Scheduling Process Order

Hi
Iam using collective  process order with one subordinate order.
All Phases are having relationship. First phase 0011 has predecessor 0888
When i reschedule header order individually then schedule dates and basic dates of header order changes in increasing order with each rescheduling of header order individually.  Iam using floats before and after production.
This happens while rescheduling  header order individually and does not happen with subordinate order.
But when i add dummy  start operation and phase  without any resource then system does not change  schedule dates and basic dates of header order changes in increasing order after rescheduling header order individually. 
Is this standard behavior or Bug?
Please could you check in your system and let me know reason.

Hi Mayuresh,
Please check your Master recipe activity hours, the system calculates the scheduling dates based on it and OMDW transaction-for rescheduling horizon,tolerance value forward/for displacement.
Best Regards,
Sriramm

Similar Messages

  • Sched.start date not allowing on week-ends for fwd scheduling process order

    Hello Experts,
    For a process order & scheduling typr forward/in time if I take sat or sunday as a start date then if I click on schedule, system changes it to previous workin day (friday). But however if i select backward/in time scheduling type & put week ends as finish day then system does not change this date.
    How can I make system to allow schedule start date on week ends also for forward/in time scheduling type. in a factory calendor sat & sunday are holidays. while for work center, calender sat & sunday are marked as working days.
    Thanks for advance,
    Vijay.

    Hi
    it depends upon client requirement.you must have defined the holiday calender as well.if you select the public holidays in your factory calender.then system will allow you to do your daily transctions on public holidays as well and vice versa.so better go with all options selected .and plz check at your end
    plz revert back if it works
    Regards
    Anupam Sharma

  • Problem: Scheduling Process Orders.

    Hi,
    I have a problem in PPPI with scheduling in Master recipe and with the process order in CM25. Can you help me?
    In Master Recipe:
    I create a capacity category 0025 to display for a resource the setup formula and Processing formula in the Scheduling Tab (as the capacity category 0001 - I also tried to let the capacity category 0001 be used in application C - Master recipe and didn´t work).
    In OP40, I created and assigned in applications to C Recipes
    Afterwards, I ordered the views in OP13.
    When im creating a resource, i prove the formula and i have no problem. But when I assigned it to the recipe and the recipe to the production version to make a process order, neither the master recipe or process order schedules the order.
    When I create a resource with a capacity category 0008 (standard) the scheduling works just fine in the process order.
    Scheduling in CM25:
    Also when Im trying to schedule the order in CM25, I see two lines of the same order (i guess are the 2 phases 0010 and 0020), is there anyway to just see the second to avoid misunderstanding?
    Thanks in advance!
    AM

    Dear,
    For FIFO you can use the Characteristic  LOBM_LFDAT for FIFO if is LOBM_VFDAT then in plant storage data 1 view maintain the SELD then assign these Characteristic to class in CL02 then assign this calss to material master.
    Then craete sort rule in CU70 withCharacteristic  LOBM_LFDAT or LOBM_VFDAT
    then assign it to serch strategy in MBC1 or COB1 with selction criatoria.
    In OPL8 assign this serch procedure.
    Then create the order and check the result.
    Regards,
    R.Brahmankar

  • Scheduled Process Order

    Hi All,
    I am a BW guy. In one of my BW reports I need to count the quantity of order units scheduled.
    This is what I am doing:
    Scheduled order = Order for which "Technical completion date" (AUFK-IDAT2) = Blank or 00/00/0000
    Order quantity = Total order quantity (Item quantity, AFPO-PSMNG) Minus Delivered quantity (GR qty, AFPO-WEMNG)
    Please let me know if this is correct. Also please correct me if I am wrong.
    The most informative answer will be rewarded with the highest points!
    Thank you

    Hi Satyajith,
    I would like to calculate the order quantity for all "scheduled orders" (i.e. orders that have not been completed yet)
    First I need to identify what orders are scheduled orders (How do I do that?). Then for those orders, I need to calculate the order quantity.
    So going back to your question, it would be the quantity of units to be produced. I am trying to calculate this like the way I wrote in my first post. Am I doing it the right way? Please correct me if I am wrong.
    Again, my primary question is, how do I know whether an order is scheduled and not completed? Is an order for which technical completion date (AUFK-IDAT2) = Blank or 00/00/0000 a scheduled order?
    Thanks for your reply.

  • Process order scheduling based on in-house production time.

