Scheduling period in Maintenance plan

Hi
If I enter scheduling period 365 days & my cycle is 3 months.Once I schedule the maintenance plan, in IP10 I can see planned date only upto 365 days.How can I populate the planned date after crossing 365 days ?
rgds
rajib

Hello Rajib,
You are getting planned dates for one 365 days because you have entered 365 days as the scheduling period. If you want to have the same for say 5 years, then first change the unit of scheduling period to 'YR' and make scheduling period as '5'. Then schedule the plan and see the planned dates for next 5 years. Maximum you can do ti for 999 YR.
You may choose unit as Week or month also.
It is recommended to use IP19, setting With Further Dates. flag.
Hope this will help you. Please revert for any clarification.
Regards,
Vaibhav Mishra
Edited by: Mishra_Vaibhav on Apr 29, 2010 2:18 PM

Similar Messages

  • Setting Expiration period for Maintenance Plan Backups fails to work in sql server 2008

    I have created a Maintenance Plan to do a nightly full backup and set the backup
    set to expire after 4 days in sql server 2008 R2.
    Weeks later, old backups are sitting on the hard drive.Please do the needful.

    I have created a Maintenance Plan to do a nightly full backup and set the backup
    set to expire after 4 days in sql server 2008 R2.
    Weeks later, old backups are sitting on the hard drive.Please do the needful.
     Can any one please explain what is the use of BACKUP Expiration ??? 
     I created a backup with expiration date but still am using the same backup file to restore databases?? Then what is the use of Expiration date?

  • Scheduling period - IP30

    Hi All
    My scheduling period in maintenance plan is 365 days.
    I have the monthly plan.
    I am doing IP30, so that it generates 12 work orders.
    I am not indending to change anything for the next 10 years in the maintenance plan.
    My question is will the system stop generating work order after 365 days.
    If yes, should i put 10 years in scheduling period of maintenance plan to generate work orders with IP30
    or any other solution, your comments please..
    Thanks
    Jain

    Hi,
    You do not need to put 10 years in the scheduling period. The scheduling period specifies how far in advance the maintenance calls are generated. You would not normally want to create the calls for the next 10 years.
    The current setting of 365 days will ensure that every time you schedule the plan, all calls for the next year are generated. If you schedule the plan this month all calls due in next 365 days are called. If you schedule the plan in June 2012, all calls due up to June 2013 will be generated.
    -Paul

  • Problem regarding scheduling of maintenance plan

    Dear Sap Gurus,
    I am facing the problem during the scheduling of maintenancepan thruough IP10 follwing error is coming
    "Planned date for maintenance plan 124 was scheduled for 00.00.0000"
    Planned date for maintenance plan 124 was scheduled for 00.00.0000
    Message no. IP889
    Diagnosis
    During scheduling of the maintenance plan, the planned date was set to 00.00.0000.
    This error can occur, if, for example, the cycle for the planned schedule is too big (offset) means that the planned date is actually after the 31.12.9999.
    Procedure
    Check the master data of the maintenance plan to ensure that no date is calculated after the 31.12.9999.
    If necessary, check the counters used and the annual performance.
    I explore all the things in SPRO also also check the setting parameter for the plan but i didnt get any breakthrough for my above problem.Plz guide me whats the exactly problem with scheduling of of maintenance plan.
    points are sure
    Regards
    Rakesh

    Summary
    Symptom:
    In the scheduling of a multiple counter plan, the system
    1. generates message IP889 "Planned date for maintenance plan &1 was scheduled for 00.00.0000" or
    2. terminates with CONVT_NO_NUMBER.
    Other terms
    Scheduling, IP10, IP30, maintenance plan scheduling, maintenance plan, multiple counter, BADI IPRM_MCP_SCHE_CHANGE, CONVT_NO_NUMBER, SAPLIWP2, LIWP2F19, MCP_PREPARE_RESCH_CALLED_CALLS, LV_ABNUM
    Reason and Prerequisites
    This problem is caused by a program error.
    Solution:
    Implement the attached source code corrections.

