Scheduling in Planned order

Dear All,
When I am creating a planned order thro MD11 and scheduling it, it is picking only one operation from the routing of the material for which the plnd order is created. What could be the reason for this?
Manisha

Hi,
Please check the below ...
Proper relationship is maintained in the routing or not.
Check that the other operation are alternate operations are not.
Check the control key of the operation it is copying in the planned order.
Hope thi can help.
regards,
kaushik

Similar Messages

  • Collective scheduling for planned order

    Dear Gurus,
    i create the planned order using the bapi standard whit the production version , but when create the new planned order the version don't is read in the order, ( BOM + ROUTING ) OF THE version.
    For read the production version you must reschedulling the planned order.
    Are there the methods for read the production version at the creation of the panned order ,
    or the strument for rescheduling collctive?
    Thanks a lot
    Daniele Pistilli
    PP TEAM

    Dear Gurus,
    thanks for indication of the material master, but we don't  always manage the versions of productions.
    For the production order there are the routing without the production versions, but when i create whit the bapi or whit the transaction MD11 the new planned order manually i need setting the production version , but when i setting the version for the find the version ( bom+routing) i must re-scheduling the planned order.
    Are there the BAPI or alternative soluction for re-scheduling the planned order collective, or for read directly the version present in the BAPI ?
    Thanks a lot
    Daniele Pistilli
    PP TEAM

  • REM scheduling in planned order

    Hi,
    I am using repetetive manufacturing. I have maintained Forward scheduling in transaction OPU5 and selected the selection ID 02 for rate routing for detailed and rate based scheduling.
    Planned orders are created from MRP. When I check the planned order deatails, in the Det.Scheduling tab it shows scheduling type Forward and in the Production rates tab it shows backward scheduling. I have maintained Forward scheduling in OPU5. So the production rates tab shows different scheduling type. How?
    can any one explain this.
    thanks and regards
    murugesan

    HI
    Check the entry parameters for the planning table in OS80 .
    check and revert
    Regards
    Anupam Sharma

  • Scheduling of planned order and Production order

    Dear PP gurus,
    I have run MRP , after running MRP, system has created planned order. These planned order dates are  schedule by the system in 2015....I am not able to understand. how? . When i  double click on
    planned order order and try to convert it in production order  those dates get copied into production order.
    DO i need to change the dates thr? or  keep the same dates  which the system is giving>
    I  m going wrong somewhere. please tell me where and   what is config for scheduling for planned order and production order?
    Please tell me step by step procedure
    Regards
    Edited by: Aadi1981 on Apr 1, 2010 9:02 AM

    Thanks for replying,
    I have done the below setting for shceduling. Kindly check and let me know any setting needs ot be changed or incorect
    FOr scheduling  production order , i have configured below settings in OPU3
    In OPU3 ,  
    Detail scheduling tab
    Scheduling and  Generate cap req tab is checked.
    then
    adjust scheduling , adjust dates  tab,    :  adjust basic dates , adjust  dep , reqt to operation date  is selected
    scheduling type is backward.,
    Automatic scheduling tab is  checked.
    In OPU5
    Scheduling of PLanned order
    Scheduling and  Generate cap req box  is checked  (selected)
    Adjust scheduling
    Sheduling level: via  detail  scheduling
    adjust dates:     adjust basc dates , adjust  dep reqt , req to  operation dates
    For capacity  scheduling ;  always  basic dates, dep reqts to operation dates
    scheduling type ; backwards
    apart from this do i need to do update  ca96/ ca97?
    best Regards
    Edited by: Aadi1981 on Apr 3, 2010 7:42 AM

  • Masss Scheduling of Planned Order

    Hi
    Is there is any transaction for Mass Scheduling of Planned orders preferabaly at plant level.?

