Scheduling comparision in Gantt Chart- Project planning board

Hi All,
I Need to use the "Scheduling comparision" in Project planning board gantt chart. This is to compare the original status of activities before and after scheduling.
But the "Scheduling comparision" button in the PPB does'nt seem to work.
( I am selecting the activity and then pressing the button for"display original status" )
How do I use this functionality?
Thanks in advance.

Hi Potluri Srinivas ,
After some tests, I still donot get, how does this functionalties work either.
I assume, it is linked with the setting in 'option' -> 'planning board' -> 'diagramm area' -> 'orginal schedule'.  But I donot know, how the two things linked directly.
If you find it out, please post it.
Thanks and  regards,
Zhenbo

Similar Messages

  • Network Header at  the Project Planning Board gantt chart

    Hi again,
    Does anyone knows a configuration to allow the network header to appear in the project planning board gantt chart?
    Tks
    James

    Try transaction OPT7
    Double click on the appropriate Profile
    On the Table Area Tab, select the flag for the field "Display Network"
    Hope this helps
    Regards
    Steve

  • Activity bar not displaying on Project planning board

    Dear All,
    I am getting one problem related to project planning board. I am working on a system in which when i am trying to run  project planning board, its coming but in that gant chart i am not able to see bar for activity. Bar for project definition and wbs coming properly. In tabular form also i can see the activities. But the only problem i am not able to see bar for activity with relationships. I have check almost all configuration related to project planning board profile and also scheduling proflies.
    Kindly suggest what can be the reason for the same.
    Regards
    Abhishek Sinha

    Hi Abdul,
    Thanks for reply. I have check all these options but all things are in place. OPT7 setting also right there. Kindly suggest what other setting can affect. In the planning board i can see the activity at left hand side corner with details but in gantt chart where we see bar chart for schdulines there activties are not coming.
    Kindly suggest.
    Regards
    Abhishek Sinha

  • Project Planning Board - Customising

    Hello All,
    Do we have an option to customize project planning board.
    If yes where exactly in SPRO can we do this, and does anyone have any documentation on what all can be configured in project planning board.
    Points assured.
    Thanks in advance.
    Warm Regards,
    Jatinder Bansal

    Project planning board customization is available at IMG. path IMG>PS>Structures>Project Planning Board.
    Planning Board is based on Gannt chart. the customization includes, Define Time Profiles, Define profiles for time scales ,  Define scale for the time axis, Define Profiles for the Project Planning Board, Maintain Report Assignment from the Planning Board & Capacity Leveling/Capacity Evaluations.
    Regards
    Murali

  • Default print settings in the Project Planning Board CJ02N CJ2C

    Hello
    When you print the Project Planning Board CJ02N/CJ2C - there is an option to change the page setup.
    I would like to change the default settings for left,right, top and bottom margins for all users.
    Can anyone suggest where this would be done ?
    Thankyou
    Ros

    Hi Varun,
    Thanks for the fast repply!
    Please see below the CJ2C and CNE5 screen shots:
    Thanks and Regards
    James

  • Project planning board report to microsoft project report

    hi all
    good morning
    i want to convert the project planning board report to Microsoft project and primavera report ...
    please guide me through the steps......
    Thanks in advance
    Surya

    Hi,
    OpenPS for Microsoft project (OpenPS4MSP) is an Add-on to SAP R/3 Project System which enables users to transfer project related data between Microsoft Project and R/3 Project System.
    Refer SAP Note: 579761 for OpenPS.
    Then to integrate SAP and Primavera , you can use various integration tools available. One of them is Primavera Inspire.
    Refer :
    http://www.oracle.com/applications/primavera/primavera-inspire-for-sap.html
    Regards,
    Amit

  • Viewing CO versions in project planning board

    Hello,
    I have saved two CO versions of my project. When i go to the project planning board the approved plan column is full of data and looks great but the other version as no information. I have SAPALL so this isn't an authorization issue. Can someone please help me work out was is wrong?
    Thanks a lot
    Jason

