Scheduling and external scheduling in plant maintenance

hi expert ,
can you explain the scheduling in plant maintenance step by step beside external scheduling and how to made the external scheduling in IDS system also i read the sap help links about external scheduling and add the external scheduling in the order type pm01 and add the:
Function Module PM_ORDER_EXTERN_SCHED_DIALOG in Configure Communication in the (D: For scheduling in dialog with external scheduling) should be dialog box Scheduling agreement appears after the order has been scheduled and this is not appear and information message (Link to the scheduling system could not be built) is appear.
is any configuration missing.
thanks sadin

Hi,
I understand you want to practice in IDES.  But to work with external scheduling you need a third party system that performs the scheduling. The idea of this type of scheduling is that the SAP ERP system interfaces with this other system (for example Click Software). It is this interfaced system that calculates the scheduling dates and passes them back to SAP.
Without such a third party system you cannot perform external scheduling. You error does indicate that it cannot communicate with such a system:
       (Link to the scheduling system could not be built)
-Paul

Similar Messages

  • System Warning and Error Messages in Plant Maintenance

    Hi All,
    Where can I find the list of system warning and error messages for Plant Maintenance?
    Thanks
    Andrew

    Hi,
    Follow the following path in SPRO. Some of the standard messages you will fond there:
    Plant Maint & Customer Serivces - Maintenanace & Service Processing - Maint. & Service Orders - Message Control.
    SM

  • Maintenance activity type  and order type  for plant maintenance order

    How can i get the maintenance activity type  and order type  for a given plant maintenance order. Please let me know the table where i can get these two fields
    In AFIH i can only get the MAT for an order number

    Maintenance activity type -
    AFIH - ILART
    Order Category Indicator Plant Maintenance -
    AFIH - AKKNZ
    reward if heplful

  • View labor and material costs in plant maintenance work order

    Hi
    I am aware we can bring in the costs in the work order through Activity types and assigning the costs to the acitvity type.
    Is there anyway we can bring in the actual cost for the work performed by the associate? should we link the work center to HRMS?
    Please advise. I need your valuable input for all the points below.
    Main points that need to be addressed:
    1. Each associate that is capable of confirming hours to a work order needs to be assigned an hourly rate that is reflective of the actual cost for the work performed by this associate. These hours are then tracked through the work order to give a cost for labor assigned to that particular job.
    2.Any materials used in the performance of the required task(s) dictated by the work order will be assigned to that order. These materials can be assigned through SAP purchase requisitions, tool crib spot buys, or procurement with a purchase card.
    3.Standard reports need to be created so we can track the total maintenance costs for any level of the equipment hierarchy as currently set up in SAP. When this report is created it should show the total maintenace costs for all the levels of the equipment hierarchy broken down into labor cost and material cost.  I am using Tcode IW37N and IW40 . Is there any suggestion?

    Greetings Chandra,
    1) You will need to create Work Centres for your associates and create the Activity Types. You can default the Activity Type for each Work Centre and maintain the rate for the activity via t-code KP26 planning.
    2) Planned and unplanned Purchase Requisitions for Components with category N will debit the order with material costs. But what do you mean by "tool crib spot buys" and "procurement with a purchase card"? You may need to develop a solution to do such postings to the Order (or for purposes of Cost controlling, manual activity allocation similar to confirming work may be desired such as Manual Activity Allocations via CO transactions (KB21N), unless you can cover that with Purchase Requisitions and POs with "F Order" account assignment.
    3) MCI8 Cost Report should be suitable for you, once you set up the Value Categories & Cost Key Figures.
    See
    PMIS Cost Analysis Reporting Overview
    Maintenance Cost Key Figures in MCI3 and MCI8 Reports
    PM Order Value categories and costs display

  • SAp Plant MAintenance certification test questions

    Hi all,
    I am due to take Plant MAintenance certification  this march.It would be greatful if I can get some sample question before I appear for this exam.