    Dear Mayuresh,
    In my understanding there is no T Code to schedule as set of  planned orders
    This will impact on the other reciepts and only during MRP rescheduling happens.
    But also have a check the FM that Mr.Brahmankar has suggested.
    Dear Rupesh,
    Do u think even if you have an action plan and execute MDAC will it help to schedule the planned
    orders?
    Regards
    Mangalraj.S

  • BAPI or FM for scheduling a planned order (like MD11 or MD12)

    Hi guys.
    We are working with a group of materials and planned orders, in order to modify and create new planned orders depending on the stock per each material. So we use MD12 to 1) modify the quantity in the order, and MD11 to create new planned orders for the rest of stock for this material.
    For process of creation we don't have problems (BAPI_PLANNEDORDER_CREATE makes its work well ), but when we want to schedule the new planned order created before via FM or BAPI, we cannot see any results in MD12.
    I mean, when a planned order is scheduled via menu button, a new tabstrip appears in the transaction with dates. So this similar action we've tried using CX_PLANNED_ORDER_SCHEDULE or CX_CRP_PLANNED_ORDER_SCHEDULE but there was no change.  If we execute the Schedule button action, in table PLAF (master of planned orders) apears a new number in field PLAF-BEDID related to MRP.
    So guys, could you please help us how to get this issue? As last option is BDC, but BDC's and me are not good friends because its performance. So please, any suggestions?
    Thanks in advance!
    Raul Romero

    Hi guys...
    Sorry for the long time without an answer, which I'm sharing you now:
    1. In order to perform the proccess of scheduling, you have to record the steps from menu bar in your batch input. I mean: (1) set values into fields CRHARBPL-LOW () and CRHWERKS-LOW
      PERFORM set_batch USING: 'X' 'RCCRY000' '1000',
                                      space 'BDC_CURSOR' 'CRHARBPL-LOW',
                                      space 'BDC_OKCODE' '=PLNG',
                                      space 'CRHARBPL-LOW' p_arbpl,
                                      space 'CRHWERKS-LOW' 'PR01'.
    (2) After you ordered your list of planned orders or production orders, loop your internal table and per each order record these commands (these simulates the popup option to select the order you want for scheduling and mark it in the dynpro you are processing):
      LOOP AT gtd_tabofplan INTO gvc_tabofplan.
        PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                                        space 'BDC_OKCODE' '=Z021'.
        PERFORM completa_bi_campos USING: 'X' 'SAPLCY19' '0120',
                                space 'BDC_CURSOR' 'CYMARK-VALUE(02)',
                                space 'BDC_OKCODE' '=BACK',
                                space 'CYMARK-VALUE(02)' gvc_tabofplan,
                                space 'CYMARK-MARK(01)' space,
                                space 'CYMARK-MARK(02)' 'X'.
        PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                                space 'BDC_OKCODE' '=SL25'.
      ENDLOOP.
    (3) Set the SAVE operation.
      PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                              space 'BDC_OKCODE' '=SAVE'.
    Hope you' ve succeeded in this task, let me know if you've another questions.

  • Need Automatic Lead-time scheduling in Planned Order using MD11

    All,
    Our users have a requirement that when they create a planned order using MD11, they would like system to do automatic lead-time scheduling based on the "basic finish date" entered by the user. Currently the system is taking 3 days from the in-house time maintained in material master to calculate the basic start date. But users want to use the 100 days that have been maintained in the routing.
    Currently users have to click on "manual scheduling" on the planned order for system to pick up 100 days from routing which is an additional step for the users. Hence users want an automatic way in which system would do lead-time schedule when they enter the basic finish date.
    Thanks,
    Swapnil

    Dear Swapnil,
    In my understanding it is the standard SAP behaviour even if you have made the necessary settings in OPU5 for the planned
    order type.
    If my understanding is correct, then as per this setting the MRP behaves for the particular plant and order type combination.
    Whenever you create a planned order manually you have to do a detailed scheduling and then you get the production dates
    for the planned order.(This might be because generally when a planned order is converted into production order the system
    carries out a lead time scheduling.- Check the same and correct me if I'm wrong)
    Even if you update the material master through CA97,you will not get the detailed scheduling done along with the production
    dates.So you have to perform this manual activity during MD11.
    What is the reason of setting the in-house production time as 3 days,if the exact production time is going to be more?
    Check and revert
    Regards
    S Mangalraj

  • Scheduling for planned order

    When I choose leadtime scheduling in MRP RUN then system does forward scheduling always.
    Then in planned order change mode when i do manually do scheduling then it does backward scheduling as  per settings in OPU5.
    How to get backward scheduling in MRP.??