  • How can we know a particular maintenance plan is stopped

    Hi All,
    Suppose a particular maintenace plan BP-P-0108 which is monthly recurring plan is created in 01/01/2008 and scheduled from 01/01/2008. Subsequesnly, the maintenace plan was stopped in 01/01/2011.How can I know this maintenance plan is stoppped from scheduling?
    Thanks
    ebenalfa

    HI Pete,
    Thanks for your response.
    I am in the process of migrating maintenance plans which has been created already in the past 10 to 12 years. During this period, many maintenance plans were cretaed and scheduled. Some of the maintenance plans might have become obsolete and need not be migrated.  The maintenance plans may not have scheduled in the near past. How can I know that these are not scheduled in the near past?
    If the user sets deletion flag or deactivate it. i may not have the scheduling happen.
    Apart from these two statuses of maintenance plan, is there any way I can identify a stopped maintenance paln schedlue ?
    If so, Which SAP table will give me the required information
    Thanks, ebenalfa

  • Counter based maintenance plan triggered improperly

    Hi,
    we have created one counter based maintenance plan with cycle unit 1000 hours  offset unit 0 hours this plan was created on 21.04.2008 . But 68 orders triggered on 19.04.2011 why it was happend.
    how find start of cycle reading  for the Maintenance plan?
    Regards
    Ganesh

    Hi,
    Counter based plan will work based on the Measuring point assigned to that.
    In Measuring Point, you would have defined the Annual Estimate. Based on the Annual Estimate & Cycle value in Plan & Scheduling period in the plan, based on all these, call object would be generated.
    Doubt in Single Cycle Performance based Plan
    Regards,
    Maheswaran.

  • Change or Add Cycles in a Maintenance Plan (IP02)

    good afternoon all,
    we have an issue with a number of maintenance plans that were setup as 1 year cycles, and now we want to run them as monthly. Is there a way to either change the yearly cycle to monthly, or add a new monthly cycle?
    SAP ECC6
    Release 731 sp level 0007.
    Thanks.

    Greetings Santosh,
    You are correct, the key word here is "approximately", as the Cycle Modification Factor has only two decimals of precision, you will need to input 0,08 to reflect the appropriate factor of 1/12=0,08(3) - so that will mean your cycle is 360*0,08=28,8 and not 30 days, which is why I did not propose this route. But if it's not an issue, then yes, that's another way to do this
    EDIT: Which reminds me, after switching the cycle to monthly, consider if you require Time or Key Date scheduling on the Maintenance Plan scheduling parameters, as for SAP 1 Month = 30 Days with the former, but with the latter the scheduling is always for the same day of each month.

  • Scheduling Period  mandatory in maintenance plan  PM module

    Dear Friends,
    Please let me know,how scheduling period,maintenance activity categroy can be made  mandatory in maintenance plans.
    Thanxs in advance
    Jyotish Kumar
    9810170091

    hi
    upto my knowledge i think it is not possible to have your fields mandatory in maintenance plan,you think of using Tcode SHD0 which is used for Transaction and screen variants
    regards
    thyagarajan

  • Maintenance Planning & Scheduling of calibration order

    Hi
    I have to schedule calibration inspection of a few equipments in such a way that system automatically create inspection lot & calibration order daily.
    Whether user enter calibration result or not, inspection lots in future should be created automaticallly.
    I created a single cycle plan using IP41 and start the schedule using IP10, the system created first inspection lot automaticaly but always require me go to to scheduling and save the plan again if I want to create next inspection lots. How can I configure/set the system in such a way that it creates inspection lots/calibration order automaticaly
    Plz also tell after taking usage decision of inspection lot whether I need to do some act on calibration order such as technical completion or business completion.
    Thanks in advance

    Dear Chris,
             In maintenance plan go to Maintenance plan scheduling parameter & put Schedule Period '360' Days in sub screen under Call control parameter.
    Then Go to IP10and make automatically scheduling it will make plan for whole yera.
    Regards... Rakesh Saxena

  • Certain Maintenance Plan not getting scheduled in the background job

    Hi Gurus,
    I am facing an issue here.
    A weekly background job (RISTRA20) runs every weekend and schedules the maintenance plans.
    But we have noticed that some maintenance plans are not getting scheduled. i.e no orders or schedule is getting generated.
    When I run IP30 manually for these plans then the schedule gets generated and orders get called.
    I have checked up the background job and it is running fine.
    Also, i have noticed a similarity in all these plans which are not getting scheduled. There schedule has been restarted (through IP10) at somepoint or the other.
    But i don't see any direct impact of this?
    Can any of you provide some help on this?? Points will be rewarded.
    Thanks and regards,
    Nitin Saini

    Hi Narender,
    Thanks for replying.
    The message number for 'Groups don't match' is ME303.
    I think this does not have anything to do with the restart as i have done further investigation.
    Whenever I run IP30 with sortfield input as AS02*, i get the error as mentioned above for a certain number of maintenance plans while the remaining plans get scheduled.
    If i run IP30 for any other sort fields, it runs fine and i don't encounter the error
    mentioned above.
    If you send me ur email address, i could forward you screen-shots of the issue.

