Scheduling of pld. order incl. production versions

we are running production versions controlled by quote arragements. Because of the different routers in the background of the production versions we generate different InHouse production times. Currently we established the longest Inhouse prod. time as default in MM.
In some cases the basic dates of a pld. order deviate from the productions dates. I have the impression that the basic dates are driven by the InHouse production time out of the MM, the production dates are driven by the router.
My question is, is there a possibility to switch the basic dates always to the router or to synchronise them with the production dates ?

thanks for your replay,
these setting in OPU5 synchronized the basic start date. But I have still the following effect,
Scenario,
-two routers for one material number,
-router one 100 days inhouse production time,
-router two 30 days inhaouse production time.
-router one with 100 days inhouse production time, set as default in material master
-quote arrangement with 50% deployment
-demands above 30 below 100 days
Effect,
system splitts between versions acc. quota arrangement and sets all pld. orders to forward scheduling incl. the ones which have only 30 inhouse production time. Because we are starting the 30 day pld. orders to early.
Is there a way to change backswards / forwards scheduling depending on the production dates ?

Similar Messages

  • Scheduling of planned order and Production order

    Dear PP gurus,
    I have run MRP , after running MRP, system has created planned order. These planned order dates are  schedule by the system in 2015....I am not able to understand. how? . When i  double click on
    planned order order and try to convert it in production order  those dates get copied into production order.
    DO i need to change the dates thr? or  keep the same dates  which the system is giving>
    I  m going wrong somewhere. please tell me where and   what is config for scheduling for planned order and production order?
    Please tell me step by step procedure
    Regards
    Edited by: Aadi1981 on Apr 1, 2010 9:02 AM

    Thanks for replying,
    I have done the below setting for shceduling. Kindly check and let me know any setting needs ot be changed or incorect
    FOr scheduling  production order , i have configured below settings in OPU3
    In OPU3 ,  
    Detail scheduling tab
    Scheduling and  Generate cap req tab is checked.
    then
    adjust scheduling , adjust dates  tab,    :  adjust basic dates , adjust  dep , reqt to operation date  is selected
    scheduling type is backward.,
    Automatic scheduling tab is  checked.
    In OPU5
    Scheduling of PLanned order
    Scheduling and  Generate cap req box  is checked  (selected)
    Adjust scheduling
    Sheduling level: via  detail  scheduling
    adjust dates:     adjust basc dates , adjust  dep reqt , req to  operation dates
    For capacity  scheduling ;  always  basic dates, dep reqts to operation dates
    scheduling type ; backwards
    apart from this do i need to do update  ca96/ ca97?
    best Regards
    Edited by: Aadi1981 on Apr 3, 2010 7:42 AM

  • No Automatic Dispatching Of Planned Order to new Production Version

    Dear Sir,
    When rescheduling an operation from one line to another, the system
    checks whether a production version exists for the material to be
    produced that contains the new production line as the preferred work
    center. If such a production version is found, this version is taken
    over into the planned order. The planned order is scheduled again based
    on the production version.
    The second function allows you to automatically search for an
    alternative work center in the case of a capacity overload of a work
    center, and to dispatch the operations to it. The predefined
    prioritization of the alternative work centers is considered in this
    case.
    The indicator Reschedule with production version must be set in the
    strategy profile.
    My issue is sytem does not making automatic Dispatch to the second
    Production version for the material at the time of insufficient capacity
    Best Regards
    Rami Abd El Fattah Mohamed,PPQM Functional & Technical Application
    Consultant

    In the dispatching control u can remove operation date check indicator and regarding the termination indicator SAP help says"
    "if you have not set this indicator then dispatching is not terminated but carried out without taking the production version into account. That means that the planned order is scheduled with the old standard values and the formulas from the new work center and dispatched to the new line."
    Please check if it works now.
    thanks

  • How to add production Version  field in COOIS to selection options?

    Dear Experts,
    Need your suggestion for below issue raised by client.
    1) As per client, he was running COOIS with the selection option of a production version. But currently he is  not able to see this selection while executing a COOIS t-code.-----> Kindly guide me on its possibilities & necesary checks.
    2) If I want to correct it & want to add Production Version field in COOIS report what steps I should take?
    Need all your valuable guidence to resolve above issue.
    Thanks & Regards,
    Mehul

    Hello Vivek,
    Really thanks for your mail. Please see below comments-
    1) I checked the transaction COOIS & also told user to select Production Version after executing the report by giving Plant code & dates. But user asking for this field before execution.
    As per your suggestion I checked in Header level of first screen but its not showing me also.
    2)  I am using ECC6.0 version
    3) One finding from my side- This is I am checking only selecting Production Orders. But when I am selecting only Planned order then Production version can be seen in first screen under Repetitive Mfg. section.
    so kindly tell me why this not showing when Production order selected?
    Thanks in Advance for your help.
    Regards,
    Mehul

  • Planned order to production order conversion

    Hi,
    I have one requirement from  my clinet. My client want to convert the planned order into production orders through a background job. We can use the t.code:co41  to convert the pld order into production order, but CO41 program can not be executed in background.
    Is there is a way to do this in background..
    Please advice.
    Thanks and Regards
    Puruhsothaman

    Puruhsothaman,
    Yes.  Use the standard SAP program PPBICO40 in your background batch job.
    Rgds,
    DB49

  • How BOM and routing is selected for Planned order and Production order?

