Schedule local process chain

Hi, I have a requirement to schedule local PC to run every 8 hrs instead of daily as it does now.  Local process chain is called within a meta chain.  Is there a way I can schedule local process chain separately within a meta chain or I have to change schedule for the entire meta chain? 
Thanks!

No need to change schedule for the entire meta chain. U should schedule local process chain separately.
For local chain change mode
Right click 'Start Variant' -> Maintain variant -- Direct Scheduling -- Change Selections
Enter Date/Time... Select periodic Job
Periodic Values -- Other period -- enter 8 for Hour(s)
If u r using company calender -- Select 'Restrictions' -- enter Calender ID
Save -- Activate - Schedule
Local PC will run for every 8 hrs from the time u specified, and also run in metachain (once in a day if metachain runs daily)

Similar Messages

  • Schedule Local process chain (by fac calender) in a daily meta chain

    Hello SAP Gurus,
    We have a meta chain (e.g. M1) which runs daily. Within this meta chain (M1), a local process chain (e.g. LP1) is attached. This LP1 should run once a month on a Monday (defined in factory calendar). Please note LP1 can not be scheduled separately by factory calendar, as it depend on few activities in daily meta chain. I think LP1 can be scheduled by using the decision in meta chain. I have rough idea of the formula, but not sure. Can you please suggest what should be the suitable formula in decision to schedule it.
    Example formula:
    DATE_WEEKDAY1(Current Date, 'P1' ) = '1'
    Where
    DATE_WEEKDAY1 = Calculate weekday Number from Date
    P1 = Factory Calendar for one year. Only 12 days (Monday) are open. For example 17 Jan, 14 Feb 2011, etc

    No need to change schedule for the entire meta chain. U should schedule local process chain separately.
    For local chain change mode
    Right click 'Start Variant' -> Maintain variant -- Direct Scheduling -- Change Selections
    Enter Date/Time... Select periodic Job
    Periodic Values -- Other period -- enter 8 for Hour(s)
    If u r using company calender -- Select 'Restrictions' -- enter Calender ID
    Save -- Activate - Schedule
    Local PC will run for every 8 hrs from the time u specified, and also run in metachain (once in a day if metachain runs daily)

  • How to trigger a local process chain to run manually

    Dear Experts,
    In my company, I have a Daily process chain.
    In this Daily process chain, it contains many other local process chains which are grouped by modules.
    For example, I have created the following 3 process chains:
    - Accounts Receivables Process Chain which contains all the required process for loading FIAR data.
    - Accounts Payables Process Chain which contains all the required process for loading FIAP data.
    - Inventory Process Chain which contains all the required process for loading  Stocks data.
    These 3 process chains are scheduled one after the other in the main process chain which is called Daily Process Chain.
    FIAR needs to be successful before FIAP can run and Inventory chain will run only after FIAP is successful.
    Normally it runs without any problems.
    But recently, when the previous chain is successful, the next process chain does not get triggered to run.
    In the end, I have to manually execute the remaining process chains to start running.
    With this, all data are loaded, but the Daily Process Chain status for the day is yellow because it is not complete.
    Is there a program or method which I can execute or use to trigger the process chain to continue to run in the Daily Process Chain? If there is, please let me know so that I can avoid having to run the process chains manually one by one.
    Thanks in advance for your help.
    Regards,
    Shunhui.

    Check thid thread with the similar issue:
    Process Chain - Node untriggered.
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains

  • Local Process Chain

    Hi Friends !
    We have one "Main Process Chain' within the main process chain there is a "Local Process Chain". Main PC is scheduled at 2 PM.
    Ques : For the Local Process Chain, will the start variant be "Immediate"? Please advise.
    With Regards
    Rekha