    The examination questions are based on the functionality and features of the SAP PM.  The possible topics covers are:
    1. Organizational Units and Master Data in Plant Maintenance
    Organizational Units
          - Maintenance Plant and Planning Plant
          - Work Centers
          - Storage Locations  Functional Locations
          - Structure Indicator
          - Reference Location and Functional Location
          - Creation Options
          - Data Transfer  Equipment
          - Installation/Dismantling at Functional Locations
          - Equipment Hierarchy
          - Change Documentation
          - Equipment Category  Material and Serial Numbers
          - Serial Number Profile
          - Goods Movement and Warehouse Stock
          - Valuation Batches  Bills of Material (BOM)
          - Assemblies
          - BOM Categories
          - Item Categories
          - Change Documentation  Additional Functions
          - Configuration
          - Classification
          - Measuring Points and Counters
          - Partners and Addresses
          - Document Link
          - Status Management
          - Permits and Warranties
          - Data Transfer
    2. Maintenance Processing
    Breakdown Maintenance
    Preventive Maintenance Processing
          - Notification Types
          - Objects and Object Information
          - Catalogs and Catalog Profiles
          - List Viewer for Notifications and Orders
          - Order Type
          - Object List
          - Operation List
          - Relationships
          - Material List
          - Availability Check
          - Order Release and Printing
          - Material Withdrawal
          - Completion Confirmation in Time
          - Technical Completion Confirmation
          - Technical Completion
          - Action Log and Document Flow  Processing External Services
          - External Services as Individual Purchase Order
          - External Services with External Work Centers
          - External Services with Service Entry Sheets  Processing Refurbishment Tasks
          - Valuation Type and Valuation Category in the Material Master
          - Refurbishment Without Serial Numbers
          - Refurbishment with Serial Numbers
          - Inventory Management and Controlling  Processing Maintenance Projects
          - Planning and Executing Maintenance Projects
          - Completion, Settlement, and Monitoring of Maintenance Projects  CATS - Cross-Application Time Sheets
          - Data Entry Profile
          - Data Entry Sheet
          - Data Transfer  Capacity Planning
          - Scheduling
          - Work Center and Available Capacity
          - Capacity Leveling
          - Employee Assignment
    3. Controlling Functions in Plant Maintenance
    Plant Maintenance in the Organizational Structures of Accounting
          - Budget Planning and Monitoring
          - Cost Estimation
          - Planned/Actual Cost Determination
          - Order Settlement
          - Logistics Information System (LIS)
          - Plant Maintenance Information System (PMIS)
          - Enhancement Options
    4. Preventive Maintenance
    Task List Management
          - Task List Types
          - Profile and User Fields
          - Component Assignment
          - Task List and Order  Single Cycle Plan
          - Structure
          - Scheduling Indicator
          - Deadline Monitoring  Strategy Plan
          - Maintenance Strategy
          - Task List and Maintenance Strategy  Performance-Based Maintenance Planning
          - Counters and Measurement Documents
          - Maintenance Plan Scheduling  Maintenance Planning with Several Counters
          - Cycle Sets
          - Link Type 
    (Referece: SAP-IMG.COM)

  • Workflow Scenarios (PM/CS) - Plant Maintenance (PM) - SAP Library

    To add a comment, please log in or register on the top of this page and choose Reply. Please write your comment in English.
    You can also go back to the SAP help page.

    hi sergej,
    Check the below link and forums
    [Integration of Predefined Portal Content Home page|http://www.sdn.sap.com/irj/sdn/contentportfolio]
    SAP PM (Plant Maintenance) Integration
    Plant Maintenance Iviews- BP requirements for SAP PM
    Is there any Business Package for Plant Maintenence and Project Systems ?
    Plant Maintenance Iviews- BP requirements for SAP PM
    maintenance order workflow (in plant maintenance module)
    BADI for log book in Plant Maintenance
    EAM Simplification
    hope these links are useful,
    Regards,
    maheshchandra.

