Scheduling Agreement: Planning in Frozen Period

Hi,
as you know you can set 2 fixed periods for scheduling agreements and configure SAP to create fixed or non fixed schedule lines inside the period.
Do you know if there is anyway to configure the system in order to prevent it to create new schedule lines inside this period?
I explain better: we define a contract with the vendor and enstablish that there is a frozen period of 90 days, meaning that from here to 90 days your delivery schedule can't change in any way. Therefore i set the first fixed period of SA to 90 days and tell the system to create fixed schedule lines in that time interval, so they won't be changed. But if a new requirement in the past or within the 90 days comes out and the MRP runs with automatic schedule lines creation enabled, then i get more fixed schedule lines in the past and contractual parameters are violated.
Any way to prevent this?
Thanks and best regards

Hi,
Thanks for all your replies, mentioned settings are already maintained and I did check all the queques for any error.
OLTP transfer setting is also maintained as immediate..so I don't need to transfer change pointers through report, as it should immediately be transferred to ECC.
My question is: We have report - create release (transaction - /SAPAPO/PWBSCH1) to release scheduling agreement, so I believe for scheduling agreement we need to use above transaction.
It seems to work, as I can see IDOC but its in failed status.
I have following question:
- Does scheduling line release work in a different way than purchase req, in APO. I did test with purchase req and it was immediately transferred to ECC.
Has somebody worked for schedule agreement scenario in APO?
Any insights would be appreciated.
Thanks
Sharad

Similar Messages

  • Schedule Agreement - Planned delivery time

    Can you still use planned delivery time when using Scheduling Agreements?  Or does this field need to be set to 0 for the delivery lines to get created properly when using JIT/FRC schedules?  If we cannot use Planned delivery time, is there another field that can be used to hold the Vendors lead time.  We want to take this into consideration when determining the end date of the Scheduling Agreement.

    Hi,
    the planned delivery time field on the material master is designed to be used when it cannot find the correct data from the info record. It should always contain the planned delivery time that should be applied if the vendor is not specified.
    the same field on the info record should contain the planned delivery period for the appropriate vendor.
    This field does not have to be 0 if you are using JIT etc.
    Steve B

  • Scheduling Agreement & Planning Time Fence

    Hello,
    I read a lot of articles on Planning Time Fence and the MRP Types P1 to P4 that goes with it. And I have tested it out in a Testing Environment.
    But I can't get it to do what I need.
    This is a normal planning with no PTF and MRP Type PD.
    Sometimes we have false requirements that show up in the past due to human error. When this happens, MRP rolls during the night and adds a bunch of deliveries in the past to cover the requirement.
    I wanted to use the PTF to prevent this. Meaning that extra deliveries would get added by MRP but after a PTF and not Firm deliveries. So that once the error is corrected, MRP rolls again and deleted all the extra deliveries it added.
    ** Only P2 and P4 adds deliveries after the PTF, but I need it to act normal on a day to day basis aswell and have MRP create deliveries like the print screen above. To add non-Firm deliveries after the PTF is just in rare cases of human error.
    Not sure if my explanation is clear.
    Patricia

    Hi Patricia,
    The planning time fence is there to stop MRP from making changes to requirements that fall within the planning time fence.
    Your planning time fence is a rolling period which shifts by 1 day each day and is calculated as of the current date. Yesterdays date is passed so it would not make sense for a planning time fence to use a date in the past to start it's calculation.
    Everything that falls before the end of the planning time fence will not be changed by MRP and you will see that all these schedule lines in MD04 will have an * assigned meaning they are firmed for MRP.
    If you manually add schedule lines in the past, the planning time fence will not stop you from doing this. The planning time fence will only stop MRP from making changes.
    By the way:
    If you manually add requirements to the scheduling agreement then MRP will never change these requirements as these are fixed requirements.
    If your customer would add requirements in the past or you add independent requirements in the past and your current stock does not cover the requirements the system will generate schedule lines and will put these directly after the planning time fence with an exception message assigned to them.
    As a side note:
    I always wonder why such questions arrive in the forum as this is something that can be very easily tested in the test environment.