    Rekha,
    There shouldn't be any problem even the local chain is set to "Immediate". it all matters with the Meta chain, the subsequent local chains are taken care during the Meta chain run.
    In the scheduling option of the Local chain start variant ,you can select either of the options Direct or Start using metachain.
    We have Direct shceduling for our local chains(with in the Meta chain) and there has been no problem.  this will be an advantage to maintain with the option "Direct shceduling", so that whenever you want to run the local chain seperately, there will not be any need to change any setting. else if you use "Start Using Meta chain or API", each time you have a need to run the local chain the setting has to be changed to "Direct shceduling" before executing it.
    Regards,
    Sudheer
    Edited by: Sudheer Kumar Kurra on Oct 17, 2011 9:30 AM

  • Local process chain used in Meta chain

    Hi,
    Suppose there is a Local process chain (X), and in it has scheduling options "Start using meta chain or API" selected. How can I know which meta chain is using this local chain.
    Something similar functionlity of "Where used list" which can give a list of meta chains where this local process chain (X) is used.
    Thanks.

    Hi Lohana,
    I think there no such functionality.
    Local chains means just you are calling from some other chain. But that it self a process chain. You are just linking in the chain through Local mode.
    Regards,
    Kishore Reddy.

  • Scheduling of process chain with background job

    Hello All,
                  I have scheduled the process chains through background jobs. I have copied the meta chain and created seven background jobs that is from Monday till sunday. The problem is most frequently the job gets cancelled with the message
    Process CHAIN, variant PAA1_GS001 is not scheduled waiting for event RSPROCESS 44NRPDWZ7CQUJ92ATDTY6368H.
    This is the variant for the next process after the start process. I tried by giving merge active versions, but one day the background job runs fine , but the next day it gets cancelled.
    If anyone has faced this issue before kindly let me know.
    Regards,
    Karthik.

    Hi,
    It seems to be there may be in probelm in Varients, so create a separate Varient for each PC and then activate the PC and execute.
    Thanks
    Reddy

  • Local Process Chains

    HI Guys,
    I am in the process of designing the process chains for data loading. I have a situation where I am planning to use local process chains in the meta chain. Situation is like this:I have created Meta Chain for Master Data loading, which is having 2 local process chains, one is for Attributes and another is for loading texts. I placed them in the sequential order. First Attributes chain and on successful completion of Attribute chain it should run the Text process chain. But in the system it executes the Attribute chain successfully but the text process chain is always in the YELLOW( in progress ) state even though in that process chain I have only start process. In the SM50 it shows two background process with the user id ALEREMOTE, but process chain never finishes. In the Messages of the Text process chain I see the message"Communication buffer delted from the previous run ".
    So I put the process chains in the parallel manner, meaning after start process of Meta chain I attached the two process chains so that they should execute simultaneously. But in this case too, Attribute local process chain gets executed but not the Text local process chain.
    We tried debugging the process in SM50, it seems that there is some infinite loop.
    If anybody has any clue then please reply back at your earliest. Your help is highly appreicated,
    Thanks.
    Santosh Taware

    first point, i think you can have single process chian for both attributes and texts one after other.
    second thing check in st22 if any dumps are occuring and check in the monitor in which step it is still running.
    reward if helps.

  • Two buttons "Activate" and "Activate and Schedul" in Process Chain

    What are the functionalities of the two picture buttons "Activate" and "Activate and Schedule" in process chain. In which case the "Activate" button should be used and in which case, the "Activate and Schedule" button should be used? If we click the Start variant of a process chain, then click "Change Selections" button which bring up the window "Start Time" where the buttons "Immediate", "Date/Time", "After job", and "After event" are listed at the top. If we modify at any of the above buttons, then after save this modification, we will have to click "Activate and Schedule" button to make it work, right?
    Thanks a lot and everyone's idea is greatly appreciated!