    Hello!
    I have following problem. My SAP system is configured in that way that process oedrs are schedulled based on times saved in master recipies. When I input data to in-house production time in master data for materials and make new process order, this time is not
    taken into account.
    Where I have to change configuration to use in-house production time from material master data to make scheduling process orders.
    Regards
    Bogdan

    Dear
    Process Order /Production Order scheduling ( Lead Time Scheduling )  based on the Operation timings in the routing not based on the Material Master In house Production Time in Work Scheduling View .
    If you are loking for Basic Date Scheduling then it will happend based on material master , scheduling margin key  at material master level .
    It depends the selection of Schedueling indicator while excetion of MRP in MD02 .
    In case of Process order specifically , you need  to schedule the Master Recipe and check whether operations are getting scheduled, if it is not then you need to first the problem, which may be because of wrong "Forumla" or paramater assigned in resource or the resource is not maintained for Finite scheduling (capacity header).
    Master reciepe can be schedule in the change transaction C202, and from menu you would find the option to schedule the recipe .
    Also  check the OPU3/OPU5-Define scheduling parametres wether scheuling , adjust scheduling , scheuling type , logs all are in place .
    Check and revert
    Regards
    JH

  • Process Order Scheduling dates.........

    Hi there,
                 For the process order where we can do the configuarion in SPRO so that the opreation starts on the basis of earlier dates or the latest dates...
    Thanks
    Kaushik

    Using OPUZ transaction you can Specify Scheduling parameters to operations in the Process Orders.
    Use the following path via SPRO
    Production Planning for Process Industries --> Process Order --> Operations -->Scheduling --> Specify Scheduling Parameters
    Specify Scheduling Parameters
        In this step you define the parameters for scheduling process orders for
        each plant, order type and production scheduler. It comprises
        maintenance of
        o   scheduling levels (detailed-, production-rate and rough-cut
            scheduling)
        o   date adjustment when deadlines are exceeded
        o   scheduling control for detailed scheduling
        o   reduction
    Hope this helps you.

  • How does the GR processing time affect the scheduling of the process order & the latest start date in the operation.

    Hi
    Can anyone explain  how does the GR processing time affect the scheduling of the process order & the latest start date in the operation overview.

    Hi
    GR processing time means number of workdays required after receiving the material in storage.
    Check this link:GR Processing time
    Regards,
    Anupam Sharma

  • Scheduling Time in process order

    Dear All
    While creating process order system is not picking scheduling time as per maintained in recipe because of this capacity is not being load on WC & showing zero reqmnt. Whreas date are properly calculating as per inhouse time maintained. In OPUZ i had ticked both scheduling & capacity reqmnt.
    In resource i had maintained all parameter in capacity & capacity is showing as 24 Hr. Scheduling & Capacity fromula had aslo maintain. Wht could be other reason for nt calculating time as per recipe.
    Thanks & regards

    Rashid,
    So is the dates getting populated correctly after scheduing function? If so then probably you current system design it to perform scheduling manually. You can use the "Production Scheduling profile" to perform this automatically. You need to assign a production scheduling profile defined for automatic Scheduling at the creation stage to you materil master "Work Scheduling" view
    Regards,
    Prasobh

  • Scheduling in Process order

    Dear All
    While creating process order system is not picking scheduling time & date as per maintained in recipe after clicking scheduling tab, because of this capacity is not being load on WC & showing zero reqmnt.
    When i checked scheduling at recipe level there also it is happening.
    In OPUZ i had ticked both scheduling & capacity reqmnt.
    In resource i had maintained all parameter in capacity & capacity is showing as 24 Hr. Scheduling & Capacity fromula had aslo maintain. Finite scheduling is ticked.The control key assigned to the phase, is also defined with "Scheduling and Capacity requirments".
    Wht could be other reason for nt calculating time & date as per recipe.
    Thanks & regards
    Abhijit Gautam

    Hi,
    Refer below thread,
    [Thread |No reqmt/capacity exist or not relevnt for finite scheduling: Mesage: CY298;
    Regards,
    Dhaval

  • Process Order Basic Finish Date and Scheduled Finish Date

    Folks,
    I have a requirement from the business to be able to update the Process Order Basic Finish Date and Scheduled Finish Date independently from each other.
    In other words, update the Basic Finish Date and the Scheduled Finish Date cannot change or update the Scheduled Finish Date and the Basic Finish Date cannot change.
    I believe the reason for this is to be able to use the Basic Date to maintain the ATP accurately and keep the Scheduled Date to mark when the order was originally due from the shop floor to be able to measure if orders are being completed on time or late.
    I have worked in tnx OPUZ and had some success with other issues with these dates but I can't seem to make them work independently from each other.
    Or does anyone have any ideas how to measure proces order performance to the production schedule?
    Thank you for your help,
    Greg