    Dear,
    MRP do the backwordscheduling but The system always determines the basic dates for planned orders using backward scheduling.
    The system automatically switches to forward scheduling if the determined start date lies in the past.For this you have to maintain 2 settings.
    1)In OPPQ - Plant parameters maintain the indicator for start date in the past allow. 2) In OPU3 for your plant & order type , maintain the no. of days for start date in the past.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Scheduling of Planned Order for dependent material

    On exection of MRP, we are exepecting  that Finish date/time of the dependent material's planned order should be the start date/time of the header material.
    This is not observed
    We are on ECC 6.0 and have Rep mfg with std routing. there are no inhouse time or schedule margin key values.

    Hi,
    Please check below link if this can help it.
    http://help.sap.com/saphelp_scm2007/helpdata/en/c3/9e443cfb06e532e10000000a114084/content.htm
    Regards,
    Anil

  • Scheduling for planned order & production order

    Hi,
    I am not using fully routing.
    I have given requirement.
    08.2009--- 100 MT
    09.2009--- 100 Mt
    When I run MRP system always schedule FRom 01.08.2009 to 31.082009 .How to made settings.
    I have maintained In house production date 30 days.Forward scheduling.System always calculates from the current date,If I given oder start in past is activated in customizing take as 01.08.2009 as order finish date.
    Guide me
    Regards
    bhuvan

    Hi bhuvan,
    That is because of your requirement date.
    Which are 08.2009 and 09.2009
    08.2009 means your finish materials should be ready for delivery on 01.08.2009 similar way 09.2009 material should be ready for delivery on 01.09.2009.
    System always schedules the orders to meet the requirment dates.you may find exception msg like rescheduling in(10) or Plan process according to schedule (30) along with those plan orders.
    Regards,
    Dhaval

  • Scheduling firmed planned order

    Hi all,
    I have follwoing situation:
    In the MF50-planning table firmed (as customized in REM-profile with parameter "Allways Firm")
    planned orders are created manually also in the past/backlogs.
    The MRP/program RMMRP000 is updating the production dates of these FIRMED orders to the actual date/today. Because of this the planned order is shown on the actual date in the MF50 instead of the original planned production date in the past..
    Usually the MRP doesn't consider firmed orders regarding their quantities and basic-/production-dates. In our case the MRP is changing production dates what is not expected.
    Do you have ideas about this ?!
    Thanks,
    markus

    Hi,
    MRP-type is customized with firming-type '2-Automatic firming and order proposals rescheduled out'.
    Firming indicator has not been changed after creating the planned order in the MF50/Planning table; this has been already checked in MD04/MD13.
    Further ideas ??
    Regards,
    markus
    Edited by: Markus Krauss on Aug 5, 2010 8:55 AM
    Edited by: Markus Krauss on Aug 5, 2010 9:37 AM

  • Not scheduling on manual creation of planned order

    Creating planned order through MD11 and noticed there scheduling not done and capacity planning not done and on doing scheduling manually dates altered and capacity planned which are appearing in CM01 for the respective week
    Planned order created through MRP are fine with scheduling an capacity planning .
    Please let us know what could be a reason for not updating on manual creation.

    Hi
    This is standard behavior of SAP as when you create the planned order through MD11 manually , you need to do the detailed scheduling manually by executing schedule in Edit>Schedule.
    Check this thread:
    Need Automatic Lead-time scheduling in Planned Order using MD11
    Regards,
    Anupam Sharma

  • Scheduling problem in planned order.

    Hi all,
    I have a problem in scheduling of planned orders.
    I had mentioned the following parameters.
    1. Available capacity in the work center as 06:00:00 to 12:00:00
    2.Set up time is 10mins in the routing.
    3. The planned order qty is 100 nos.
    While doing manual scheduling in planned order, the system proposes the start time as 11:50am and finish time as 12:00am. But as per calculation, for 100nos x 10 mins = 1000 min = 17 hrs.
    But the system calculated 10 mins for 100 nos.
    Is there anything i am missing , due to which the system is doing wrong scheduling.
    With regards,
    Afzal

    dear afzal ,
    system is taking setup time only for first piece you are machining and for rest other 99 piece its not considering the setup time.
    Check in the formula you are using if its defined as only to consider one time the setup activity or its taking piece wise/quantity  wise.
    Check and change it , it will solve your problem.
    Hope it helps you.
    regards
    Ritesh

