Scheduling Agreement conditions

Hi,
1.Conditions in info record and contracts and general conditins are time dependent conditions.
2.Conditions in P.O always time independent.
3.Withe the doc type you can control wheather time dependent conditins are available for quotation and scheduling agreement.
Can you please explain the 3 rd comment.

for SAs - it depends on settings in SPRO for your SA document type if  time-dependent or time-independent conditions can be specified....when a scheduling agreement is created, the system carries out price determination only if the "Time-dependent conditions" indicator is deactivated @ SPROMMpurchasingSAdefine doc types---there 10th column on screen "time - D.C"
you select or untick the indicator
yogesh

Similar Messages

  • Change in Scheduling agreement condition value

    Hi Friends
    i have a scheduling agreement with a CVD condition maintained as 10%. the SA is not yet closed and the CVD value has to be changed to 8%. i cant update the value as it is not coming from condition record. cant delete the material line item also. please suggest any alternatives.
    thanks in advance

    Have you created SA with info record?
    can you able to maintain the CVD at info record level with effect from say 26.06.2009 as 8%
    keeping other conditions unchanged
    this is just a thought

  • Scheduling agreement condition type default deletion indicator in backend system

    Dear team,
    our business process is that-
    In SRM system scheduling agreement is created. once its approved from SRM in Backend ECC R3 system the same is getting replicated.
    But in few of the cases its been obserbved that the condition pricing is flowing but with deletion indicator selected by default.
    I have checked the IDOC for the same but there is no value found flowing from SRM to ECC.
    Even searched for the same Material & same vendor in some cases only observed with deletion indicator.
    For entire scheduling agreement the deletion conditions are updating that is for all line item in scheduling agreement.
    There is no info record exists.
    Appreciate if anyone can throw some light over this.

    Appa K wrote:
    Even searched for the same Material & same vendor in some cases only observed with deletion indicator.
    What is the special cases ?
    I hope you are using time dependent condition for you SA document type.
    Check is it fetching from last PO or SA ?
    What is happening, when you are trying to create SA manually via ME31L for the same material and vendor?

  • Schedule Agreement Conditions

    Hi Gurus,
    I want all those conditions that are present in Pricing procedure and those appear in PO to appear in Schedule agreement too. I am not getting the conditions except discounts in SA. I want conditions like Packing & Forwarding, Frienght to appear in SA too.
    I am getting these conditions only when I make the SA document type as Time Indipendent which I do not want. That mean I want these conditions to appear in SA even when it is time dependant.
    I appreciate speedy response and reward...
    Regards
    Shash

    Hi,
    In pricing procedure please give all the condition and assing the schema group to the vendor .try to create scheduling agreement definitely all the condition will come there
    G.Ganesh Kumar

  • Scheduling Agreement - Conditions not getting copied from Contracts

    Hi All,
    Requirement: Global outline agreements with scale prices will be created in SRM which will be into ECC as Contracts. Scheduling agreements will be created referecing the Contracts and the conditions with the scale prices needs to be copied into the scheduling agreement.
    Issue: We could create Global outline agreements in SRM and are getting replicated into ECC as contracts successfully. Conditions and the scale prices are not getting copied into the Scheduling agreement from the Contracts.
    Please guide.
    With regards
    Krishna

    Hi,
    I couldnt reach out a solution for this problem.
    SRM Version: SRM 5.0
    Yes. We create Scheduling agreements referencing the contracts.
    With regards
    Krishna

  • Auto Update of conditions in Scheduling Agreement

    Dear experts,
    i have a requirement like this..
    when we create a scheduling agreement ...we enter material,vendor,target qty and validity date ,price and enter tax code.
    After that we maintain condition types Vendor, material and Plant level....
    So in the same scheduling agreement we are adding one more material and giving same tax code.....Is there any possibility,so that system should copy condition types when we choose this tax code....rather than entering again and again for each material....
    Please do reply me...
    Thanks and Regards
    MK

    Hi MK,
    Are you asking about pricing conditions or tax conditions?
    Tax conditions flow auto when you enter tax code
    Whereas pricing conditions if those are manual conditions have to be maintained
    manually
    for conditions to flow automatically you have to customize the condition type for "changes can be made" with manual entries indicator as B
    and maintain the condition record
    Diwakar
    reward if useful

  • BAPI_SCHEDULE_MAINTAIN - Scheduling Agreement  (Deleting Item Condition)