    Hi,
       Basically there are possibilities of creating Plan version.
    1) one you can create in CJ40 by manually feeding the Version ex:0,1,2 etc....
    2) create one version in CJ40 and copy the same to another version in CJ9BS.
    once the versions are created make the changes of values in the respective versionand save the changes.
    Please check the version comparission in S_ALR_87013539 - Project Version Comparison: Plan.
    Comming to plan board which fields did you picked up for comparission?
    Rgds
    Sudhir Reddy

  • Unicode in Project Planning Board Screen (CJ20N)

    Hi,
    I'm facing a problem of unicode as follows:
    I inputed some unicode (Vietnamese) at Project Structure screen, It is ok. but when I switch to Project Planning Board screen, It don't work. I also cannot input Vietnamese with unicode at this view.
    Text example: "Các công tác chuẫn bị"
    Please help!
    Thanks
    Long

    Hi,
    Found something on Service.sap.com
    Thought would be useful..
    To access this page you need a login id for service.sap.com
    https://websmp108.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000557148&
    thanks..

  • Small Font for Date in Project Planning Board

    Hello Friends?
    Iam Using ECC 6.0 C Version in our Company. iam facing a problem in <b>CJ2B</b> that Date is displaying in very small font. i could n't solve that problem till date. Can any body help me where can we make settings for making fonts size bigger for <b>dates</b> other than zooming in Planning Board.
    Appreciable for ur kind information.
    Thanks.

    Hi Hari,
    Once you are into CJ2B, Please follow the following steps:
    1. Click on the icon " Planning board Assistant"
    2. Select the gantt Chart----Misc. in diagram Area
    3. In the Selection of the "Text" of "Date Descript."--- Select "Dates one-line " ( This is applicable if your date is on the left or right side of the date bar)
    4. Now you can change the Font colour, Font and Font Size, Bold or Italic.....
    5. To Confirm the setting Click on "Update graphics" button on the screen.
    6. Now, If you notice, the dates fonts will be as per your requirement.
    If this does'nt work.. Try to explore in this area only..Probably try selecting other "Text" in the "date Descript."
    Hope this helps.
    Warm regards,
    Srinivas Potluri

  • Looking for Gantt Chart /Project management reports in jps

    Hi all,
    I am starting the development of the project management charts (Gantt chart) for my organization. Customer (internal department of my company)wants the solution in Jsp. I request your input for good resource on project management (Gantt ) chart resource to start with in jsp
    pl. help me with the code if possible or the already developemnt resource.
    thanks in advance,
    regards,
    Kumarappan.S

    http://www.google.com/search?q=java+gantt+chart

  • Gantt chart project renaming MSproject 2010

    sounds simple, but it really irritating me, because i can't  find a title renaming option ANYWHERE. my friend  let me  use his project as a template for me to edit, and i did.  when i do a printout, it still shows his project name in
    the bottom left corner of the  printout. i changed the file name, but that didn't do anything. can anyone tell me how to rename the project?

    FCBO --
    Thank you for your very kind words, my friend.  As always, you are more than welcome for the help.  :)
    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

  • Activity Confirmation  -  Gantt Chart  -  Planning board

    Hi
    suppose i have a activity duration from 1st february 2009 to 28th february 2009
    on 15th february i confirm 0nly 10% of the work as completed in the activity confirmation screen in the degree of processing field and also enter the start date as 1st february 2009 and the finish date as 15th february 2009.
    when we look at the planning board in CJ20n transaction subsequently (gantt chart) the activity bar shows a colouring from 1st february to 15th february instead of showing only 10% of the activity bar coloured for completion of the work
    where is it possible to see the percentage completion of an activity graphically as 10% this data is available in table format in CN48N transactio

    Hi,
    we can view in table format by selecting the fileds related to percentage of completion in the project planning board (gantt chart).
    The requirement you had explore is possible in MS projects, but in standard SAP we can't view in the graphically mode.
    Regards,