  • Scheduling agreement planning in APO

    Hi,
      Currently I am planning in APO (SCM 5.1) and have scheduling agreement (type - APO Sch. Agree.)
    Planning run created - Schedule lines and using transaction - /SAPAPO/PWBSCH1, create release.
    Then I went to external procurement master data and clicked on SA release and executed Schedule line.
    I could see it green.
    But if I check ECC, I don't see Schedules lines in agreement.
    Do let me know if I am missing any steps or any configuration which I might have missed.
    In the "Partner" tab within external procurement master data, I changed medium to "XML" and can see one failed IDOC.
    How scheduling lines are released from APO to ECC? is it not standard "pulbication of planning result"
    Thanks
    Sharad

    Hi,
    Thanks for all your replies, mentioned settings are already maintained and I did check all the queques for any error.
    OLTP transfer setting is also maintained as immediate..so I don't need to transfer change pointers through report, as it should immediately be transferred to ECC.
    My question is: We have report - create release (transaction - /SAPAPO/PWBSCH1) to release scheduling agreement, so I believe for scheduling agreement we need to use above transaction.
    It seems to work, as I can see IDOC but its in failed status.
    I have following question:
    - Does scheduling line release work in a different way than purchase req, in APO. I did test with purchase req and it was immediately transferred to ECC.
    Has somebody worked for schedule agreement scenario in APO?
    Any insights would be appreciated.
    Thanks
    Sharad

  • Scheduling agreement with Delivery and Periodic billing

    Hi Gurus
    Can anybody suggest the process if available, having scheduling agreement -
    delivery --- and periodic billing.
    Thanks
    MM

    Hi there,
    Is is possible. Define a scheduling aggrement with mentioning the required delivery dates. This will convert as schedule lines.
    When the item is due, delivery will be created.
    Define a periodic billing type & assign it to your billing type. Define the validity period for your periodic billing.
    Make sure you define the copy controls from delibery - invoice.
    Regards,
    Sivanand

  • Release date and release no of Scheduling Agreement

    Hi All,
    I have a problem with Scheduling agreement.
    I have created a scheduling agreement with long validity period.
    I maintained delivery schedules within that validity period.
    I have generated forecast schedules. then using ME84, creating a releases.
    the problem is occurs here.
    it was not updating the release no and release date for the schedule line.
    still it is showing a *yellow light* .
    where is the problem and why it was not updating.
    and can u please explain the process and significance of those lights.
    Thanks in Advance.
    Regards
    Kishore

    Verify the table T161M has the values
    kvewe = 'B'
    kappl = 'EL'
    druvo = 1
    kschl = LHPA
    as mentioned in the code.
    The solution is add in SPAD the

  • Scheduling agreement with Consumption based planning

    Dear Experts,
    I Have a Scenario,
    I need to Bulit a Laptop which is a Finished Material, and the Components like Hardisk, Processor, Ram, Casing, Monitor are my Rawmaterials. By using these rawmaterials we are building the parent material.
    My Client requirement is 1) Plan and schedule the requirement
    2) Replenish the stock based on consumption based planning.
    My query is
    1) How should i proceed for mm based procurement ?
    2) Does i need to create scheduling agreement for rawmaterials and and maintain schedule lines ?
    3) For which materials i need to run the MRP ? weather its parent material or Component material ?
    4) What are the sequence of process need to be carried out ?
    Required ur valuable inputs on this.
    Best Regards
    SAP LEARNER
    Edited by: JAVEED AHAMED on Feb 12, 2010 8:34 AM