  • Scheduling planned order of semi finished

    Dear all,
    I have the following scenario finished product A is made of semi finished product B , when making a plan for A to be delivered say 1\6\2010 the system schedules a planned order for A to be delivered on 1\6\2010 at 7:00 AM and start on 25\6\2010 at 14:00 PM therefore for semi finished B a planned order should be scheduled to be delivered on 25\6\2010 at 14:00 PM .
    the problem os that B is scheduled to be delivered on 25\6\2010 7:00 AM not 14:00 PM . known that no schedule margin key is used and the start time of the plant is 7:00 AM. is it configuration or SAP standard?
    Regards,
    Ahmed Sobhi

    Dear  Mr.Ahamed ,
    Basically , if you have Capacity Requirement Profile active , when you dipsatch the operation system will ask you to review  the Work centre  ,  Operation  , Timing  before depatch based on the capacity load  .I am not sure wether u are utilising that functionalty or not
    However , Convert the Planned Order to Production Order for B .Goto Operation Over view .How many operations are there in  B? .You can change the time , if you dispacth( Select the line itme - operation AT HEADER -DISPATCH )  , select the line Operartion line item and double click , goto Date , here you can change the Date , Time (Set up, Processing , Teardown , Move Time , Wait Time ) .Basically u should deal with Operation Execution time (Set up , Process , Teardown ) .
    We generally  change the timeing like this in our shop floor  in our business process.
    Secondly , at configuration level , you can goto -OPJN-Select the Scheduling Type -Mark the option With Time  so that you can enter the timing also when to start and end  at planned order as well production order .
    Try and revert back
    Regards
    JH

  • SNP Planned order not following resource bucket capacity/factory calendar

    Hi gurus,
    SCM 5.0
    I am running SNP heuristics for a product and expecting planned orders for it.  It has corresponding production data structure and multimixed resource.  The resource has an assignd factory calendar and SNP bucket capacity.  The bucket capactiy availablity dates of the resouce is consistent with the factory calendar workdays/holidays.  Using simple lot for lot strategy, I am expecting heuristics to schedule the planned orders on the dates of the demand in compliance with teh SNP bucket capacity availability of the resource.  APO does not schedule on holidays consistent with bucket capactiy.  This is true until...
    We have a public holiday in factory calendar that needs to become a workday. To remedy this, we put a special rule for the factory calendar and explicitly made that holiday into a workday.  The changes were synchronized with APO, and this is also reflected in the bucket capacity of the resourc: former holiday now has bucket capacity after the calendar change.  However, when running heuristics, it still does not create SNP planned order on that former holiday that has been changed into workday.  Even if it is a public holiday, there is already a special rule for the factory calendar and the resource bucket capacity reflects this correctly. But SNP heuristics seems not to follow this change.
    Any ideas on this? looks like a bug.

    Hi Edgar,
    Yes, when your resource reflects the addional capacity of the holiday turned working day, then it is expected to be considered for the SNP planned order.
    Instead of SNP heuristics, you may try to check interactively in SNP planning book, if manual order creation in the bucket works out.
    Since this is a mutlimix  resource , it can also be checked if in PPDS planned order can be created on the day.
    The above checking may not solve your problem , but will get to know if at least manully the bucket is being considered or not.
    regards
    Datta

Maybe you are looking for

  • How do you synchroniz​e accesses to a LabVIEW Shared Variable?

    I would like to create an ad-hoc weather station program (I'll explain more in a bit).  I am using LabVIEW 8.0 Full Edition, and I would like to share data over a network between stations with the LabVIEW Shared Variable.  Here's what I want to be ab

  • BW upgrade from 3.x to BI 7.0

    Hello BI experts, Could you please let me know how will we plan the BW upgrade? It would be better if somebody can give me steps. Answer will be appreciated and rewarded with full points. Thanks and regards, Harry

  • After Applying SP 5.0 in SRM 7.0

    Hi ,               I am in SRM 7.0 SP 5.0. We have recently update SP level to 5. After SP 5.0 we are encounter the error " No G/L account was entered ; enter a G/L account " and " Error in account assignment for item"   Whenever I change the materia

  • BPS Object inventory display

    I need to map objects in BW and BPS for upgrade preparation and documentation.  BW is easy in that there is the metadata repository, is there any equivalent way of looking up BPS objects? I suspect that there isn't, is there any other way, tables I c

  • What do you mean its not shippi

    Ordered a few 28MB fm tx's last weekend and was promised deli'very in time for x-mas. Called Wednesday and was told that they were backordered...but then the CS rep checked with some one else who said it shipped and I should have it on Thursday. Call