Scheduling agreement type LP

Hi Experts,
We have a schedulling agreement (type LP) with quantity of 100 EA. Delivery schedule is maintained with 150 EA and while saving we get a message that 'Scheduled quantity 150 EA greater than target quantity 100 EA' and allows us to save by ignoring the message and we are able to do GR for 150 EA quantities.
We dont want to have the delivery schedule to be allowed with greater than target quantity. Kindly let me know the control settings that needs to be maintained so that the delivery schedule cannot be maintained more than the quantity in SA.
Regards,
Venkata Prasanna.R

If it is maintained as error message, it does not allow me to maintain delivery schedule more than target quantity of 100 EA. Also the overdelivery tolerance is maintained as 20 %, so it should allow me to maintain delivery schedule of 120 EA, but it does not allow me to maintain greater than target quantity of 100 EA. Please let me know your comments.

Similar Messages

  • BOM in Scheduling agreement (Type LZ)

    HI
    I am using scheduling agreement (Type LZ) for maintaining my sales plan for a period of 4 months. (1st one month - daily & subsequent months as weekly requirements). Ii would create delivery and invoices for each supply.
    Pricing previously was based on the finished product (basic price for product was available). SO there was no problem.
    <u>New requirement:</u>
    finished Product above - is made up of components. Now, price should be derived from components. For this I have enabled SD Bom for my finish product.
    But the problem is when i use the Finish product code in scheduling agreement type LZ, the BOM doesn't explode (it explodes in other scheduling agreement types, say LP)
    Clarification:
    1. Is it possible to calculate price of the higher level material by summing up the components' price?, with out BOM explosion
    2. Is BOM explosion possible in scheduling agreement with delivery schedule (LZ).
    Note:
    1. Necessary settings for item category & BOM master already in place.
    2. BOM is exploding in sales order and other sheduling types, except doc type LZ.

    If it is maintained as error message, it does not allow me to maintain delivery schedule more than target quantity of 100 EA. Also the overdelivery tolerance is maintained as 20 %, so it should allow me to maintain delivery schedule of 120 EA, but it does not allow me to maintain greater than target quantity of 100 EA. Please let me know your comments.

  • How I restrict Scheduling agreement type for specific Purchase organization.

    Hello Experts,
    I have created Scheduling agreement type (ZLT). I want to restrict this agreement type for specific purchasing organization.
    I have search many threads but I didn't get solution.
    Is it possible through Configuration or user exit.
    Kindly give me solution in details.
    Thanks,
    Ranjit Kumar.

    hi,
    I don't think that there is standard configuration to restrict Purchasing document type for purchasing group. you can restrict this trough user authorization or you can make user exit development.
    Regards,
    mukesh

  • BAPI to create and update scheduling agreement (type LZM) in ECC

    Hi,
    We have a requirement to create and update scheduling agreement of type LZM in ECC from an external system.
    Is there a BAPI available for this in ECC 6.0 which can be used?
    The integration is using PI.
    Regards,
    Srivatsan

    Hello,
    Please use the T-code "SE93" and then click on Display option after entering the T-code. After entering into the detail screen of the T-code, you shall find option to click on OBJECT LIST and then enter into the Function Group. Now enter the T-code and then click on function module and a list of function module will be displayed in referrence to the T-code. 
    For your easy reference i have also mentioned the flow.
    SE93 --> Use tcode (eg. VA01) > display> Object list ---> Function Groups --> Tcode ---> Function module.
    Regards,
    Sarthak

  • How to change the scheduling agreement type

    Dear experts
                    By mistake i created wrong sched agreement type in va31, is there any possibilityto change the  sched agreement  type?
    Regards
    Rajakarthik

    Dear   RajaKarthik.
    As per  my  concern  why  dont  you  delet  the  scheduling agreement   and  creat  new one.
    i think   it  will  help you.
    jeevan.