    Hi Kevin,
    Simply activating ur PC wont trigger ur PC. U have to use the other option Activate and Schedule then only the process chain trigger as per the scheduled option.
    U can give the Date/Time option and if it is a periodic job then u can specify the periodicity, later save all the things and when u come back to RSPC screen then click the 'Activate and Schedule' Button which looks like a clock.
    When u do this then ur process chain will be in released status.
    When ever if u activate ur chain will be with the Green color it means that its in Active status. But if u choose the second button then only ur chain will gets trigger..
    Regards-
    MM
    Assign points if it helps
    Message was edited by: vishnuC

  • ABAP Program for set local process chain failed

    I would like to execute ABAP Program in local process chain. If the condition is in the pre-defined bussiness rule, local process chain is set to fail.
    Currently I use ABAP and Raise Message Error = Message Type E for cancel program. After program is cancelled, local process chain don't know its status, wait for job SAP_CCMS_MONI_BATCH_DP  to determine status of process chain and then further execute subsequent process.
    I 'm not sure that our solution is right or not about set process chain to fail via ABAP. Please suggest us if there are other solution to set process chain as failed.

    Hi.
    Plz see my answer to similar question in [this thread|Re: Manage a message at the end of process chain on Web planning Application].
    Regards.

  • How to change local process chains job priority to A?

    hi experts,
    there are process chains are running in BW production system.
    for independent process chain when i forcefully change JOB PRIORITY from C to A last night it was executed successfully with PRIORITY A, but whereas i have meta chain in that there are some local process chains, though i forcefully change the JOP PRIORITY in PRODUCTION TO A, still those local chains were executed with JOB PRIORITY C only.
    Can you tell me the reason and solution to change the local process chain as well with JOB PRIORITY A.
    The metachain with JOB PRIORITY shows my userid, and the local chains shows BW_USER id.
    Regards
    venuscm
    Edited by: venu WAD on Nov 18, 2011 6:37 AM

    Check what's job priority for particular cube in TA RSRT->double click on your chain->menu Process chain->Attributes->Job Priority. Via this you can set priority as you need.

  • How to schedule the process chain

    hi
    guys,
                       how to schedule the process chain to run on thirsday and friday b/w 8pm to 11:55pm which has already been scheduled for daily loads at 9am to 11am?
    (Tell me the answer in detail)
    your regards
    suresh

    Hi Suresh,
    If you want to change in the Production system, you may not have the Authorizations. If you have authorization;
    1. Goto RSPC-->double click on the Process chain
    2. double click on the Start variant of the process chain-->Click on the EDIT button
    3. Click on the CHANGE SELECTIONS then click on the DATE/TIME Tab;
    4. There pls give from which date this process chain has to run to with your requirement time,
    then give the time and select the periodic job and select with your requirement.
    Save and exit.
    It is done!!
    Hope you understood.
    Regards,
    Ravi Kanth

  • Scheduling a process chain running in a specific hour

    hi,
    Is there any other way to schedule the process chain to run in a specific time besides using different meta chains to call the main process chain to do the loads separately.
    Can we do this by using one main process chain?
    for example, this is performed daily (hourly load: 4am load, 9am till 9pm load).
    willie

    Hi,
    <b>Process Chains</b>:
    From 3.x onwords to automate loads as well as process like Openhub,ababp
    programs or activations or etc., We are using this process chains.
    Coming to the major advantage
    Like eariler infopakge groups if any pak fails we need to trigger all the loads
    manully .wher as in Pchaing just correct that particular ipak and repaeat from that
    particular process .it will take care abt remaing subsequent chain .
    And also we can trigger parallel loads as well in this. Its much user friendly in monitoring.
    1)You can make the process chain to be trigered by an event.
    You do so by having the Job that start the PC start after an Event.
    Then you define your set of job's (thru SM37) and make sure these jobs fire the event that starts the PC.
    There is an ABAP program you can use that fires events (FM -> BP_EVENT_RAISE).
    2)In the Start process of your process chain, select Direct Scheduling and then click the Change Selections icon. This will bring you to the Start Time window where you can put in the Date/Time you want to start your process chain. At the bottom of this window, click on the Periodic job box and you will notice another icon way at the bottom called Period Values. Click this to determine what frequency the job should be rescheduled (ie. daily, weekly, etc.).
    3)you can do this by right-clicking on the start process, selection "Maintain Variant", choose "Direct Scheduling". Next select "Change Selections", pick your date and time, set your period values and you're done.
    You can Schedule process chain in background by right-clicking on the start process, selection "Maintain Variant", choose "Direct Scheduling". Next select "Change Selections", pick your date and time, set your period values and you're done.
    Hope it helps.
    *****Assign points if helpful*******
    Thanks,
    Amith

