Scheduling Agreements without MRP
Hi !
I have a depot scenario wherein the organization doesnt have MRP runs configured.
Can we by any way configure Scheduling Agreements for customers, the basic purpose of which will be automatic creation or otherwise proposal of creation of deliveries on the required delivery dates, based on the available stock of materials?
Thanks and regards,
Shamik.
This is correct !
Regards
Bhavesh Mistry
Similar Messages
-
Scheduling agreements in mrp ?
Hi Gurus,
please explain the over all scope of scheduling agreements in MRP. my requirement is like if i run MRP for A FERT Material at MD03 it has to consider the sto scheduling agreement which is all ready created with sales depot.
1. wiil the system considers the sto sch agreements if we run the mrp ?(Material will supplied to sales depot through sto sch agreements ).
2. what is the scope of using special procurement key 40 and 45 (can we use these keys if we procure materials from more than one plant trough sto sch process ?
3. what are the mrp settings we need to do for scheduling agreements?
please clarify my doubts .
Best Regards,
Mahesh.Hello
What you observe on your system is according to the standard system design. Please refer to the following information, provided on question 6 of the FAQ note 550568, which explains the system behaviour:
6. Question:
There are several requirements on one day. Is it possible that the
MRP creates a separate procurement proposal for every requirement?
Answer:
Same as for the daily lot size with a number of periods = 1 (lot
size TB), requirements of one day are also grouped into one
procurement proposal for the lot-for-lot order quantity (lot size
EX) (see documentation for the lot-for-lot order quantity). Separate
procurement proposals can be achieved only if you work with
make-to-order production. Here, the requirements are managed in
separate planning segments of the stock/requirements list.
I suggest you to work with make-to-order sales scheduling agreement. In this case, system will create separated sales order stock for each document. You can test make-to-order setting planning strategy 20 for your material on tab MRP3 of the material master.
BR
Caetano -
GR refer to schedule agreement without release
Hi
We want to do GR according to a schedule agreement without release. but sap cannot skip release process. I find out the configuration is common for both PO and schedule agreement. everybody can give me some solution?
I also see some difference between schedule agreement type(LP/LPA). but this not solved my issue.
Regards
HenryHi Henry
If u want to release the schedule agreement even though u use LP document type then
Goto SPRO-MM-Purchasing-Schedule agreement-Define document types....Here in LP document type, click the check box of release docu. Then system will prompt for release...
Regards,
Dharshan -
Scheduling agreement without usage in MRP / MD04
Hello,
i want to use a scheduling agreement which isn't relevant for MRP. I use the standard agreement type LPA (Scheduling Agreement). The storage location for this process is marked as u201Cstock excluded from MRPu201D and the Source list record is also not relevant to MRP. Although I set these parameters, the schedules appear in MD04.
Is there any possibility like the requirement class in SD? In SD I can set the parameter "Transfer of requirements".
Regards
AndreasIt wont be possible to exclude seperate document type from MRP.
Excluding a Sloc wont work. MD04 list will show the Scheduling Agreement.
You can use a Custom 'Z' Logic to supress the Scheduling agreement from MD04. the program can be written in ABAP Code. -
Order of delivery schedule line counter at schedule agreements from MRP run
Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
Thank you
Daniel Guillen
IT
Skyworks Inc.Hi,
Pls put this query in SD fourms and get immly help because this is technical fourms.
Anil -
I have created a scheduling agreement for a material for 50000. There are dependent requirements on this material which creates scheduling lines. When the cumulative quantity of scheduling lines is greater than 50000 I want MRP to create purchase requisitions instead of scheduling lines based on dependent requirements. Is this possible thru configuration. Currently it creates scheduling lines even after the cumulative quantity is greater than the scheduling agreement quantity of 50000.
thanks a lotHi,
I think that you can achieve this by using Quota Arrangement definition.
Regards,
Mario -
Schedule lines on scheduling agreement by MRP
Hello,
we use MRP to generate delivery schedules on a purchasing scheduling agreement. The vendor of the material has a limited capacity but when the need of our customer is very big MRP generates schedule lines on one date (too many for the vendor too handle).
Is it possible to limit the amount of a schedule line per period (for example we allow to generate 100 tons per week, if the need is 500 tons it should be splitted into 5 schedule lines over 5 weeks).
Thank you for your help!!!!Hello,
the weekly lot size generates lots per week but this answers only a part of my problem.
example: vendor can produce 50 tons per week
need is 200 tons
with a weekly lot size and a maximum lot size of 50 the system proposes 4 schedule lines of 50 tons on the same week and this is not what I want. I want 1 schedule line of 50 ton on the week and the rest on the weeks in the future. -
To generate Schedule lines for scheduling Agreement when MRP is run.
Hi,
Please help advise on my following requirement:
When I run the MRP for 'Single Item - Multi level' (MD02) for a material, I want MRP to generate delivery schedule lines for that material in Scheduling agreement.
Please advise as to how i can go about with this.
Regards,
ManjuHi Manju,
For this you need to set creation indoactor for planning run in SPRO.
The path is spro-MM-CBP-Carry out overall maintenance of plant parameters-Click on maintain-give your plant-click on external procurement under planning run-here you can give your option for the schedule line creation.
Traction code is omi8. Hope this will help you.