  • Scheduling agreement LPA type

    DEAR ALL,
    while updating the Firm zone and trade off zone  in Scheduling control for scheduling agreement type LPA.
    system donot show the  END OF FIRM ZONE and END  OF TRADE OFF ZONE
    what setting was missed . pls clear me .
    Thanks
    v raj

    Hi Raj,
    In SAP IMG > Material Management > Purchasing > SA > Define document type
    Check the Field Selection for the Document type. Eg;-LPA = LPL
    Then in SAP IMG > Material Management > Purchasing > SA > Define Screen Layout at Document Level
    Over there Check on:-  LPL
    Scheduling Control > Firm/Trade-off Zone if flaged in optional.
    Hope this will solve your issue.
    pherasath

  • MRP Run with Scheduling Agreement

    Hi All,
                Can anyone explain the the Scheduling Agreements, we are running the MRP with schedule lines generated.I want to know the complete cycle with the T-codes in sequence they are executed.My requirement is business people need a demo of the Scheduling Agreement,type LP,LPA how they work and difference between LP and LPA.They run the MRP everyday.
    Thanks,
    Kris
    Edited by: Csaba Szommer on Sep 19, 2011 12:52 PM

    Hi,
    The basic difference between LP and LPA  is the way that the schedules are communicated to the vendor.
    for more clarity please refer the blow links.
    LP and LPA in scheduling agreement?????
    Difference between LP and LPA scheduling agreements
    http://it.toolbox.com/wiki/index.php/Scheduling_Agreement
    Thanks.

  • Scheduling agreement planning in APO

    Hi,
      Currently I am planning in APO (SCM 5.1) and have scheduling agreement (type - APO Sch. Agree.)
    Planning run created - Schedule lines and using transaction - /SAPAPO/PWBSCH1, create release.
    Then I went to external procurement master data and clicked on SA release and executed Schedule line.
    I could see it green.
    But if I check ECC, I don't see Schedules lines in agreement.
    Do let me know if I am missing any steps or any configuration which I might have missed.
    In the "Partner" tab within external procurement master data, I changed medium to "XML" and can see one failed IDOC.
    How scheduling lines are released from APO to ECC? is it not standard "pulbication of planning result"
    Thanks
    Sharad

    Hi,
    Thanks for all your replies, mentioned settings are already maintained and I did check all the queques for any error.
    OLTP transfer setting is also maintained as immediate..so I don't need to transfer change pointers through report, as it should immediately be transferred to ECC.
    My question is: We have report - create release (transaction - /SAPAPO/PWBSCH1) to release scheduling agreement, so I believe for scheduling agreement we need to use above transaction.
    It seems to work, as I can see IDOC but its in failed status.
    I have following question:
    - Does scheduling line release work in a different way than purchase req, in APO. I did test with purchase req and it was immediately transferred to ECC.
    Has somebody worked for schedule agreement scenario in APO?
    Any insights would be appreciated.
    Thanks
    Sharad

  • Excise base amount is not changing as per the scheduling agreement

    Sub: in migo excise base amount is not changing as per the scheduling agreement type LP ( time dependent ).
    I have created the scheduling agreement type LP with time dependent.
    I have maintained the price value in two validated period i.e
    01/07/08 to 31/07/08 price is 100 rs.
    01/08/08 to 31/08/08 price is 200 rs.
    I have maintained the delivery schedule on
    15/07/08 of quantity 1 nos.
    When I am doing the goods receipts for the scheduling agreement on
    Document date I am giving 15/07/08.
    Posting date I am giving 15/07/08.
    I am giving the posting date in the excise also 15/07/08.
    After item ok.
    When I will the excise base value it is taking 200 and also excise duty is also calculating on 200.
    When I will post the document
    The stock account and GR/IR account is taking 100 only
    And excise duty is posting for rs: 200 only
    Why the excise base value is not changing as per the validity period.
    What setting I have to do the change the excise base value as per the validity date maintained in the time dependent .
    regards
    jrp

    dear sir
    doc date and posting date i have given 15/07/08 and also excise posting date i have given 15/07/08,
    but excise base value it is taking Rs:200 .
    in inforecord price date category 5-goods recepit date i have given
    yes i ahve changed the excise base value it will post , if i will not change the excise base  value i will post rs:200 only and GR/IR clearing account will post Rs100 only.
    why the excise base value will not take based on the time dependent.
    regards
    JRP

  • Third party sales using Sales Scheduling agreement.