    Dear Friends,
    My requirements is change or create the Scheduling Agreement - Schedule Lines (ME32L). I am using BAPI -->
    BAPI_SCHEDULE_MAINTAIN
    Its updating correctly, but automatically the item condition price details are deleted.
    1st time i am facing this issue.
    kindly help to rectify this issue. I am waiting for your valuable response.
    FYI - this is my code
            t_schedule-item_no    = t_alv_output-it_no.
            t_schedule-sched_line = t_alv_output-sh_no.
            WRITE t_alv_output-de_dt TO t_schedule-delivery_date.
            t_schedule-quantity      = t_alv_output-de_qt.
            t_schedule-stat_date = t_eket_qty-slfdt.
            APPEND t_schedule.
            t_schedulex-item_no       = t_alv_output-it_no.
            t_schedulex-sched_line    = t_alv_output-sh_no.
            t_schedulex-sched_linex   = lv_x.
            t_schedulex-delivery_date = lv_x.
            t_schedulex-stat_date     = lv_x.
            t_schedulex-quantity      = lv_x.
            APPEND t_schedulex.
          CALL FUNCTION 'BAPI_SCHEDULE_MAINTAIN'
            EXPORTING
              purchasingdocument = t_alv_output_head-po_no
            TABLES
              schedule           = t_schedule
              schedulex          = t_schedulex
              return             = t_return.
    I am also tried
    BAPI_SAG_CHANGE
    . this also updating the Schedule Lines. but deleting the item condition records.
    Thanks & Regards,
    Durai V

    Kindly check notes 1034912 and 1046851
    Regards
    JP Milton

  • Condition Types in Scheduling Agreement(Urgent)

    Dear Experts.
    This is a query with reference to my earlier issue Changes in Condition ME32L.As per suggestions, to get validity periods i have clicked on Time dependent Condition In SPRO settings Under Define document Types.
    After that i am not able to enter Custom Conditions while creating a Scheduling Agreement.So i tried by removing this Time dependent setting,then was able to enter Custom Conditions...
    But i need to see validity periods too when i change condition types through ME32L...
    So,Please give me appropriate Suggestion....
    Thanks and Regards
    MK

    I'm not sure about your own pric proc, but in standard it should works, and also its apply per organization level.
    RM0000 and RM1000                                                      
        Control the price determination process in POs, quotations, and    
        scheduling agreements.                                             
        Both calculation schemas require 2 condition types for the gross   
        price: one for automatic price determination (standard: PB00) and  
        one for manual maintenance (standard: PBXX).                                                                               
    RM0001 and RM1001                                                      
        Determine which condition types you can enter in purchasing document
        headers with time-dependent conditions (e.g. contracts).

  • Conditions in scheduling agreement.

    Hello Guru,
    I am creating scheduling agreement through ME31L.While entering conditions I am only able to enter few conditions like  gross price,discount etc.which are in pricing procedure RM1002.When tried to enter condition FRA1 got error "Condition type FRA1 is not in procedure A M RM1002".
    1) My query is how procedure RM1002 is picked up by system as when created normal order for same vendor purchase order pricing procedure is shown as RM1000.
    2) How for same vendor different pricing procedure are picked up in different document as procedure is picked up from schema group in vendor master.
    Regards
    Vinay

    Hi,
    Thanks for feedback.
    1) Upon entering  purchase organization data in ME31L i am getting pop up "Purchasing org.  xxxx is not assigned to company code.Please enter company code".Upon entering company code i can proceed ahead.
    But with same purchasing organisation  with same company code standard order is created without any pop up.
    2) yes Same vendor.
    3) No  vendor subrange
    4) It is not STO .
    Regards
    Vinay

  • Delivery cost in scheduling agreement having time dependent condition

    Hi experts,
    We have one peculiar requirement.
    We have palnt at indonesia.  We are doing import there from india.
    Our requirement is as follows.
    1. We should use scheduling agreement with time dependent conditions.  Because we want to track the price changes and sometimes we want to retro pricing effect and revaluate it.
    2. We want to add importers vat and import tax.
    3. But those tax amount should not get added into inventory
    4. During MIRO it should get accounted to vendor.
    We could succeed this by removing "Time dependend condition" check in document type config.
    But our client is definitely required the point no 1.
    But when we activate time dependent condition check, during MIRO those conditions are not appearing.  But if you remove that check, it is appearing in MIRO accounting.
    Can any one suggest suitable solution?
    Or SAP MIRO will not permit this scenario?
    regards,
    K.Sundaresan.

