Schedule lines are not generating properly in MD04
Hello All,
I have a issue in MD04, in which schedule line for Schedule agreement is not getting generated on the same day as sales order is created (09.05.2014). But Schedule line is getting created in different date. Because of which i am creating schedule lines manually at required dates.
Note: I have attached screen shot of MD04
Kindly help me to overcome this issue.
Regards,
Manoj
Hello Manoj
Please observe that there are rescheduling exception messages and rescheduling dates for your scheduling agreements. It generally happens when you have sales orders in the past and you don't allow "start in the past" for replenishment proposals generated by MRP.
Go to the customizing transaction OPPQ and change the customizing "start in the past". After that, run MRP again for your material and the schedule line dates should match the sales order. Please observe that firmed schedule lines wont't be changed.
BR
Caetano
Similar Messages
-
When we run the MRP schedule lines are not generated automatically.
Hi,
In MD04 requirement date is on 5.12.2009.My source list validity starts from 1.12.2008 onwards.When i run the MRP for the material system generates the Purchase requisition instead of the schedlue lines.When i change the source list validity as 25.11.2008 now i run the MRP system generates the schedule lines.
My question is why the system couldn't able to generate the schedule lines when the validity starts on 1.12.2008.In the source list we maintained the scheduling agreement and maintaine the MRP setting as 2.hi,
Let me know your purchasing processing time defined in the SPRO settings for CBP?? It may be due to this also...
Regards
Priyanka.P -
Schedule lines are not getting generated during MRP Run
Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
Can any one help me and suggest me what to be done in this case .
Thanks & Regards ,
NirmalyaDear,
Welcome to SDN,
In transaction OMDT you have to enable the indicator create schedule lines
In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
If u run MRP properly u will get schedule lines automatically in ME38.
Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
Regards,
R.Brahmankar -
Schedule lines are not in sink for PO
Hello Everyone,
We are using ECS.
So we create PO in SRM with some schedule lines and transfer it to the ECC system.
But sometimes the schedule lines are not in sink on both the sides because buyer update the schedule lines on SRM side.
So we need to check that is schedule lines in SRM and Basic quantity in SRM are same or not?
So is there any OSS note to check this?
Regards,
Khushbu.Hi,
In transaction OMDT you have to enable the indicator create schedule lines
In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
If u run MRP properly u will get schedule lines automatically in ME38.
Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3. -
Lines are not generated for holidays and sundays
Hi
creating a sale order shcedule lines are not generated for sunday for a particular plant .
Schedule lines are generated for subsequent monday only.
the plant calander is also correct
with regards
parthaHi
I would really double check the factory calendar ans the of the plant and sales organisation
regards,
Sidi -
Schedule line should not generate until SA release
Dear All,
We want when we run MRP against schedule agreement then "Schedule line should not generate until SA release"
AbhinayHI Abhinay Sachan ,
Bascially when we run the MRP the system generate the Schedule Lines for that schedule line we are doing release .....
If you have SA for a particular materail system gives the Error or warrning message based on the setting what we made...if it is error sysetm won't allow other wise it is warrning meaasge means we can cretae the PR for the particular materail i hope i wll help you
Regards
Murugan J -
Schedule Lines are not getting generated after MRP run.
Hi,
I have an issue where a SA exists for the parent material with item category L (subcontracting). The parent material has a valid BOM and some sub components as well. I see in CS03 that BOM is fine with validity dates for the parent material. A valid source list also exists for the parent material where SA is present as the source of supply with MRP indicator as 2. Now when i run MRP for the parent material using MD02 (NETCH), with indicators as below:
Create pur.req. 2
Schedule lines 3
Create MRP list 1
Planning mode 1
i don't see any schedule lines in MD04. Instead it creates a PR that too without any source of supply.
In master data for the parent material MRP type is PD with Procurement type F and special procurement key 30. I have checked and every thing seems to be fine still MRP run doesn't create schedule lines.
Any help is appreciated. I can give more info if required.