    Hi All,
    We have a scenario where we are creating a scheduling agreement type LP for a main material and its returnable packaging.
    We are using item category group as BANS and LEIH respectively. We are able to create the agreement, trigger a Purchase requisition from the main material and also a outbound delivery.
    We are facing issue when we are trying to create billing document.
    Has anybody worked on such scenario and suggest us as to why this issue?
    Also we want to create a commercial invoice before final billing document. Plz suggest the process of commercial invoicing in SAP and the output type to be used for the same.
    Rgs,
    AJ.

    Dear Atual,
    You have stated " you are facing issue in billing" however, you have not mentioned what is the issue!!!
    Secondly, I did not understand
    " Also we want to create a commercial invoice before final billing document. Plz suggest the process of commercial invoicing in SAP and the output type to be used for the same.
    What do you mean by commercial invoice and Final Billing document? for me it looks the same. SAP standard provided output normally does not serve the customer requirment. Hence it will be always custom developed. Standard output type is RD00, you can copy and define your own output type. Attach the custom developed program and layout as applicable.
    Regads
    Murali

  • I- doc for creation/updation of Sales Scheduling Agreement

    Hi,
    Could anybody tell me details regarding the idoc details, for Sales Scheduling Agreement Creation & its updation.
    Need the - Process code, Message type , Basic type & other details
    Will the Idoc type be of DELORD. We will be getting the flatI file from the client for the creation of Scheduling Agreements
    Appreciate the help
    Thanks

    For Automotive Suppliers, and SD scheduling agreement types 'LZ', etc. 
    Normally, the users create the SD Scheduling Agreement using VA31 first.
    Then the Idocs, which are processed through IDOC_INPUT_DELINS_START, simply update the SA.
    One SA may continue to be updated by EDI releases for many months.   
    On an 'LZ' type SA, there is a tab for Forecast Delivery schedules and a tab for JIT Delivery schedules.
    At the simple level, which tab gets updated is controlled by the value in E1EDP10-SCREL.
    For inbound 830 / DELFOR / VDA4905 transmissions, usually map SCREL = '03' which updates the Forecast Delivery Schedule.
    For inbound 862 / DELJIT / VDA4915 transmissions, usually map SCREL = '02', which updates the JIT Delivery Schedule.
    The search criteria in the search box you see on VA32 are similar to the key Idoc fields which are used to find the SA which needs to be updated.
    Hopefully the users have access to transaction EMFOR to monitor the inbound Idocs and reprocess if necessary. (This is easier than workflow or WE02/BD87)
    From EMFOR, Idocs in status 51 can often be processed in foreground. This is the quick way to figure out why you are getting a status 51. But I suspect it's because the SA was not created first.

  • Determine distribution of GOA as a Contract or a Schedule Agreement

    Hello,
    We are using SRM 5.5 Server and R/3 4.7 as a backend system. Uptill now we have distributed our GOA by maintaining the same transaction type on SRM and the backend for contracts. However now we have a requirement to be able to distribute GOA as a scheduling agreement for certain product categories. When we choose Scheduling Agreement on item distribution screen, GOA is again distributed as a Contract.
    How can we maintaine settings or use a BADI to be able to distribute the GOA as a Schedule Agreement type that R/3 uses instead of the contract type we maintained?
    Thank you,

    Hi Gaia,
    you can manipulate the transaction type via BADI BBP_CTR_BE_CREATE
    in SRM. Use a Case logic for field iv_logical_system to switch the transaction type
    before IDoc transfer to the Backend System. Just ensure that the transactio type
    with valid number range is available in the Backend System.
    Cheers,
    Claudia

  • How I get a Information about how many Scheduling agree

    Dear friend,
       Can any one tell me a process ,How I get a information about how many scheduling agreement or Schedule lines created with in given time.Any standard tcode available  ?
    Regards
    Abrar AHmed

    Dear Abrar
    - To see how many scheduling agreement is created for a given period, use VA05, click on [Further sel criteria] and tick the box against [Sales Document type]  Now input the scheduling agreement type and execute.  You will get list of all scheduling agreements created within the specified period.
    - You can see how many line items are created in a sale order for a given period via VA05.
    thanks
    G. Lakshmipathi

  • How are deliveries automatically created from scheduling agreement?