    Hi
    Consumption based planning and Scheduling agreement are two different functions.
    Consumption-based planning is based on past consumption values and uses the forecast or other statistical procedures to determine future requirements. The procedures in consumption-based planning do not refer to the master production schedule. That is, the net requirements calculation is not triggered either by planned independent requirements or dependent requirement. Instead, it is triggered when stock levels fall below a predefined reorder point or by forecast requirements calculated using past consumption values.
    A form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period.
    With release documentation (in the standard system, document type LPA)
    The schedule lines in the system have internal character. This means that you can change them in any way you wish. The schedule lines stored in the system are not transmitted to the vendor until you explicitly create a scheduling agreement release (which may take one of two forms: a forecast delivery schedule or a JIT delivery schedule).
    The release documentation allows you to display the releases transmitted to a vendor over a certain period in order to establish exactly when you transmitted which information to the vendor.
    Without release documentation (in the standard system, document type LP)
    The schedule lines immediately have official character, i.e. they are immediately transmitted to the vendor the moment you save them (transmission time-spot 4 for messages). There is no release documentation in this case.
    It cannot be explained in few lines. You need to study the below link.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/75/ee1fa755c811d189900000e8322d00/frameset.htm
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/7d/c2821c454011d182b40000e829fbfe/frameset.htm

  • Planning horizon and scheduling agreements

    We have a planning horizon that goes out 1 year.  However MRP stock requirements is showing planned orders for scheduling agreements that go out beyond the planning horizon.
    Is there a reason MRP sees these MRP elements with dates well beyond the planning horizon of 1 year?

    Hi,
    In MRP we can run the MRP with Planning run Type  With indicator
    NETCH(Net change planning) and NETPL(Net change planning in the Planning Horizon)
    Planning Run Type in the Initial Screen
    Use
    You use the planning run type (Processing key indicator in the initial screen of the planning run) to determine which materials are to be planned.
    Features
    There are three different planning run types:
    During regenerative planning, all materials are planned for a plant. This makes sense when you are carrying out the planning run for the first time as well as later during production if data consistency cannot be guaranteed due to technical error.
    The disadvantage of regenerative planning is the fact that the system has to deal with high capacity loads because all materials are planned, including materials, which may not be affected by the planning run.
    To overcome this disadvantage, it makes sense during production to carry out the planning run using the net change planning procedure. The only materials that are included in the planning run are those, which have undergone a change relevant to MRP since the last planning run, for example, because of warehouse issues or sales orders, changes to the BOM and so on.
    The net change planning procedure makes it possible for you to execute the planning run in short intervals, for example, in daily intervals. You can thus always work with the most up-to-date planning result.
    You can use net change planning in the planning horizon to shorten the MRP planning run even further. The system then only plans materials that have undergone a change relevant to MRP within the planning horizon. In order to also plan changes outside of the planning horizon, you must execute the net change planning run in greater time intervals.
    You define the planning horizon per plant or per MRP group in Customizing for MRP in the IMG activity Define planning horizon. The planning horizon should be at least long enough to cover the period when sales orders are received. It must also accommodate delivery periods and the total lead times of the materials.
    In single-item planning, you can only choose between net change planning and net change planning in the planning horizon. Regenerative planning is not useful, because the material has already been defined and does not have to be determined after the evaluation of the planning file.
    The system automatically flags the materials that have undergone a change relevant to MRP with a corresponding planning file entry in the planning file (see also  Checking the Planning File and  Planning Run Type).
    Regards,
    nandha

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • Planned delivery cost for the scheduling agreement

    Hi Experts
    1. I have an requirement to post Invoice ver. for the Planned delivery cost (freight,customs duty,CVD etc) against the Scheduling Agreement just like Import Purchases with checking off the GR Based IV Indicator before doing the GR
    I tried it but its giving me that no delivery costs are Planned in the Scheduling agreements it runs fine in case of the PO because PO is a time independent.  Please inform how to post the same for schedule agreement with time dependent indicator on. I tried switching off the time dependent indicator and the system allowed, but my requirement is to Post I.V for the delivery cost with the time dependent indicator on.
    Appreciate if you can suggest something in this case Urgently .
    2. Aother issue is we have some uploaded Scheduling agreement from legacy system with Time dependent conditions. For this we need to post planned delivery cost in Miro. Since the system is not allowing to post, how to about for this. Shall we enter the delivery cost in unplanned delivery cost in Miro and post.  Please suggest if any alternate solution is available.
    Regards
    Arvind