  • FM to find out schedule calls and their statuses for a Maintenance plan

    Hi,
    Please let me know if there is any FM to find out all schedule calls and their statuses for a Maintenance plan.
    Regards,
    Vimal

    Hi Vimal
    Below function module will serve your purpose.
    ZPM_GET_SCHEDULING_STATUS
    Regards
    Anil Kumar

  • Scheduling plant maintenance

    Hi
    I need for information about how to create or scheduling plant maintenance.
    Schedule preventive, predictive & corrective how can maintain in PM module.
    Ram Rathode

    Hi,
    In preventive maintenance scenario following are the things :-
    1) Creation of task list (for Equipment or Functional Location or General).
    2) Creation of maintenance plan (for Equipment or Functional Location or General).
    3) Attaching maintenance task list to the maintenance plan created.
    4) Scheduling of the maintenance plan for creation of maintenance orders (Call Objects).
    5) Maintenance/Breakdown order proceeding ( notification,planning,scheduling,execution,completion)
    There are following types of maintenance :
    1) Single cycle maintenance planning.
    2) Strategy plan ( Time based & Performance based )
    3) Condition based maintenance planning.
    4) Project based maintenance planning etc.
    Regards,
    TRB

  • Implement the exit IPRM0005 to schedule preventive plant

    Hi,
    I've implemented and activated the user exit IPRM0005 to schedule the preventive maintenance plant .
    Which tx do I have to execute to pass across the code to modify the performance of the maintenance plant?
    Thanks in advance
    Kind regards¡¡

    Hi,
    Look for the Program running behind Txn Code IP10 using Txn Code SE93, or use the Path on the TXn First Screen .....Menu Bar : System->Status look for the Program name, and double click on that.....Use String Search for your User Exit "IPRM0005"........and look for the code of the User Exit....

  • Plant Maintenance and ECS SRM

    I've been asked to investigate the feasibility and steps involved in integrating Plant Maintenance to SRM.
    I've looked at the standrard documentation and it appears that this is pretty straightforward.
    Can anyone give me any pointers on the following:
    1) What BAPIs etc are used to transfer the PReq from the backend to SRM.
    2)What are the require configuration settings ?
    3)Are there any attributes that need to be maintained within the org plan?
    Regards
    Keith

    Hi,
    In addition to Marcin answer, you can connect your catalog directly to PM in transaction IW31 and IW32.
    There is also a scenario to connect PM with SRM without external requirement configuration.
    This is the "old way" and "abandonned" by SAP: please see here :
    Re: EBP integration with PM and PS
    Kind regards,
    Yann

  • Plant Maintenance to External Service Requirement (MM-SRV)

    Hi,
    Kindly tell me how to create a MM-SRV Purchase Requisition from Enterprise Asset Management (Plant Maintenance).
    eg. A plant maintenance order (IW31) is created for repair of a transformer. It requires external service procurement with following structure.
    Service Item D: Transformer repair
    Limit 10,000 eur
    Outline 10: Dismantling
    Service Line 10: Junior Technician 5 hr, 10 eur
    Service Line 20: Senior technician 3 hr, 15 eur
    Outline 20: Cleaning
    Service Line 10: Oiling 5 hr, 20 eur
    Outline 30: Reassembly
    Service Line 10: Junior Technician 15 hr, 10 eur
    Service Line 20: Senior technician 10 hr, 15 eur
    Kindly tell me how Purchase Requisition can be created with service structure from Plant Maintenance.
    Thanks & Regards,
    Ashish

    In IW31, select the Order type. Select the Planning Plant.
    give the main work center & Functionla location of performing the services
    Click on the operations tab, select the Control Key PM03 Plant maintenance-External(services). Enter the operation short text. Select the line item & click on External Icon (at bottom of page)
    Give the details such as material group, purchase group, Purchase organization , requisitioner.
    Create the service lines & Save the data. Order gets created. goto IW32 & release the order.
    PR can be viewed in Act. Data tab at the service lines.
    Thanks & Regards
    Kishore

  • Plant Maintenance - Linkage between Task List and Maintenance Plan

    Sir,
    In Plant Maintenance, I have an equipment for which there are 9 maintenance activities that have to be performed every year. Out of these 4 activities will be carried out every month. 1 activity will be carried out during the months of February, June and October. 5 activities will be carried out only in the month of December.
    I need to create Task List for all these activities and subsequently create Maintenance Plans for all these Task Lists.
    Can I group all the 4 activites which will be carried out every month into one single Task List, with separate operation nos and time against each activity?. I don't know whether it is correct or not.
    If I use the above method I can create 3 Task Lists for this particular equipment with same Group no and 3 Group Counters.
    How to create Maintenance Plan for the above scenario?.
    Eventhough, 4 activites are carried out every month and they have been grouped into a single Task List (Group counter 1) and if these activites are carried out on different dates within a month how can I create Maintenance Plan and subsequently create a Maintenance Order?.
    I need some help in this regard. A detailed reply will be helpful.
    Can anyone throw some light in this regard.
    Regards,
    R. Vijayakumar

    you need to create one task list with a maintenance strategy with packages and hierarchy to outline the work requirements i.e. some tasks to be carried out 3 monthly some 4 monthly etc, and also if common tasks appear in 3 monthly package vs 4 monthly package then to suppress the duplicating task
    you would then define a strategy based maintenance plan and run it to get the respective maintenance orders