Thanks.Dear Rakesh,
Scheduling agreement:An outline agreement against which materials are procured at a series of
predefined points in time over a certain period.
1.For this you have to first use ME31L for creating scheduling agreement and then ME38 for maintaining scheduling agreemnet
schedule.
2.Ensure in the source list after maintaining the material,vendor combination the setting for MRP relevancy is set to 2 - Record
relevant to MRP,Schedule line generated automatically.
Moreover you have to use value 3 for delivery schedule line which is one of the MRP control parameter while taking MRP run.
So for the materials for which scheduling agreement exists,schedule lines will be generated.
Check and revert back.
Regards
Mangalraj.S -
MRP schedule lines are not created by MRP
Hi !!
I have a finished product ""111-2523-64"" and in its BOM i have a semifinished product ""111-2523-64-010"" produced(Inhouse)& three raw materials .
For the Raw Materials I have made the scheduling agreement & source list with indicator ("2"" create schedule lines automatically""
Problem -: Now when I run the MRP using T-Code MD02 the system is planning the finished & semifinished product
*but no schedule lines are created for the raw materials.*
Please Guide , Itz very urgent.Vijay , Pleae clear
I have a doubt
I am having one finished product & in its BOM i have three raw materials.
I have created the scheduling agreement for these three raw materials and source list too.
now when i run the MRp for finished product using t-code md02 the schedule lines must be generated for these three raw materials.
or
i have to run the MRP (seperately using T-Code Md01 ) for these three raw materials
Please guide , its very urgent. -
Schedule lines are not getting confirmed even though stock is there
HI,
i want to discuiss one sensitive issues which is a simple one.
my schedule lines is not getting confirmed even stock is there at sales order.
there is no delivery block.
there is no minimum stock level.
there is no credit check for that.
there is stock of 2 EA in that plant and storage location, but stock is not getting confirmed at sales order level or transaction level.
even stock is there it is going to avaliability check overview screen and giving stock confirmation after 12 days.
even i checked all the dates.............but its of no use.
what to do ?
after testing all the possible options i am taking help from
please help me in this regard,
regards,
balajitHi
you need to check the following.....
First check the Factory calander of your plant whethear some holidays or not
Second most importantly you have to check which stretagy group is assigned in the material . whethear it is make to order or make to stock. change it as make to stock.
"What happened if material stretagy group is make to order then from sales order system generate requirement of that material against that particular stock, that time system do not consider the unrestricted stock and not confirm schedule line."
Regards
Shambhu Sarkar -
Schedule lines are not getting generated through MRP
Hello Experts,
While running MRP, we observed that the system is creating PR instead of schedule lines, although all the necessary prerequistes to generate schedule lines through MRP are maintained. For e.g.
1. MRP Schedule line relevant indicator '2' is maintained in the Source List.
2. Sch. Agreement dates and Source List validity dates are same.etc...
Further after some analysis, we observed that if we change the source list validity from date to some back date then system is creating correct schedule lines.
Example: Material M1; Planned delivery time 7 days; GR processing time 5 days; MRP Type PD; Lot Size WB;
SA validity dates - 07.09.2011 to 31.12.2011
Source List validity dates - 07.09.2011 to 31.12.2011
If MRP run on 12.09.2011 and source list dates are retain same as mentioned above, system creates the PR.
If MRP run on 12.09.2011 and source list dates changes to 05.09.2011 to 31.12.2011, system creates the schedule lines.
Could you please let us know, why the system behave like this?Dear,
Welcome to SDN,
In transaction OMDT you have to enable the indicator create schedule lines
In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
If u run MRP properly u will get schedule lines automatically in ME38.
Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
Regards,
R.Brahmankar -
Schedule lines are not coming for HALB after MRP run
Dear All,
I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
Pls let me know if I am missing something and guide me further on this.
Thanks & Regards
Kundan KumarHi,
In transaction OMDT you have to enable the indicator create schedule lines
In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
If u run MRP properly u will get schedule lines automatically in ME38.
Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3. -
Schedule lines are not coming after MRP run for HALB material
Dear All,
I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
Pls let me know if I am missing something and guide me further on this.
Thanks & Regards
Kundan KumarDear All,
I am closing this thread. As the vendor mentioned in scheduling agreement is not a subcontracting vendor. Its a individual vendor.
Thanks for all the reply.
Thanks & Regards'
Kundan Kumar -
Scheduling lines are not created in mrp running
Line 1 & 2 are having same items with different schedule lines qty 250 & 275 nos. respectively. Stock was 250. System bokked stock 250 against line 1 & given proposed delivery date for line 2. In MM module, by running MRP system generated requirement only for 25 pcs.(may be it taken again stock 250 against line 2 in consideration while running MRP). This is happened in various cases.KINDLY HELP ME in solving this problem.
REGARDS,
G.V.SHIVAKKUMARHi,
With my experience I will share something:
1) Do you have valid Schedule Agreement?
2) Have you entered Sch. Agreement number in source list?
3) Have you selected MRP as " 2 " in source list?
With your earlier checks, please chekc these also.
Karthik Params -
Schedule lines are not modified when i change the requested delivery date
Hi
i have a issue when i am created sales order with requested delivery date 10.11.2011
and the same is copied in to item schedule lines as a 10.11.2011
before saving the order i change the requested derlivery date to 11.11.2011
this new requested delivery date is not dopied to schedule lines at item level (still is having 10.11.2011)
can any one tell me this is system standard behaviour or can we correct this
Thanks and Regards
KishoreHi DevarapalliKK,
I tried this solution & problem is solved.
--Go to VA01 & enter the material & qty
--Select the line item in VA01 & click on Edit
--Select Fast Change of & click on Delivery date & mention the Delivery date as 11.11.2011. & click on copy.
--Check the request delivery date in header level in sales tab it will change to 11.11.2011 & also check the Schedule lines in Item level the date will be 11.11.2011 & Save it.
Please let me know if your problem is solved
Regards
Pradeep -
MRP Run error " Schedule Lines not generating properly"
Hi Folks,
I am facing a typical issue with MRP Run.
Every time when I am running the MRP for a particular material I have made settings such that Schedule lines to be generated by maintaining the Source list and MRP relevancy as 2 in source list. Also I have fixed the vendor. Now my problem is I am getting Schedule lines for first run and Combination of Purchase requests and Schedule lines or only PRs for the next MRP run.. This is keep on repeating in such as way that the planning is shifting as said above for subsequent MRP Run.
Note that the initial settings during MD02 remain same for all run.
I want only schedule lines to be generated but not PR.
Pls advise and provide input where the wrong might be.
Quick responce would be appreciated.
Regards
ShashDear shash,
Check with What are the MRP control Parameters values which you are using for the MRP run.
In MD02, For Deleivery schedules run with value 3 - That's - Schedule lines.
The other options are 1 No schedule lines
2 Schedule lines in the opening period.
check with this & revert back.
Regards
Mangalraj.S
Maybe you are looking for
-
Please help!!!
-
Problem with variadic macros, Forte 6U2
The following code demonstrates a problem with namespace qualifiers used in variadic macros. The workaround (if you want to call it that) is to use triple colons as the scope resolution operator inside certain cases of variadic macros. The following
-
I have this weird problem on my Nokia N81. The screen is flashing all the time, and I can't solve the problem myself. When I restart the phone the problem disappears, but after the keys are locked and opened again it comes back. Can anyone help me? H
-
I cant audio chat with another mac user
I have a friend that has a an apple powerbook, and on Ichat it says that I can audio chat with him, but any time I or he try to connect and do that, it says that one or the other of us didn't respond. So, how can we fix this problem? Its driving both
-
Customer Trans Transaction Invoice Code Date Type Amount A001 01-JAN-2004 invoice 1000 A001 01-FEB-2004 Receipt -1500 A001 01-MAR-2004 invoice 2000 A001 01-APR-2002 invoice