  • Gantt chart- How to change the color of time bars of different versions

    Hi All,
    My Client wants to see all changes in planning schedule. I made different versions of these changes but he also want to see all these changes in gantt chart and in different colors. I tried to change the color in planning board assistant but in this screen (CJ27/ CJ2B). we cannot view all versions together. And if I use CN41, there I cannot change the colors of time bars.
    Secondly, we can change colors of times bars of basic dates, forecast dates and actual dates but there is no provision to change the colors of schedule bars of different project versions. Kindly reply-
    1. How to see all project versions in CJ27 or How to customise bar chart in cn41 or if we change in SPRO, then how to change graphic profile in project info profile
    2. How to change colors of different time bars of different versions.
    3. How to mention these legends (meaning of each color in chart) at footer of gantt chart (in print outs)
    Please Help.
    Thanks & Regards
    Dinesh Chauhan

    Thanks,
    actually I've created new project planning board profile where planning board assistant is customized but unable to use this profile in CN41. we can change PS info profile in CN41 and that;s why I thought that planning board profile may be assigned somewhere in PS info profile so that changes in planning board assistant will be applied in CN41 through PS info profile. Graphic profile is too complex to understand and not sure if it will help to get colored time bars of projct versions in gantt chart. Still not clear.
    Secondly not able to see all versions (snap shots) in gantt chart with different colors of time bars.
    I mean planning board screen can be customized but we cannt see different versions here which are possible in CN41, but we cannt customize the gantt chart (time bars) in CN41. Pls help.
    Thx & Regards
    Dinesh Chauhan

  • Print out of Gantt Chart

    While using the menubar path Project> Print> All/Gantt Chart in the Project Planning Board screen of a Project, the print preview showing the display area only. The table area is showing without the text and data. Please tell me what type of settings to be done for this problem.

    Hi Mohanty,
    Plz check.
    Project planning boardu2026u2026..projectu2026..printu2026..All/Gantt.
    Here if u are not able to see the valuesu2026.Text.
    Clicku2026.Page setupu2026.optionsu2026.see the columns have u given zerou2026u2026make it as 20.
    I hope it will solve.
    Regards
    Chandra

  • Issue in Pop-up behaviour within Gantt chart

    We use Jdeveloper 11.1.2.0 in creating multiple type of applications. We are stuck with one issue in Pop-up behavior in Gantt chart and needed your help. Any help in this will be highly appreciated. It seems that this was the known issue in 11.1.1.4 but not sure if this is resolved in current release of 11.1.2.0.
    Jdev Version: 11.1.2.0
    Control Used: Panel Tabbed, Gantt Chart (Project), ADF Popups and Dialog
    Scenario: We are having Panel Tab. One tab is having Gantt chart whereas second tab is having read-only Table. Gantt chart has pop-up window (Along with Dialog), which opens up on hovering one of the column.
    Issue: Gantt Chart and Popup works fine but pop-up gives error (Region not valid) when we click on second Tab and come back to the Gantt chart tab. Screenshots are attached for your reference.
    PS: I can see know issue at this link but did not see this in current release known issues.
    http://www.oracle.com/technetwork/developer-tools/jdev/relnotes-14-jan-11-261400.html#dvt2
    Many Thanks.
    Regards,
    Sachin G

    OK, I did't realise you were using adf faces.
    Quoting the Oracle WebCenter Framework documentation:
    "17.5.2.3 Oracle ADF Faces Guidelines
    The Oracle ADF faces guidelines are as follows:
    * Oracle ADF Faces client side implementation is not supported. One weakness of JSR 168 and WSRP 1.0 is that they do not account for portlets using client-side programming techniques, such as Ajax or hidden frames, for partial page rendering. As a result, all Oracle ADF Faces facilities that rely on client-side programming techniques do not work. These facilities include the following:
    o Oracle ADF Faces partial page refresh (PPR) facility
    o The client-rendered aspect of Oracle ADF Faces rich client components
    o Oracle ADF popups, <af:popup>, which fail to work because of their reliance on the PPR facility
    o The Oracle ADF Faces SelectText, SelectDate, and SelectColor components, which use visual assist popups
    To avoid breaking existing applications, the popup is disabled when used in Oracle ADF Faces pages exposed as a portlet. Thus, functionally speaking, these components are equivalent to InputText."
    So guess that just won't work.

Maybe you are looking for