  • How to read the configuration for SAP GUI elements in Plant Maintenance module from SPRO and leverage the same in NWBC for HTML.

    Dear Members,
    Greetings for the day!
    I am working on NWBC for HTML in Plant Maintenance module.
    We have configured some changes in SPRO for customizing the UI elements( like visibility, mandatory ) like tabs and fields in transactions like IW21( Create Notification).
    As of now separate parallel configuration needs to be carried out in NWBC for HTML in PM module to achieve the same UI features for creating notifications and this is time consuming.
    Is there any way to read the configuration done in SPRO for the SAP GUI's and leverage the same in NWBC for HTML.
    Appreciate your time in responding to this.
    Thanks & Regards,
    Ram.

    >
    <IfModule mod_weblogic.c>
    WebLogicCluster 127.0.0.1:7005,127.0.0.1:7007,127.0.0.1:7003,127.0.0.1:7103,127.0.0.1:7104
    MatchExpression /app1
    </IfModule>
    <Location /weblogic>
    SetHandler weblogic-handler
    WebLogicCluster 127.0.0.1:7003,127.0.0.1:7005,127.0.0.1:7007,127.0.0.1:7103,127.0.0.1:7104
    DebugConfigInfo ON
    PathTrim /weblogic
    </Location>
    <IfModule mod_weblogic.c>
    WebLogicCluster 127.0.0.1:7003,127.0.0.1:7005,127.0.0.1:7007
    MatchExpression /app2
    </IfModule>
    <Location /weblogic>
    SetHandler weblogic-handler
    WebLogicCluster 127.0.0.1:7003,127.0.0.1:7005,127.0.0.1:7007
    DebugConfigInfo ON
    PathTrim /weblogic
    </Location>
    >
    This configuration is weird little bit. There is MatchExpression /app1 and MatchExpression /app2 and at the same time two <Location /weblogic> sections. Are you sure you understand what that configuration stands for?
    Try something like this ...
    <Location /app1>
    SetHandler weblogic-handler
    WebLogicCluster 127.0.0.1:7003,127.0.0.1:7005,127.0.0.1:7007,127.0.0.1:7103,127.0.0.1:7104
    DebugConfigInfo ON
    </Location>
    <Location /app2>
    SetHandler weblogic-handler
    WebLogicCluster 127.0.0.1:7003,127.0.0.1:7005,127.0.0.1:7007
    DebugConfigInfo ON
    </Location>
    where /app1 and /app2 are contexts of your weblogic applications.
    http://download.oracle.com/docs/cd/E11035_01/wls100/plugins/apache.html
    http://httpd.apache.org/docs/2.0/mod/core.html#location

  • Plant Maintenance and Work Clearance Management

    Where can i find functionality info on Plant Maintenance and Work Clearance Management. How can these functionalities be activated  - is there a switch?

    Please go thr below SAP Help links for Plant Maintenance and Work Clearance Management.
    http://help.sap.com/saphelp_47x200/helpdata/en/2b/1b713896fab752e10000009b38f889/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/2b/1b713896fab752e10000009b38f889/content.htm

  • Plant Maintenance Datasources and Cubes

    Hi Experts ,
    I need to extract Plant Maintenance Data and generate Standard Reports on PM . Client want to see standard reports on PM.
    Can anyone plz guide me what all cube's in PM module supports what all datasources for those respective cube.
    Thanks in advance
    Regards,
    Mahesh

    hi
      For data sources you can find in rsa5/rsa6 t-code.
    for those particular datasources you can find the cubes in business content ( rsorbct t-code )  if you select before and after option under grouping then you van find both the cubes and standard reports. based on the requirement you can choose the standard reports.
    thank you