    Hi,
    Can any1 plz tell me how BOM and routing is selected for a planned order and production order. ?

    Hello Mathisuthan,
    BOM and Routing selection for the planned order and production order through production version, If u have more than one BOM and more than one Routing then u can maintain this information as Production Version in the system.
    Production version you maintained
    MM01/MM02 -- MRP4--- Production version
    Or you can create Production Versions in Mass also with Transaction Code "C223"
    In the case no production version maintained/created  for the material, then system by default  will pick the first BOM and routing.
    I hope this information helpful to you.
    Regards
    Umesh Mali

  • [JHS10.1.3]About production version released date

    Current JHS10.1.3 preview version cannot be used in production and we have to begin a new project now.
    It's really a dilemma in choosing which version to use.
    If possible, can we know the estimated JHS10.1.3 production released date ?
    That will help us in project time control in the future no matter which version we will use.
    Thank you.

    Eron and others,
    We are getting real close, but are not ready yet. The current schedule is to release the production version end of July, and we are very confident we will make that deadline.
    Note that we will continue to upload latest builds to the cso.oracle.com, so you can already start development with 10.1.3 Preview.
    Steven Davelaar,
    Jheadstart Team.

  • Demand Management with Production Versions

    Dear all,
    Is it possible to link the requirements in Demand Management with a production version which I've listed in the MRP 4 view?

    Hi,
    Yes it is possible. In MD61 when you place independent demands, switch to the schedule line view & specify which Production Version you want the demand to consider.
    Hope the above clarifies.
    Regards,
    Vivek

  • MRP Scheduling with a material with multiple production versions scrap rate

    Greetings all.
    I have a problem with MRP scheduling.  How do you account for different loss rates or scrap rates on a material because of multiple versions of a material that are in production.  For example, we have an item.  There are two differen ways to make that item and both have different loss rates or scrap rates.  How do we account for this.  And whatt happens when you have these with multiple routings.  Thanks.

    Dear,
    It can be handled in 3 ways.
    1st way - Create 2 versions to represent 2 ways of production. Create a 3rd version name it as total and make it as a first version so that MRP will take this version for scheduling. In total version give the most correct scrap qty and timming in routing. Hence when you run MRP system will consider the total version, then change the varsion in planned order as per your requirement.
    Second way - Create 2 version and if you are using Demand planning, in MD61 against the qty represent the version number so that when youn run MRP, the planned order will carry the version.
    3rd way - Create 2 Production version and create a quota arrangement and assihgn these two Production version as Quota items and give the % share. Hence when youn run MRP system will share the demand qty into two different version as per Quiota arrangement(setting in MRP2 is necessary fir planning).
    Please come back which one you are looking for so that we can give furthur information

  • MRP-Delivery Schedule for Sales order is not updating in Production order

    Dear Experts,
    I have created Sales order and maintained delivery scheduling, Then Run MRP through MD50,
    We received Planned order then through this we have converted to Prodcution order.
    When we observe the delivery schedule for sales order under assignment Tab in Produciton order which is showing zero instead showing line item of Delivery schedule.
    I am able to see Sales order and Line item but i am not abel to get any delivery schedule line item.
    Please suggest where settings are missing.
    Thanks in advance
    Regards
    Don

    Dear Experts,
    Please provide me solution.
    after Running MD50 transaction against Sales order.
    If I maintained different Scheduling Line Item for First Line item of Sales order.
    The Respective Scheduling Lines should update against Each Production order which has converted from Planned order.
    Thanks in advance.
    Regards
    DON

  • Change Production version during creation of Process Order COR1

    Hi,
    Scenario:
    Based on the entered Material, Plant and Order type system need to trigger a popup asking the user to select the Production Version. This should happen before clicking on SAVE button, so that all the values will be populated correctly based on the changed VERID.
    I did not find a user exit that enables to change the Production Version (VERID) value. So I thought of displaying the popup in the user exit EXIT_SAPLCOZF_003 which will be triggered before initial screen appears, export the selected value and pass it to a User Exit or BADI where VERID can be changed. But cannot find a user exit to do it.
    Please help me find a User Exit or BADI to change the Production Version during creation of Process Order using COR1 transaction before clicking on SAVE button.
    Thanks,
    Manoj.

    Hi Manoj,
    So - almost four years later - I saw your post and I saw myself in the very same situation as you did...
    I found a solution for those who wants to change the production version of the production order from the sales order creation: create an enhancement in the function module 'MD_VERSION_SELECTION' and you are good to go.

