Schedule margin key

i am a beginner in SAP.
could some one tell me how to find the appropriate 'Schedule margin key'.
i was trying to create a new material under a new plant.
so while filling the 'Schedule margin key' tab what should i type,how can i find the appropriate schedule
margin key. what is the rule for that .when i type some value randomly ,the following message displays
the message says as " the scheduling margin key  does not exist for the plant"
could some one can help me.
thanks
zuhair

Dear Zuhair,
1) As i already told you, schedule margin key is for defining floats or Production scheduler
2) Floats are basically calculated in Days
3) if you press F4 for the schedule margin key then u can see
4) float before production float after production release period
5) this are nothing but  the days ( or extra days ) are given for production scheduler
for converting plan order to production order
6) and if we are maintaining floats ( schedule margin key ), then this will be copied to
production order. even scheduling considers this floats & calculates dates for plan order
Hope This Helps You
Regards
Madhu Kumar

Similar Messages

  • Opening period (schedule margin key) in forward scheduling

    Please advise whether opening period is used in forward scheduling that we specify in schedule margin key? if not, what will be the reason?

    Hi,
    Opening period is used only in Backword scheduling.
    b'cause opening period is period of workdays deducted from the start date to determine the creation date of order.
    reward points if useful to you.

  • Scheduling Margin key ( Float before production - Float after production)

    Dear Expert ,
    I maintain in material master float before and after production
    When i rescheduling in house production in routing and display the result i found the time for float is calculated in Interoperation time
    And I as i know Scheduled start & Scheduled finish determined the production dates only & FBefProd is time between basic start and Scheduled start and FAftProd is the time between Scheduled finish date & basic finish date
    Why he put it there at the time it's not actually maintained in production date ?
    Regards
    Rami

    Dear,
    In the routing, click on scheduling result push button,
    Here you can see how this interoperatioon time is calculated
    how much is Float before and after production.
    example-
    schedule margine key - 001
    float before production - 2 day
    Float after production - 1 days
    Routing data- for 1 qty - 24 hrs
    After you schedule in routing and see the details of scheduling result, the following result
    Basic start date - 30.11.2008
    Basic finish date - 03.12.2008.
    Scheduled start date - 02.12.2008
    Scheduled finish date - 02.12.2008.
    base qty - 1 TO
    Processing time - 1 day
    interoperation time - 3(all inclding floats)
    Total inhouse production time - 4 days
    Now repeat it for 2 qty, results are as below
    Basic start date - 30.11.2008
    Basic finish date - 04.12.2008.
    Scheduled start date - 02.12.2008
    Scheduled finish date - 03.12.2008.
    base qty - 2 TO
    Processing time - 2 day
    interoperation time - 3(all inclding floats)
    Total inhouse production time - 5 days
    I hope you got the idea.

  • Include the Scheduling Margin Key to the LOIPR02

    hello Experts,
    I am trying to find some details on how to include the Scheduling Margin Key(SAP1 in our case) to the IDOC before passing it to the
    ME.
    Please let me know if there is any standard way of achiving this.
    We are using : SAP ME 6.0 and MII 14.0
    Thanks in advance,
    Pradeep D

    Here is a document how to extend an iDOC
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/80677e5d-dc79-2c10-b7bb-a7e99767c8f6?QuickLink=index&…

  • Make optional from material master of Schedule Margin Key

    Hi PP Guys
    I am using MRP Type PD & there is no floats in schedule margin key.
    So client want make a optional of schedule margin key from material master.
    I tried from L-G --> Material Master --> Field Selection --> Assign Fields to Field Selection Gruops / Mainatin Field Selectio to data Screens.
    Bur here this filed is optional.
    I think some relation from MRP Type or What ?.
    Pls suggest.
    Regards
    Ashish

    Dear Asish,
    This is the required master data to create order also, based on this only all your order dates are calculated, like when to release the order, start and finish and finaly material available to dispatch.
    So for MRP calculation and to promise the delivery to sale order also it is must.
    When u create order this gets copied to the order this u can see in production order Genaral data tab.
    i hope u r clear
    sree

  • The scheduling margin key 000 does not exist

    Hi guys
    There is query from my side please do help me out
    to get a solution for the following query
    i was asked to give schedMarginKey = 000 while creating
    a material for MRP(material requirement Planning)
    but if i give schedMarginKey = 000 and save this it shows the
    following error
    The scheduling margin key 000 does not exist for plant JOP1
    is ther any transaction code to overcome this?
    please do help me out in this!!
    Regards
    Jino.