Cheers
Ravi -
Planned delivery time in Scheduling agreement and MRP
Hello,
Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
Regards, jaanaThis can be customized in
SAP Customizing Implementation Guide
-> Production
--> Material Requirements Planning
---> Planning
> Procurement Proposals
> Define External Procurement
Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level. -
Firm scheduling agreement in MRP
Hi gurus,
We are maintaining scheduling agrements in ME38 manually. system shows firm schedule lines in md04 screen. When we run MRP system does not consider or minus stocks and create planned order equals to the requirements. we need this scenario in this way that when we run MRP so system should minus stock if it finds schedule agreements, PO etc.
Please suggest.
Regards
Majid Ali Khan.Hi
In T.code OPPQcheck rescheduling horizon days for your plant. If the number of days are less than your delivery date then it will not consider. you need to change your rescheduling horizon days.
And I belive you have done setting right in OMIN for Scheduling agreement.
Regards
Antony -
Firm scheduling agreement with MRP
Hi gurus,
We are maintaining scheduling agrements in ME38 manually. system shows firm schedule lines in md04 screen. When we run MRP system does not consider or minus stocks and create planned order equals to the requirements. we need this scenario in this way that when we run MRP so system should minus stock if it finds schedule agreements, PO etc.
Please suggest.
Regards
Majid Ali Khan.Hi Majid,
As per stanrd sap mrp process , system has to consider the current stock level/ available procureemnt prosposals in mrp calculation.
Are you using gross planning (PS 11)? what is the mrp type for the material. -
Scheduling agreement between mrp areas.
Hi all! I have a question.
Can i create scheduling agreement between two storage location whitin one plant for stock transfers? (storage locations - mrp areas).
where can i read about this?
Thanks.Hi Mildar,
Following OSS notes will be useful to you.
1402298 Purchase order handling release with MRP area
1067960 Stock trasnfer reservation not created for MRP area
Following URL will help for the functionlity of MRP areas within APO
http://help.sap.com/saphelp_scm70/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm
Please check and confirm.
Regards
Datta -
Hi,
do you agree with the following statement ?:
"MRP cannot create automatically scheduling agreement but only schedule lines"
RegardsThis is correct !
Regards
Bhavesh Mistry -
Stock on hand vs stock required from Scheduling agreement from MRP not MD04
Hi SAP Guru's,
1.Currently on 4.6C and client requires a report to view similar to MD04 with capability of multiple materials and vendors and way of summarizing the future requirements and current receipts?
Right now with MD04 we can see for one material current and future Scheduling aggrements(SA) but does not have a report to tell how many are past due (other than going back to look at SA to view cummulative qty).
2.Curretly MRP PD is using SA aggrements for the semi-finished mateirals for planning and maintaining Safety stock and Goods receipt date in Material master to control the schedules? as system generated SA quantities vary with high differences - for example weekly requirement for material A is 480 parts from Vendor A and Vendor delivers on plaaning cycle Tue and Thurs and daily end of the day 65-85 Production orders are confirmed and backflush happens and then MRP runs but instead of 240 per schedule it is splitting 360 once and 220 etc i mean the quantities are very high fluctations and vendor cannot delivery these variation of quantities ? needs your input where the issue is happening and also client want to use Reorder point Qty instead which is not in use currently.
Appreciates everyone time and your help.
Thanks and Regards,
Siva DarbhaNo Solution
-
Schedule Lines generated for expired Scheduling agreements
Hi All,
We are facing problems in Scheduling agreements.
Schedule lines are getting generated for those agreements whose validity has expired(i.e Validity in Past).
Is there any check to restrict those Scheduling Agreements??
Please Help.
Regards,
Ritesh.from OSS note 914607 - FAQ: Validity and status of scheduling agreements
1. Question: When I process scheduling agreements without delivery schedules, I have the option to specify the validity of the scheduling agreement: "Valid" and "Valid to". What role does the validity play when the scheduling agreement is processed?
Response: In the case of scheduling agreements without delivery schedules, the system checks the validity of the scheduling agreement if you create a new schedule line or change an existing schedule line. If the schedule line date is outside the validity interval, a warning message is issued. You can then decide whether or not to create the schedule line or whether to adjust the validity of the scheduling agreement. No error message is issued.
2. Question: What role does the validity play in the case of scheduling agreements with delivery schedules?
Response: The function is similar to scheduling agreements without delivery schedules. The only difference is that the entry of the validity is optional (unlike scheduling agreements without releases) and this is not checked by the system. If the validity is missing, the system does note issue a warning message. If you specify the validity, the system behaves in the same way as for scheduling agreements without releases.
Maybe you are looking for
-
How can i switch my iTunes account to a different users account on my i mac
how do i reset my parental control pass word i forgot it and cant get in too my iTunes
-
HDMI output to monitor not displaying all colors
I am trying to use a second monitor on my Satellite S55t-b5152 and am able to get 1920x1080 output from the HDMI port through an adapter to either VGA or DVI into my external monitor, but with either adapter the colors look washed-out and not all the
-
Hi all, I am trying to configure the SAP J2ee Engine in NWDS by entering the Message server port and host frm Windows- preferences-SAP J2ee Engine . Host: <servername> Port:<3601> but it doesnt show up the j2ee engine view below with the instances .
-
Any one prepar integration test cases in SAP XI
Hi, any one help me ,how to prepare integration Test cases in SAP XI bye suresh
-
High definition TTS voices do not download on Mountain Lion
I'm running 10.8.5 (Mountain Lion), and trying to download some of the high def TTS voices using the Control Panel Text to Speech area. I select the voice. I choose install. It gives me a terms of service which I agree to, and then is starts a downlo