    How are deliveries automatically created from the schedule line of the scheduling agreement? Can anybody explain this step by step? Can we use the code VL10BATCH for this purpose? If we can, how is this code used?
    Thanks in advance.

    hi
    A customer scheduling agreement is an outline agreement with the customer containing delivery quantities and dates. These are then entered as schedule lines in a delivery schedule. You can either create schedule lines when you create the scheduling agreement or you can create them later.
    You fulfill a scheduling agreement by creating the deliveries in the schedule as they become due. You process deliveries for a scheduling agreement in exactly the same way as you process a normal delivery. After you have carried out the delivery, the system updates the Delivered quantity field in the scheduling agreement item with the delivery quantity.
    The scheduling agreement is used as a basis for delivering a material. The customer sends in scheduling agreement releases, referred to as delivery schedules, at regular intervals to release a quantity of the material.
    Document Types
    To configure document types for scheduling agreements, choose Sales -> Sales Documents -> Sales Document Header -> Define sales document types in Customizing for Sales and Distribution.
    The R/3 System contains the following document types for component suppliers:
    LZ - Scheduling agreement with delivery schedules (no external agents)
    LZM - Scheduling agreement with delivery orders
    LK - Scheduling agreement with delivery schedules (external agents)
    ED - Delivery by external agent (consignment issue)
    EDKO - External agent correction
    RZ - Scheduling agreement returns (no external agents)
    KAZU - Consignment pick-up for external agents
    KRZU - Consignment returns for external agents
    Item Categories
    To configure item categories for scheduling agreements, choose Sales -> Sales Documents -> Sales Document Item -> Define item categories in Customizing for Sales and Distribution.
    The system determines the following item categories for the related document types in
    documents containing materials with item category group NORM:
    Item category LZN for scheduling agreement type LZ
    Item category LZMA for scheduling agreement type LZM
    Item category LKN for scheduling agreement type LK
    Item category KEN for document type ED
    Item category EDK for positive corrections (or the manual alternative EDK1 for
    negative corrections) for document type EDKO
    Item category REN for document type RZ
    Item category KAN for document type KAZU
    Item category KRN for document type KRZU
    Schedule Line Categories
    To configure schedule line categories for scheduling agreements, choose Sales -> Sales Documents -> Schedule lines -> Define or Assign schedule line categories in Customizing for Sales and Distribution.
    The R/3 System contains the following schedule line categories for component suppliers:
    L1, BN, L2, and CN for item category LZN
    E4, E0, E5, and BN for item category LKN
    L2 for item category LZMA (standard for delivery order processing)
    Schedule Line Types
    To configure schedule line types for scheduling agreements, choose Sales -> Sales Documents -> Scheduling Agreements with Delivery Schedules -> Define schedule line types in Customizing for Sales and Distribution.
    Creating Scheduling Agreements
    To create a scheduling agreement with delivery schedules:
    1. In the Sales menu http://Ext. choose Scheduling agreement ->Create.
    2. Enter scheduling agreement type LK (standard) or LZ (external agents) and the
    relevantorganizational data.
    3. Choose ENTER.
    4. Enter the following data:
    Sold-to or ship-to party number
    Purchase order or closing number
    Material or customer material number
    You can use the Description field to identify the scheduling agreement. For
    example,
    you could enter the model year for a particular production series.
    The system allows up to 35 digits for a customer material number.
    Rounding quantity
    Usage
    Choose Goto -> Header -> Sales to enter the usage at header level, or Goto ->
    Item-> Sales A to enter it at item level. The system proposes usage S, for series, as default in both cases.
    Planning indicator
    Choose Goto -> Header ->Sales.
    Target quantity
    Mark an item and choose Goto -> Item -> Sales A
    Partners
    For scheduling agreements with external agents , choose Goto -> Header
    ->Partners to enter the external agent as forwarding agent and special stock partner
    on the partner function screen.
    5. Create a delivery schedule
    Mark an item in the scheduling agreement and choose Goto -> Item -> <Delivery
    schedule>. Enter:
    A delivery schedule number and date
    The cumulative quantity received by the customer
    The last delivery confirmed by the customer
    A schedule line with date, time, and quantity
    To enter additional data in the delivery schedule, choose DlvSch.Hdr (delivery schedule header).
    configuration:
    img->SD->Sales->sales document->scheduling agreements with delivery schedules->
    step1: define schedule line types
    schedule line types are not schedule line categories. Schedule line types are used for information purpose only.
    stds are 1. fixed date 2. backlog 3. immediate requirement
    4. estimate
    step2: maintain planning delivery sched. instruct/splitting rules
    The planning delivery schedule is an internal delivery schedule used to plan requirement s more efficiently.  It is sub divided into 3 parts
    2.1 delivery schedule splitting rules
    2.2 dly schedule instrusctions
    2.3 assign dly schedule splitting rules
    step3: define sales documents type
    step4 : define item categories
    step5: define schedule line categories
    step6: maintain copy control
    PROCESS
    step1:  create scheduling agreement
    VA31
    enter SP,SH valid from, valid to,
    goto ITEM OVERVIEW tab
    enter material, rouding qty
    select ITEM  click on FORECAST DLSCH
    enter different dly dates and qties
    save it.
    step2: create sales order with reference to above
    step3: create delivery
    step4: create billing
    regards
    krishna