  • BAPI for Maintenance Plan Scheduling with EHP5

    Hello.
    In documentation for LOG_EAM_CI_4 mentioned that: [API functions have been developed for the scheduling of maintenance plans. These APIs provide the same functions as transaction IP10: the creation of maintenance calls or the changing of existing maintenance calls|http://help.sap.com/erp2005_ehp_05/helpdata/EN/33/46AC67364447A3BA2F4EFA65B8C014/frameset.htm].
    We have activated EHP5 and all LOG_EAM_CI* business functions in our system, but still can't find this "magic" BAPI.
    Does anybody know its name?
    BR,
    Pavel
    Edited by: Pavel Nedvijaev on Nov 7, 2011 5:37 PM

    Maheswaran.K thanks for your reply, but as i wrote above we have activated all LOG_EAM_CI* including LOG_EAM_CI_3.
    Version of software components SAP_APPL, EA-APPL is 605 as it needed.

  • Update was terminated error while scheduling maintenance plan

    HI Friends,
    I created a maintenance plan.I scheduled the order and i saved.
    Now when i tried to see the schedule i am getting a message
    "Update was terminated"
    the detailed error is
    Update was terminated
    System ID....   DEV
    Client.......   XXX
    User.....   XXXXX
    Transaction..   IP10
    Update key...   49041E2C02935CCCE10000000AFA0209
    Generated....   30.10.2008, 17:22:18
    Completed....   30.10.2008, 17:22:19
    Error Info...   00 671: ABAP/4 processor: SAPSQL_ARRAY_INSERT_DUPREC
    Can anyone tell me why this error is coming and how to rectify.
    Thanks in advance
    Vivek
    Edited by: vivek mankad on Oct 30, 2008 1:38 PM

    Vivek,
    Talk to your ABAP/Basis team
    PeteA

  • Get latest order for a scheduled maintenance plan

    Hi experts,
    I have a requirement where i have to get the order id for a scheduled Maintenance plan.My scenario is explained as below:
    A maintenace plan is scheduled and as a result of it an order will be created automatically  by system. Now i have to write a Report program which will be running daily and this report has to pick only those order which are NOT complete and these order will come from the above scheduled maintenance plan.
    Therefore i have to pick incomplete order based on scheduled maintenance plan.Any idea how to achieve this requirement?
    In case of any doubt please let me know.
    Regards,
    Abhishek

    Thanks for reply. But my requirement is a bit differen.
    I need a BAPI which can take Maintenance Plan as input and it can return the latest created incomplete order which is created due to scheduling of Maintenance Plan.
    Regards,
    Abhishek

  • FM to find out schedule calls and their statuses for a Maintenance plan

    Hi,
    Please let me know if there is any FM to find out all schedule calls and their statuses for a Maintenance plan.
    Regards,
    Vimal

    Hi Vimal
    Below function module will serve your purpose.
    ZPM_GET_SCHEDULING_STATUS
    Regards
    Anil Kumar

  • Mass Re-start / Re-schedule of Maintenance Plan

    Dear Sirs,
    I have created a BDC which runs in the background at the end of every month.
    This BDC creates a Strategy Maintenance Plan (IP42), the moment a new equipment is installed in the system & it automatically gets scheduled (IP10) as per the installed date.
    After a while we came to know that the BDC was not taking the proper start cycle date & hence the Maintenance Plans which were created were scheduled on the wrong date. We have already solved the problem & have corrected the coding.
    But we need to re-schedule all the earlier wrongly scheduled maintenance plans & delete the previous history.
    When we tried to re-start the cycle manually through IP10 it was allowing us to delete the earlier records as well as to re-start the cycle.
    But as there were thousands of Maintenance plan to be re-started, we planned to create a LSMW or BDC to do the same.
    But while running the LSMW / BDC recording we are not able to delete the earlier records & those are showing as skipped.
    We want the earlier records to be deleted & to re-start the new cycle.
    Can you please tell me something that can be done through any std transaction like IP30 etc.
    Regards,
    YVK.
    Edited by: Yogesh Khamkar on Mar 5, 2010 1:13 PM

    Hi Goswami,
    I am facing the same problem while creating recording for restarting scheduling maintenance plan in IP10 with  LSMW , I am not getting the option screen as given below to delete or skip the call
    as result I am not getting any field in  " Maintain Field mapping and conversion rule"
    Please help me for same. As I have scheduled 1000s of plan one month ago but client need to reshedule all with new start of cycle.
    regards,
    Raj

Maybe you are looking for