    delivery cost will not work if u remove the tick Time dependend condition for SA
    SAP MIRO will not permit this scenario
    so u will have to decide what is more important to u and act accordingly
    Solution will be u ask client what is mor imp for there company
    as SAP will not support MIRO for deliver for time dependent condition
    I had a talk with SAP on this and they have told that
    SAP will not support MIRO for deliver for time dependent condition
    AS in Case of imports in india we need to do MIRO before GR
    hope this hel;sp

  • Pricing Condition in scheduling agreement

    Hi Gurus,
    I'm working with scheduling agreements and I figured that whenever I create scheduling agreements, pricing condition PB00 gets defaulted to the scheduling agreement,
    Can you guys be kind enough to tell me what configuration is driving this?? How can we make changes to the config settings so that I can have a condition type of my choice assinged to the scheduling agreenment??
    More over I have a requirement to have a tiered pricing in scheduling agreement. I do know that this is driven by SCALES in SAP however as per my requirements I need to have SCALES per formulas. In the condition type configuration we do have a field for SCALES where we can assign the formulas but whenever I click on this field a screen pops up with some ROUTINES.
    Can someone tell me how can I define the ROUTINES and the ABAP formula for this ROUTINE so that I can have my tiered pricing conditions accomplished??
    Any feedback on this will be highly appreciated!!
    Thanks folks,
    Dhaval Joshi

    Hi Ramesh,
    Thanks for the heads up. I looked at the config for the schema dtermination and I see that the pricing procedure RM0002 has not been assinged to any vendor POrg schema in this configuration.
    I then looked at the config for the condition type PB00 --> pricing procedure RM0002 has been assigned to the condition type PB00 and since we don't have any entries maintained for RM0002 in the schema determination config I was just wondering if this is what is influencing the automatic proposal of the condition type PB00 in my scheduling agreement.
    Also can you please tell me what is a difference between a Purchasing Document (BIG) and Purchasing Document (Small) in the schema determination config.
    All I wanted to accomlish here is my teired pricing to work when I assign scales on the condition type in the scheduling agreement ( not in the PIR)
    What currently happening in my case is ....
    Example: Scale From 1 pc - 100.00 USD
    from 50 pc - 90.00 USD
    from 100 pc - 80.00 USD
    Target quant. 100 pc
    schedule lines 30 pc
    20 pc
    The problem is  that the goods receipt of 30 pc is valuated at the price 80.00 USD It always takes a lowest price on the scale.
    I've tried looking for OSS notes and also looked enough on the forums but I could not get any resolution to this question.
    I would appreciate if I could get any heads up from your side.
    Cheers,
    Dhaval

  • Change history (for perticular condition type) in scheduling agreement

    All SAP Gurus,
    We have a scheduling agreement, in which certain condition (condition type for freight condition) value have changed several times.
    Where we can find the changes in the value of this condition type?
    Regards,

    Hi Rajan,
    You should be able to see in
    Item -- Statistics -- Changes. You can find that line item wise.

  • Planned Conditions in Scheduling Agreement

    Dear Expert,
    We are using Scheduling Agreement for external procurement of materials,for few materials Condition like ZNMC Cess are applicable,In Purchase Order these conditions are automatically pickup if it is maintain  in MEK1,In Scheduling Agreement these conditions are not coming automatically,How to Maintain these conditions directly,Please advice
    Regards,

    SOLVED

  • Update price condition in scheduling agreement (ME32L)

    Hi,
    I have to update scheduling agrrement (ME32L).
    The input data that i would like to update are price amount, validity start date and valdity end date.
    Is there any function or bapi which can be used to update.
    Any help in this would be highly appreciated.
    Thanks,
    Mandeep

    hi
    did you update the conditions and validity period of scheduling agreement?  If yes then plz send me the details of parameters
      ITEM_COND_VALIDITY           =
      ITEM_COND_VALIDITYX         =
      ITEM_CONDITION                  =
      ITEM_CONDITIONX                =
    I am also facing the same issue.
    waiting for your reply.

  • Pricing Conditions in Scheduling Agreement

    Hi All,
    When i create a Scheduling Agreement, i Want to Add conditions like Discount and Freight along with the net price.
    Where can i see these condition types as i see in Po?

    hi,
    After defining the material select the item and press shift +f6 ie. item conditions...
    and for header condition firstly go into the header details(hat button) and then press(ctrlshiftf4)
    You can see there to enter...
    Regards
    Priyanka.P