    Hi
    You can miantain the schedule margin key using t.code OMDC.
    reward points if useful
    Thanks & Regards
    Kishore

  • Schedule Margin Key behavior during External Procurement and Inhse Prodn

    Hi Gurus
    Could you give me detailed illustration in a visualising manner the Application of Schedule Margin Key in
    "External Procurement for Raw Material" and "Inhouse Production for Production Order" with one scenario
    Stating each and every floats in more detail
    a) Opening Period -applicable for ext and inter
    b)Float before prod-applica only for external

    Hi,
    The complete explaination for your requirment is available in help.sap.com, under MRP-->scheduling section
    Regards,
    Nataraj

  • MRP & schedule margin key issue

    Hi All,
    My client is running MRP on daily basis they have maintained schedule margin key 001 with opening period as 0010.but while running MRP & MD04 they
    found below are the issues.
    We have tested many times using SMK as 000 & 0010 but every time system displayed below errors.
    Some times they are not getting the purchase requisition created in time (System should drop the purchase Requisitions according to parameters maintained in material master).
    Some time system creates planned order instead of Purchase Requisition (Their requirement is to create purchase requisition always)
    They get the exception message past due planned order
    As per my understanding there will be problem in buffer period.How can we avoid these exception messages & how can we create always PR instead of pl order.
    I will appericate if anybody suggest me how can we rectify above mentioned causes.
    Thanks,
    Ravindra.

    Hi Caetano /Ram
    Thank you for replies.I have following doubts on your reply
    I understood if I create Variant including only PR system will display always PR in MD04.
    1.If I run MRP using option 2 PR in opening period in this case system behave like same or do I need to include this parameter in variant
    2.How can I avoid exception message"Past open due" for Ex :- 10,20,30 etc... permentaly in MRP run?
    I have not tested solution yet I hope if I create MRP group & during background MRP run if I create variant with parameter 1 (PR only) it will create PR.
    Can you pls assist on SMK? For your clarification check below is my actual scenario
    if I assigned SMK with 000 (All periods like opening period,FAP,FBP & release period is 000) then what happen in MRP run if I made your suggested setting is system means it will always create  PR.
    If I assigned SMK with 001(opening period 0010,FBP 5,FAP 2 ,release period =5) also
    if I maintained GR time= 2 days,
    Pl.delivery time =10 days  in this case will above setting  work? if i run MPR using opening Period as well as PR only.
    Kindly correct me if i am wrong.
    Thanks,
    Ravindra

  • Configuration of Scheduling Margin Key

    Good day!
    Where can I add a "scheduling margin key"?
    Thanks!

    Hi,
    There are many paths for defining the same;
    Go to path SPRO > Materials Management > Consumption-Based Planning > Planning > Define Floats (Scheduling Margin Key) and add it for your Plant.
    Also you an add it in path SPRO > Production > Material Requirements Planning > Planning > Scheduling and Capacity Parameters > Define Floats (Scheduling Margin Key)
    Also SPRO > Production > Shop Floor Control > Operations > Scheduling > Define Scheduling Margin Key
    Also you can maintain under transaction OPPQ for you Plant under "Floats" button.

  • Scheduling Margin Key

    Hello Friends
    This is regarding inspection lot, as per my knowldge, Inspection lot will be based on purchse order item level. Is lot will be based on PO header level. if so could u please explain and the details?
    Thanks
    Vijayakumar TVN

    Hi,
    Inspection lot will be based on PO Item level.
    When ever purchasing team do Gr with respect to PO inspection lot will be created
    so when ever there is a GR one Inspction lot will created
    For example if there is a PO for 100Kg and during GR the buyer will do GR 100 kg for 5 times
    From my understanding 5 inspection lot will be created
    Set Control inspection lot to 'X' (For each purchase order item, batch and
    storage location) for inspection type 01, in the inspection setup tab in
    material master.
    regards

  • Input schedule: Derive key for key range from Dimension member properties

    Hey guys,
    I'm facing the problem within a input layout. There are three keys in the row key range.
    The first row key is filled by the members of a dimension. The second and third row
    should be filled by the dependencies shown in the dimension members.
    Example:
    Dimension:
    - Order number
    Properties:
    - Client (also implemented as standalone dimension where all required characteristics are maintaned)
    - Costcenter (also implemented as standalone dimension where all required characteristics are maintaned)
    Entries in dimension members of Ordern number:
    Order number, Client, Costcenter:
    1000, 10, 511
    2000, 10, 533
    3000, 12, 511
    4000, 15, 588
    Entries in dimension Members of Client:
    10,11,12,13,14,15,16,17,18,19,20
    Entries in dimension Members of Costcenter:
    511,533,555,588
    My row key range is defined as follows: Exp1: Order number, Exp2: Client, Exp3: Costcenter
    For Planning purposes i need a input schedule that schows only the valid combinations shown above
    in master data of order number. Is this possible or do I have to leverage script logic to use dependencies shown in master data for reporting oder planning purposes !
    Cheers,
    Moritz