    Hi,
    As you know if the delivery cost document is not posted during GR the
    delivery cost is not proposed during invoice (MIRO). Planned delivery
    cost will be proposed in invoice only when there are records in EKBZ
    table. The EKBZ table will be updated when delivery cost is posted
    during GR itself.
    Please ensure in the PO itself thatr the conditions have been defined
    properly with the relevant amounts and values.
    During GR when planned delivery cost conditions are present in PO,
    system checks for values in amount field. Then only appropriate
    calculations will be done for delivery cost and planned delivery cost
    document will posted during GR and hence updates EKBZ table.
    Solution to this issue is described in below steps,
    1) reverse the invoice document
    2) reverse GR document.
    3) You have to give values in amount field in relevant conditions ZGDS
       in the PO.
       If you face any issues changing the values, delete above conditions
       and put it again manually and give values in amount field also.
    4) Post GR once again, delivery cost document will also be posted.
       You can check it in PO history.
    5) During invoice select Item + planned delivery cost and post the
       invoice. If you need planned delivery cost to be posted separately,
       then you can post individual invoice for item and delivery cost.
    Please note it is not possible to post delivery costs for documents with
    multiple accountassignments. 
    For your second question, I am afraid I can not answer. Please open a new ntry in the forum, so that someone else can answer it.
    Best Regards,
    Arminda Jack

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned elivery time in scheduling agreement

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"".  System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) .r processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 11.07.2008
    Please Guide . How can i correct this.
    Regards
    Rahul Bhardwaj

    dear colleagues,
    please check in OPPQ , external procurement,  and set the flag 'scheduling'
    best regards

  • Change in validity period of Scheduling agreement

    Dear all,
    I extended validity period of existing Scheduling agreement,
    But In MD04 it is not creating Schedule lines.
    Regards,
    Nitin Patil.

    hi,
    you shd also check the validity period of the source list maintained for this schedule agreement..
    Regards
    Priyanka.P

  • Condition values and validity periods of a Scheduling agreement .

    Dear Friends,
    I have one querry .Where does (in  Database table) ,  the condition values and validity periods of a Scheduling agreement stored .
    Thanks and regards in advance.
    Vijay.
    Edited by: vij kot on Sep 9, 2008 12:09 PM

    Hi,
    Refer Tables
    KONH - Condition Header
    KONP - Condition Item
    KONV - Conditions (Transaction Data)

Maybe you are looking for

  • Can we upload data in ASO Cube version 11.1.2

    Hi, I have a requirement where in ASO cube users need the ability to enter their plan data into the ASO application. Do we need to create Transparent Partition for that. I have an ASO and Hyperion Planning cube and in my Planning cube I have more num

  • Not generating a spool output in the background job

    Hi Team, I have an alv report and If I schedule the program using SM36 transaction it is not generating the spool ouput. If I run the same program in background mode when we use se38 and select execute in background in program menu and it works succe

  • No phone service for 3 days

    Completely unacceptable service and billing for a major utility/service provider.  I have not been able to send or receive calls for three days and can't get an explanation or estimated time of recover.  There's not a business contingency plan? The o

  • PDF Printer not saving files; 9.5.5 (pro) with Windows 7, 64 bit

    I imagine that the root of this issue has to do with compatibility between the OS 64 and and 32 bit application of Acrobat 9.5.5. The installation has been uninstalled, reinstalled, and fully repaired. Initially, while printing from powerpoint (but a

  • My Ethernet won't connect online anymore

    Just a little while this was working. I am using a school network so I have no control over the router, it's public. I had to change my MAC address in order to connect and for a couple of months it's been working, even today. I don't know what change