  • VA31 - Create a scheduling agreement

    Dear Gurus,
    When trying to create a scheduling agreement using VA31, I input the following data:
    Sched. Agreemt Type
    Sales Organization   2200   France, Paris
    Distribution Channel 14     Service
    Division             00     Cross-division
    Sales Office         2200   Office Paris
    Sales Group          2200
    Now, I cannot choose any Scheduling agreement type from a drop down menu as none seems to be linked or created for that sales area.
    Can anyone help me create a list of Scheduling agreement I can choose from?
    Thanks
    Chris

    Scheduling agreement type should have been created in VOV8 and then this document type should have been assigned to your sales area 2200 / 14 / 00 in OVAZ.  Check whether you have assigned your scheduling agreement type in OVAZ.
    thanks
    G. Lakshmipathi

Maybe you are looking for

  • View external HTML page in a custom object container

    Hi to All, I have created a custom TAB in a standard transaction. I want add a html page(external link) in custom container (like a browser). On the forum I did't find anything, can you help me? Best regards. Umberto

  • UI Shell - how to allow ADF Library Bounded Task Flow to close itself

    Hi Richard Further to my other post, we're having lots of fun with the UI Shell, it's making mockups very easy. Question for you though based around the functionality defined in the UI Shell whitepaper. Say we've created our UI Shell application, and

  • Hierarchy authorization default pick

    Hi ,    I have got a profit center hierarchy which is used in the reporting in the selection screen in BW7.0 . I had created authorisations and its working fine through RSECADMIN. but i have got a question, if i leave the selection screen variable pr

  • Since update to 10.6.8 can't export images from powerpoint and also other programs

    Ever since I updated my software to 10.6.8 I can't export images from Powerpoint or from a graphing software GraphPad Prism.  It's really frustrating.  I had no problems at all until this update. Is there any way to revert my version to the old OS 10

  • IPhoto book cover.. matt or glossy

    I have just received 4 iPhoto books. I am very pleased with the results but 2 of them have glossy covers (under the dust jacket) & 2 have matt covers. Can anyone explain why? I like the glossy better..