  • Production version selection based on Process order type

    Hi,
    I have the following requirement.
    A material is having two production version one is for R&D and one is for regular production. Now two process order types one for R&D and one for regular production. Now during creation of process order if we use order type of R&D then it has to select production version of R&D and if we use order type of regular productionthen it has to select production version of regular production. This selection has to be happened automatically. How this can be configured.
    Thanks
    Vinamrath.

    Dear Kumar,
    Assuming the production version selection is automatic in  the order type dependent parameters,then during order creation this
    can be automated only through validity date of the production version or else by locking the production version manually which
    should not get picked or else only through different Lot Size.
    Check and revert.
    Regards
    Mangalraj.S

  • Error creating Production Orders in UNCONSTR version

    I am copying prodcution orders from version 000 to unconstr version through Report I am getting following error.
    Error creating Production Orders in UNCONSTR version and Message no. ZSXXPAPO140.
    when I am executed in background it is giving following error.
    PPM FG100203.01_19_FR04_P for product FG100203.01 is not valid at the required explosion date 14.01.2010  /SAPAPO/RRP      325          E
    Please suggest me any one it is a great help to me.

    Hi Venkat,
    It seems there is an inconsistent PPM FG100203.01 exists
    in your planning version from which you are copying.
    Check the possibilities of repairing that PPM and retry
    copying.  Orelse In the /SAPAPO/VERCOP transaction,
    under the product selection criteria, exclude that item and
    try copying the version.
    Regards
    R. Senthil Mareeswaran.

  • Creating Production Order with wrong production version

    Hello Expert,
    please provide me answer and solution to resolve our problem regarding creation of production order (CO01 and CO41), because SAP provide and propose production version which have alternative BOM which is status 02 (inactive) already it is not picking the production version which has active alternative bom for our finished material. it is allowing the production to be created even the bom was inactive.
    please help us to this it still bugging our system
    tenx

    Hi Ryan,
    Production version will be selected based on the field Selection Method field in Material Matser MRP 4 view.
    1  Selection by explosion date
    2  Selection by production version
    3  Selection only by production version
    If the selected field value is 1 , then system selects the version based on the validity dates i.e whichever production version is active on that day that will be considered in MRP.
    If the selected field value is 2 by production version. Then system will select the First Prodution version mentioned in the Material Master MRP 4 View (production version Tab).
    If the selected field value is 3 always only by production version. Then system will select the First Prodution version mentioned in the Material Master MRP 4 View (production version Tab).
    So to address you query I suggest you to delete the production version PV1 with BOM 01 and Make production version PV2 will be available and active in seen as the first production version in teh screen.
    Then for your inof purpose you want have the PV1 then re-create it as second version in the Version tab screen.
    Regards
    radhak mk

  • Prod Version Slection during conversion of planned order to production orde

    Dear Experts,
    I have two BOM for a semi finished product. I have created two production version for the same. After MRP run, it created planned order for BOM1.  This is fine.
    My requirement is, when I convert the planned order to production order, it should ask for selection of production order as it ask while creating the production order using CO01. I know that I can select the alternate prodution version by reading the PP master data. Can system ask for selection of production order while converting the planned order to production order.
    Thanking You,
    Chetan

    Dear Chetan,
    If you have manual selection of production version set in OPL8 and if you have set the BOM selection method as 2 in
    MRP 4 view of the material master then,
    1.If you create a production order manually then the system displays the pop up to select a production version.
    2.If you are converting the planned order into a production order then it picks up the one which is
    present in the planned order.So obviously if 2 production versions are there with same lot size and
    validity dates,then the system picksup the first one only during MRP run.
    Even if it picks up the first prod.version in planned order,but while converting click on master data and
    change the production version if required.
    3.Otherwise what you can do is set the production version in MD61 itself ,so that its going to be
    considered during MRP run.
    Check out and revert back.
    Regards
    Mangalraj.S

Maybe you are looking for

  • Creating bookmarks on a page or on controls in the page?

    Is this available?  Generally I like to use the left panel as the "Pages" panel or hidden.  I find the bookmarks more of an annoyance unless I have more than a few pages (which happens much less, usually 2-6 pages tops). So, is there an easy way to a

  • Ovi Player Download Speed

    Since receiving the last Ovi player updates for my PC, it cannot download more than one song at a time even though I can create a download list of as many songs as I like. The download speed also seems to have slowed. Previously I was on ADSL1 and no

  • Adobe reader error when openning an email attachment on ipad.

    I can not open Adobe documents sent via email on my iPad since upgrading the app. This is the message: Please wait... If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this t

  • XL reporter generate in excel file cannot view in some excel 2007 version

    Dear all, Hi friend. Do you any experience before about the file generated by xl reporter cannot to view correctly in excel version 2007 in some workstation? I have a client cannot view the result file generate by XL reporter in excel version 2007. S

  • Integrate OAS Portal with E1 - WSRP Producer

    Hello, I want to integrate OAS Portal with E1. I am following: "JD Edwards EnterpriseOne Tools Release 8.98 Portal Reference Guide for All Portals and Platforms" and I have a doubt about how to register a new WSRP producer for Oracle Portal Server. I