    Hi Moritz,
    As Nilanjan said, this is not really possible with a basic EVDRE at the moment. Your best bet is probably to either build your own solution using EVEXP, EVGET, and EVSND, or to use an EVDRE based on only the Order # to get the values and an EVSND based on the Order # and the properties of the Order # in the AfterRange of the EVDRE.
    I actually like the second option a lot better (EVDRE with EVSND in the AfterRange) because for larger queries the read performance should be better and it will be more maintainable in the long run.
    Ethan

  • Enter scheduling Key - BAPI_MATERIAL_SAVEREPLICA

    I am using BAPI_MATERIAL_SAVEREPLICA to create new Material Header in a reference plant. The reference plant does not have a scheduling margin key. I am getting error 'Enter the scheduling margin key'. The BAPI is expecting the plantdata-sm_key. I have tried passing space but that does not work. Please help

    Hi Sabita,
    You can have a proper understanding of the functionality of BAPI  and be familiar with what data you need to be filled in the fields.
    BAPI_MATERIAL_SAVEREPLICA
    FUNCTIONALITY
                   Use this method to create new material master data or change existing material master data. Every time this method is called, data for one or more materials can be transferred.
    When new material master data is created, the material number, the material type and the sector must be sent to the method. Furthermore, a short text and the language in which the short text has been created, have to be entered. When data is being changed, only the material number need be entered.
                  First, the appropriate fields in the tables (for example, CLIENTDATA) have to be filled with data by the user. These fields must also be flagged as the method data can only be written to the database if this is the case. The user must also provide data for the appropriate fields that have been selected in a checkbox table (for example, CLIENTDATAX). Checkbox tables exist for tables that do not contain language-dependent texts (MAKT, MLTX), European article numbers (MEAN) and tax classifications (MLAN). More than one data record can be created for a material in these tables (for all materials transferred to the method).
    CALL FUNCTION 'BAPI_MATERIAL_SAVEREPLICA' "BAPI for Mass Maintenance of Material Data
      EXPORTING
        noappllog =                 " bapie1global_data-no_appl_log  Do Not Write an Application Log
        nochangedoc =               " bapie1global_data-no_change_doc  Do not write change documents
        testrun =                   " bapie1global_data-testrun  Switch to Simulation Session for Write BAPIs
        inpfldcheck =               " bapie1global_data-inp_fld_check  Response if Fields Are Inactive
      flag_cad_call = SPACE       " bapie1global_data-testrun  Call From CAD System
      no_rollback_work = SPACE    " bapie1global_data-testrun  Override Rollback Work
      flag_online = SPACE         " bapie1global_data-testrun  No ALE Field Selection
      IMPORTING
        return =                    " bapiret2      Return Parameter
      TABLES
        headdata =                  " bapie1matheader  Header Segment with Control Information
      clientdata =                " bapie1mara    Material Data at Client Level
      clientdatax =               " bapie1marax   Update Information for CLIENTDATA
      plantdata =                 " bapie1marc    Material Data at Plant Level
      plantdatax =                " bapie1marcx   Update Information for PLANTDATA
      forecastparameters =        " bapie1mpop    Forecast Parameters
      forecastparametersx =       " bapie1mpopx   Update Information for FORECASTPARAMETERS
      planningdata =              " bapie1mpgd    Change Document Structure for Material Master/Product Group
      planningdatax =             " bapie1mpgdx   Update Information for PLANNINGDATA
      storagelocationdata =       " bapie1mard    Material Data at Storage Location Level
      storagelocationdatax =      " bapie1mardx   Update Information for STORAGELOCATIONDATA
      valuationdata =             " bapie1mbew    Valuation Data
      valuationdatax =            " bapie1mbewx   Update Information for VALUATIONDATA
      warehousenumberdata =       " bapie1mlgn    Warehouse Number Data
      warehousenumberdatax =      " bapie1mlgnx   Update Information for WAREHOUSENUMBERDATA
      salesdata =                 " bapie1mvke    Sales Data
      salesdatax =                " bapie1mvkex   Update Information for SALESDATA
      storagetypedata =           " bapie1mlgt    Storage type data
      storagetypedatax =          " bapie1mlgtx   Update Information for STORAGETYPEDATA
      materialdescription =       " bapie1makt    Material Descriptions
      unitsofmeasure =            " bapie1marm    Units of Measure
      unitsofmeasurex =           " bapie1marmx   Update Information for UNITSOFMEASURE
      internationalartnos =       " bapie1mean    International Article Numbers (EANs)
      materiallongtext =          " bapie1mltx    Long Texts
      taxclassifications =        " bapie1mlan    Control Data
      prtdata =                   " bapie1mfhm    Production Resource Tool (PRT) Fields in the Material Master
      prtdatax =                  " bapie1mfhmx   Update Information for PRTDATA
      extensionin =               " bapie1parex   Reference Structure for BAPI Parameters EXTENSIONIN/EXTENSIONOUT
      extensioninx =              " bapie1parexx  Checkbox Structure for Extension In/Extension Out
      forecastvalues =            " bapie1mprw    Data Transfer for Forecast Values
      unplndconsumption =         " bapie1mveu    Data Transfer for Unplanned Consumption
      totalconsumption =          " bapie1mveg    Data Transfer for Total Consumption of Material
      returnmessages =            " bapie1ret2    Substitute Structure for Return Parameter BAPIRET2
        .  "  BAPI_MATERIAL_SAVEREPLICA
    Regards,
    Soundarya.

