some holidays or not
    Second most importantly you have to check which stretagy group is assigned  in the material . whethear it is make to order or make to stock. change it as make to stock.
    "What happened if material stretagy group is make to order then from sales order system generate requirement of that material against that particular stock, that time system do not consider the unrestricted stock and not confirm schedule line."
    Regards
    Shambhu Sarkar

  • Schedule Lines are not getting generated after MRP run.

    Hi,
    I have an issue where a SA exists for the parent material with item category L (subcontracting). The parent material has a valid BOM and some sub components as well. I see in CS03 that BOM is fine with validity dates for the parent material. A valid source list also exists for the parent material where SA is present as the source of supply with MRP indicator as 2. Now when i run MRP for the parent material using MD02 (NETCH), with indicators as below:
    Create pur.req.  2
    Schedule lines   3
    Create MRP list  1
    Planning mode   1
    i don't see any schedule lines in MD04. Instead it creates a PR that too without any source of supply.
    In master data for the parent material MRP type is PD with Procurement type F and special procurement key 30. I have checked and every thing seems to be fine still MRP run doesn't create schedule lines.
    Any help is appreciated. I can give more info if required.
    Thanks.

    Dear Rakesh,
    Scheduling agreement:An outline agreement against which materials are procured at a series of
    predefined points in time over a certain period.
    1.For this you have to first use ME31L for creating scheduling agreement and then ME38 for maintaining scheduling agreemnet
    schedule.
    2.Ensure in the source list after maintaining the material,vendor combination the setting for MRP relevancy is set to 2 - Record
    relevant to MRP,Schedule line generated automatically.
    Moreover you have to use value 3 for delivery schedule line which is one of the MRP control parameter while taking MRP run.
    So for the materials for which scheduling agreement exists,schedule lines will be generated.
    Check and revert back.
    Regards
    Mangalraj.S

  • When we run the MRP schedule lines are not generated automatically.

    Hi,
    In MD04 requirement date is on 5.12.2009.My source list validity starts from 1.12.2008 onwards.When i run the MRP for the material system generates the Purchase requisition instead of the schedlue lines.When i change the source list validity as 25.11.2008 now i run the MRP system generates the schedule lines.
    My question is why the system couldn't able to generate the schedule lines when the validity starts on 1.12.2008.In the source list we maintained the scheduling agreement and maintaine the MRP setting as 2.

    hi,
    Let me know your purchasing processing time defined in the SPRO settings for CBP?? It may be due to this also...
    Regards
    Priyanka.P

  • Schedule lines are not getting generated through MRP

    Hello Experts,
    While running MRP, we observed that the system is creating PR instead of schedule lines, although all the necessary prerequistes to generate schedule lines through MRP are maintained. For e.g.
    1. MRP Schedule line relevant indicator '2' is maintained in the Source List.
    2. Sch. Agreement dates and Source List validity dates are same.etc...
    Further after some analysis, we observed that if we change the source list validity from date to some back date then system is creating correct schedule lines.
    Example: Material M1; Planned delivery time 7 days; GR processing time 5 days; MRP Type PD; Lot Size WB;
    SA validity dates - 07.09.2011 to 31.12.2011
    Source List validity dates - 07.09.2011 to 31.12.2011
    If MRP run on 12.09.2011 and source list dates are retain same as mentioned above, system creates the PR.
    If MRP run on 12.09.2011 and source list dates changes to 05.09.2011 to 31.12.2011, system creates the schedule lines.
    Could you please let us know, why the system behave like this?

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

Maybe you are looking for

  • Web View not loading in Cocoa Applescript application?

    Hey guys...me again, and I need help, AGAIN, haha. I found a tutorial for web views in Cocoa Applescript because I couldnt find it anywhere, but it wont load. The web view does not display anything when the app is launching. I am using Cocoa Applescr

  • ValidateData.js files Error

    hi after uploading the updated validateData.js file and after that opening the Hyperion Planning web form im getting the error **"Problems with this web page might prevent it from being displayed or functioning properly "* Line : 54 Char: 4 Error: Ob

  • PDF Documents can not be printed

    Recently, after a new Adobe Reader updated, I can not print PDF document any more. (Word documents all can be printed.) Every time when I clicked "print", the error messag "Before you can perform print-related task such as page setup or printing a do

  • Upgrading Notebook RAM

    Hi, I've had my HP Pavilion m6 1006tx for about 11 months now and I have had success in most basic forms of gaming (minecraft and other not so intesive games). Now my computer has an Intel core i7-3612QM multi-core cpu running @ 2.1ghz to 3.1 with in

  • Problem with capturing video device

    I am using micro webcam but by some reason this device can not be detected even with JMF Registry editor. What could be problem.