  • Schedule a process chain on last saturday of every month

    Hi Guys,
    My requirement is to schedule process chain on last saturday of every month. Is there any way to do this?
    I am already aware of below document. So please do not reply with the same. But please let me know if I am missing on anything.
    I have a requSchedule a Process chain on specific weekdays
    Thanks,

    HI R P,
    As mentioned in 'Schedule a Process chain on specific weekdays' document to use decision step. You can go with it just before setting actual data flow PC steps. Here a help for  you.
    Logic for decision step-
    Create a new custom function/method (say ABC) to calculate last Saturday of every month by using Standard Method 'FIRST_DAY_IN PERIOD_GET' (this gives last Sunday of every month) and use code logic accordingly to get last Saturday.
    Now, pick this ABC function from 'User- Defined function' section for your decision step formula.
    Hope this help.
    Thanks!
    Pratish

  • Scheduling a Process Chain

    Hi All,
    how to schedule the process chain to run three time daily
    say at 9 am then at 12 noon and at 3 pm daily
    Regards

    Hi Check in the followinf urls, you can do it either using Events or program..
    Triggering  the Process Chains at Particular Date using Events:
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/business-intelligence/s-u/triggering%20%20the%20process%20chains%20at%20particular%20date%20using%20events.pdf
    https://wiki.sdn.sap.com/wiki/display/Snippets/BI-ABAP(TriggerProcessChainsoneverymonth3rdand4thday)
    Thanks
    Reddy

  • Local Process Chain becomes inactive

    Hi BWers,
    We are having problems with our process chain wherein one of the local process chain becomes inactive. Here's the job log of the BI_PROCESS_CHAIN job. Will give points even for those who can give hints, better if solved.
    1. Job started
    2. Step 001 started (program RSPROCESS, variant &0000000753000, user ID BATCH_AP1)
    3. Version 'M' of chain YWAR_MPC_INTERRUPTS_MD_TD was saved without checking                
    4. Chain Is OK       
    5. Version 'A' of chain YWAR_MPC_INTERRUPTS_MD_TD was saved without checking
    6. Object with runtime number                          0' not defined
    7. Job cancelled after system exception ERROR_MESSAGE
    Thank You in advance!

    Hi
    you have pasted the process chain log, as the process was terminated, i required the dump information from the st22 and system messages from the sm21 concerned messages.
    Please provide the above infomation to resolve your problem.
    Regards
    Anwer Waseem
    SAP BASIS

Maybe you are looking for

  • What softwares need to be installed on BO server for SAP BI BO integration

    Hi All, We have SAP BI 7 Netweaver 2004 on solaris. Also we have a BO XIR2 server on solaris for reporting on SAP BI cubes. Please let us know what all softwares need to be installed on the BO server inorder to access the SAP BI Infocubes and BW quer

  • Why when I select a bright/rich color it wont let me and is instead a very dull version of that colo

    why when I select a bright/rich color it wont let me and is instead a very dull version of that color? Why can't I select a color and get exactly what I picked? WTF!!!!!!!!!!!!!!!!!!!!!!SOMEONE EXPLAIN THIS!!!!!!!!!!!!!!!!!!!!!!!!!

  • PHP user management system

    I have been using an ASP based user management system with an Access database and it has worked very well, however, I need to implement a similar system on a Linux server. I know you can password protect sections of the site using htaccess but I want

  • Cannot Create DWH tables through DAC Client

    Hi Folks, When i try to create DWH tables through DAC client I get the following error. Schema will be created from the following containers: Oracle R12.1.2 Universal Conflict(s) between containers: Table Name : W_ENT_QTR_D Column Name: DATASOURCE_NU

  • Budget control

    Hi In Budget head 8CVLWRKS64 for company code OM64. The entire budget is available . But when we raised service PO, it was aborted due to budget not available. Please give me some suggestions to solve this. And what tcode i need to use for this?