  • *MRP unable to create Delivery Schedule Lines in MM Scheduling Agreement*

    Hi Experts,
    I need your help...
    The issue is, in-spit of maintaining Source List with an u201CScheduling Agreement with item No.u201D & u201CSource List Usage in MRPu201D as 2 (Record relevant to MRP. Sched. lines generated automatically), MRP run does not generate Schedule Lines, instead PRs are created.
    Please help me to understand such behavior and fix the issue as the requirement is to generate Schedule Lines only.
    Thanks,
    Pratap

    Hello
    Please check
    1) Source List maintained properly in terms of Material # ; plant # ; proper POrg ; Schd Agr # and line item# ; proper validity date & MRP relevant indicator
    2) Please also check Quata arrangement if you are using. whether % is maintained correctly against the vendor
    3) MD03 , Delivery schedules- should be 3
    4) check your planning horizon whether it is NETCH or not
    5) check material master -MRP2 view, Procurement type is F- external procurement, schedule margin key if you are using
    if everything above is set, then I feel it should work
    Also please verify-
    lot size, safety stock and the corresponding prod volume for MRP input v/s the stock available in MMBE
    example.
    MD04, we can see the open del lines.
    if SS = 50 , prod volume is 150
    1) if MMBE shows 200 then it wont generate any schedule.
    2) if MMBE is 180 and your lotsize is 40, then after MD03, you will have a schedule line of 40 (provided if everything is set properly)
    Please ensure there are NO open delivery lines . if you find such in MD04, then please close open delivery lines
    in calculation of MRP, system considers such open delivery lines are going to receive and no additional schedule line generated even after MRP run
    thanks

  • Scheduling problem with delivery date in purch.req and requirement date

    Dear all,
    I have the problem, that the calculated delivery date in the purchase requisition does not correspond with the requiement date of the production or planned order.
    I would like to use planned delivery times in the material master.
    Example:
    Planned delivery time: 20 days
    Todays date 01.10
    Case 1)
    Requiement date of planned order 10.10
    Case 2)
    Requiement date of planned order 20.09
    This situation can happen in our envirnoment, as the engineering process still continues after start of production. In this case I would like to have the following result:
    Case 1)
    Delivery date is 10.10 minus the goods receipt time
    Case 2)
    Delivery date is day of MRP or one or two days more
    I made the setting that dates in the past are not allowed. This solves my first smal problem. I tried to set the scheduling margin key but these settings do not help me, as they are relevant for all materials. I need of course individual planned delivery dates per material.
    So, I want to change the standart MRP procedure that in the case of the "wished requirement date" not the calculated date is beeing taken, but the "wished date". Usually you receive an exeption for this case and you would need t solve this manually. But this we dont want to do.
    Can s.o. please help me? Thank you all very much, I really dont know what to do in this case.
    With best regards,
    Bjoern

    The question cannot be answerd by SAP standart as I see. We will go through a workaround.

  • Regarding Scheduling issue

    Dear All
                   I have one issue regarding Scheduling
    1.we have one FG, one SEMI FINISHED material and one RAW material.
    2.The In house production days for FG  is One  day. if demand is given on may 15th,the schedule date for FG is 14th may,upto here it is clear.
    3.SEMI FINSHED material is produced by vendor i.e. SUB COTRACTING process. The planned delivery time is two days. the requirement is on 14th may ,so the release date should be on 12th may and delivery date should be 14th may. am I correct?
    4.DEMAND is given on 15th may, run the MRP, Planned order is generated for FG and SF. The Schedule start date for FG is 14th may, it is correct.
    5.The issue is for purchase requisition, the release date on 13th and delivery date on 15th may, because of this total scheduling going wrong.
    Pl give the solution for this issue so that system will give proper release date and delivery date.
    If any configuration s thr or not?

    Hi
    For this you need to have schedule margin key with flot before process should be one day. Then your requirement will work. So config a scheduling margin key and enter it in Material master of finished and Semifinished materials.
    regards
    Antony