    Rajesha, thank you for your reply but it doesn't solve my problem.
    Let me restate my scenario:
    I start a process order and both the basic and scheduled finish dates are the same, June 1.
    At some point, shop floor tells me they will be late and cannot deliver until June 15.
    I need to update a date in the system so the ATP and the MRP planning runs have correct information for promising customers, I will update the Basic Finish date with June 15.
    I also need to keep the original June 1 date in order to measure the shop floor performance to the production schedule to measure how early or late the  order was delivered. How can I keep the original finish date or how can I measure if a process order is early or late??
    Thank you for your help,
    Greg

  • Manual scheduling phases in Process order

    Hello dears,
    a question came out to my business during Process order (PP-PI module) testing.
    When a order is created, the system uses master recipe data to schedule each phase, and to assign them a start and finish time. These values are displaied in the process order for each phase.
    The question is: is it possible to change them manually, in case I need to reschedule only a specific phase and not the whole order? Because currently I see that dates fields are not editable in COR2.
    Thanks a lot.
    Kind regards,
    Giovanni

    Dear ,
    You ca not  able to manually chanes  the date and time unless they are Dispatched  after capacity evalution  or leveling at the Resource level.
    Generally , if your resource is having finite scheduling active and you have CRP planning is in place , then you need to goto CM07/CM05 to check the Overload/Availablit of the resouce in a certain date n time so that you can re-scheule them manually from CM21/CM22/CM23 .
    To meet this requirement , you have to adop Capacity Requirement Planning set up .
    Check our earlier posting  on the similar issue : Capacity Planning not considering plnd order
    Capacity requirements generation at phase level only
    Regards
    JH
    Edited by: Jiaul Haque on Dec 8, 2010 9:30 AM

  • Problem  with Process Order Scheduling..

    Dear Experts,
    i'm stucking with the scheduling of a process oreder.
    I've maintained all scheduling parameters into OPUZ except "selection ID" for detailed scheduling as it is grey & not allowing to fill any entry into it.
    I've also maintained production scheduler and other relevant settings into master recipe & resource regarding scheduling .
    Still i'm getting the error"Scheduling parameters for process orders have not been entered" message no CT609.
    Kindly help me out , where i'm wrong
    Thanx in advance...

    Dear Dennis,
    Ensure the scheduling parameters in OPUZ for the order type,plant combination and for all (* )scheduler you have maintainied
    the scheduling type,the check box for scheduling and generate capacity requirements under detailed scheduling is set.
    Check and revert back.
    Regards
    Mangalraj.S

  • Scheduled finish date for process orders not updating in BW

    We are having problems with the scheduled finish date (GLTRS) for process orders. When the process order is already released, changes done in R/3 on the scheduled finish date will not result to a delta hence data in BW is not updated. Table AFKO, where data is coming from, is always updated with the changes though. 2LIS_04_P_MATNR is used in extracting the data.
    Has anyone experienced the same problem? We are looking for possible ways on how to have a delta whenever there are changes on the process order even after it is already released.
    Any help would be greatly appreciated...

    Hi Donna,
    If I've understood your problem correctly, you can increase the load frequency as Sriee has pointed out.
    If you want latest data frequently and if you are on BI 7.0 then you can look at Real Time Data Acquisition(RDA)
    Regards,
    Tom.

  • Process Order Schedule Finish date before Schedule Start date

    On rare occasions, the process order Schedule Finish date is before the Schedule Start date.  This causes an error on the APO system when the process order is CIF to APO.  Does anyone have any ideas how this occur?
    Thanks.
    Best regards,
    Sandy

    Rajesha, thank you for your reply but it doesn't solve my problem.
    Let me restate my scenario:
    I start a process order and both the basic and scheduled finish dates are the same, June 1.
    At some point, shop floor tells me they will be late and cannot deliver until June 15.
    I need to update a date in the system so the ATP and the MRP planning runs have correct information for promising customers, I will update the Basic Finish date with June 15.
    I also need to keep the original June 1 date in order to measure the shop floor performance to the production schedule to measure how early or late the  order was delivered. How can I keep the original finish date or how can I measure if a process order is early or late??
    Thank you for your help,
    Greg

  • Scheduling of Process order

    Can somebody explain me as to how the scheduling of Process order is carried out?
    i mean in case of forward scheduling when i enter the start date, the system calculates the finish date. How?
    Thanks

    Dear
    Can u Please Check in OPU3 And OPU5
    With Regards
    Pushpalas

Maybe you are looking for